ML19344A110

From kanterella
Jump to navigation Jump to search
Testimony of Fs Echols Re Environ Impact of Continued Plant Const During 1977 & Environ Review Schedule
ML19344A110
Person / Time
Site: Midland
Issue date: 11/05/1976
From: Echols F
Office of Nuclear Reactor Regulation
To:
Shared Package
ML19344A106 List:
References
NUDOCS 8007310614
Download: ML19344A110 (2)


Text

..

.-g.-

'O.

i I

UNITED STATES OF AMERICA

.NU, CLEAR REGULATORY COMMISSION BEFORE'THE ATOMIC SAFETY 'AND LICENSING BOARD r

In the Matter of'

-CONSUMERS POWER COMPANY Docket-Nos.

50-329~

50-330 (Midland Plant, Units' 1 and 2)

NRC STAFF TESTIMONY OF-F. S. ECHOLS ON THE ENVIRONMENTAL. IMPACT OF CONTINUED PLANT CONSTRUCTION DURING THE NEXT YEAR AND ENVIRONMENTAL REVIEW SCHEDULE ~

'Having-both visited the site on October 20, 1976 and_ discussed construc-tion practices' and schedules with NRC personnel from Inspection &-

Enforcement as,well as personnel from Consumers Power Company, I conclude that although the Midland Plant, Unit Nos.1 and 2 are less than 20 percent complete, virtually all impacts upon the environment, due to construction, have occurred. The cooling pond has been construct-ed and the last remaining riprap-is being placed on the slopes; equipment lay down areas are conpleted and in use; the sewage pipe line to Dow Chemical is'nearly complete as is the water pipe line from Midland; the rail line~ is complete; county drains'have been relocated; the preparation.of the river shoreline for the intake structure is nearly e

complete:and ~ riprap-is in place, dredging has been completed; water runoff: control; practices are in effect; all spoil material is being f

used on-site.for' dike' construction and diversion 'of surface runoff; grass seeding of. banks has been done and is to be repeated if a washout occurs; the' batch plant is in operation with stack-filters in use; road watering is.used when.needed. to' reduce ' road dust; screening. techniques

.have been employed.to_ reduce visual impacts to nearby residents.

~

8co7sioj]g-k rr=

g M

w p'y4 99-w-ar W -

y Mw-q 4-e-

m-

-V p-p e

m e

en W ew

-y'i-9--

'~

~c -

Construction activity for the.next year will be in the immediate-

. area of the reactor complex.where land has already-been completely altered and control procedures employed.- Such activity 1.icludes concrete placement and earthwork,- such as grading, excavation and backfilling. The environmental impacts-due to construction expected during the next year.are the normal traffic and noise associated with:the project.

Virtually all impacts fto the environment as a-result of construction have occurred. 'No significant adverse impacts upon the environment are expected to occur in the next year due to construction'of the Midland Plant, Unit Nos.1 and 2.

~

Environmental Review Schedule for Midland Plant, Units 1 and 2 The-Staff believes that a ten' month schedule, from November 1,1976,-

will be required for the remanded environmental review of the Midland

~ project.

It should be 'noted that portions of the. schedule are fixed '

by 10 CFR Part 51, e.g., 45 day comment period after CEQ Federal-Register Notice is published, and a minimum of 30 days between issuance of FES and beginning of hearing. The'projectedLreview schedule is as follows :

November 1,1976-Begin review January 15, 1977 Issue DES e

January 21, 1977 CEQ Federal Register Notice March 7, ~1977 End Comment Period April 29,1977:

Issue FES June 1, 1977 Hearing begins.

August 1,1977 Proposed Findings LSeptembergi, 1977.

ASLB Decision l'

s r

~

' [.

(- -

,,1

~,. -,

,