Text
'
y. /
. [%/1
k
~
UNITED STATES
,
- "Y
7
,
NUCLEAR REGULATORY COMMISSION
3
{'3,
E
REGION 11
15
~,
t
n
c.
,,
q
,
.
p 4
101 MARIETTA sT., N.W.. sulTE 3100 '
"
'33
'
$
ATLANTA, G EoRGIA 30303
'3
.
d
4
.....
In Reply Refer To:
0CT 0 91980
-
u,
y
3
=.
RII:MDH _
'
9
x
50-424/80-12
)
g
4
,
Q0-35/10_-12 /
_
Georgia Power Company
ATTN:
J. H. Miller, Jr.
Executive Vice President
270 Peachtree Street
Atlanta, GA 30303
Gentlemen:
This refers to the inspection conducted by M. D. Hunt of this office on
September 9-11,
1980, of activities authorized by NRC Construction Permit
Nos. CPPR-108 and CPPR-109 for the Vogtle facility, and to the discussion of our
findings held with K- M. Gillespie at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Within the scope of this inst ection, no items of noncompliance were disclosed.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,
Title 10, Code of Federal Regulations,
a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20 days
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasons on the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate parc of the document. If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
i
4
'
C. E. Murp
, Chi
Reactor Construction and Engineering
I
Support Branch
l
j
Enclosure:
(See Page 2)
!
.
8911seO N
Q
L
_ _ . _ _ _ . . . . _
_ _ . _ - . . . _ . . _ _ _ _ _ _ .
_ . . . .
J
!
.
Georgia Power Company
-2-
OCT o 31880
..
.
Enclosure:
Inspection Report Nos. 50-424/80-12
and 50-425/80-12
cc w/ encl:
K. M. Gillespie, Construction
-Project Manager
E. D. Groover, QA Site Supervisor
D. E. Dutton, Proje et General Manager
.)