Forwards IE Insp Rept 50-397/80-17 on 801007-10.No Noncompliance Noted
ML19345C273
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/29/1980
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Ferguson R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML19345C274 List:
References
NUDOCS 8012040305
Download: ML19345C273 (2)


See also: IR 05000397/1980017

Text

-

7/C

.

-[

o

UNITED STATES

3

8

1.

NUCLEAR REGULATORY COMMISSION

i

i

. REGION V

o,

1990 N. CALIFORNIA BOULEVARD

%

d'4

'

SUITE 202, WALNUT CREEK PLAZA

4g,,*

WALNUT CREEK, CALIFORNIA 94596

O

Docket No. 50-397

3

k

'

.

h

is

i

s[E:ii

Mh

Dd

Washington Public Power Supply System

9 @1

3

gg

P. O. Box 968

Richland, Washington

y

g

3s

b

iG

V

Attention: Mr. R. L. Ferguson

Managing Director

Gentlemen:

Subject: NRC Inspection at Washington Nuclear Project No. 2

This refers to the inspection conducted by Messrs. D. P. Haist, W. J. Wagner

and A. J. D'Angelo of this office on October 7-10, 1980 of activities authorized

by NRC Construction Permit No. CPPR-93, and to the discussion of our findings

with Mr. W. C. Bibb and other memoers of your staff at the _ conclusion of

the inspection.

Areas examined during this inspection are described in the enclosed inspection

report. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and

observations by the inspector.

No items of noncompliance with fiRC requirements were identified within the

scope of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you believe to be proprietary, it is

necessary that you submit a written application to this office, within 20 days

of the date of this letter, requesting that such information be withheld from

public disclosure. The application must include a full statement of the

reasons why it is claimed that the infonnation is proprietary. The application

should be prepared so that any proprietary information identified is contained

in an enclosure to the application, since the application without the enclosure

will also be placed in the Public Document Room.

If we do not hear from you

in this regard within the specified period, the report will be placed in

the Public Document Room.

8012040 365

.

Js0

Mr. R. L. Ferguson

-2-

-

Should you have any questions concerning this inspection, we will be glad

to discuss them with you.

Sincerely,

I

0 -~T _ _ _ -

- -

,rg G. S. Spend r, C$ ef

'i

Reactor Construction and Engineering

Support Branch

Enclosure:

IE Inscection Report

flo. 50-397/80-17

.

cc w/o enclosure:

M. E. Witherspoon, Division Manager

Quality Assurance, WPPSS

W. C. Bibb, ianager

WitP-2 Project