L f/
f
- %ey%,
UNITED STATES y
g NUCLEAR REGULATORY COMMISSION i
.r wasmNGTON, D. C. 20655 2
o
\\..... /
March 25,1981 Docket No. 50-10 LS05-81-03-059 e eEC[f( n Mr. J. S. Abel
/ lpg k6 Director of Nuclear Licensing
'9 u,, h "ee% **/Sg7A Q
Commonwealth Edison Company
\\ g' 4 Post Office Box 767 P
Chicago, Illinois 60690
Dear Mr. Abel:
ro Our initial Safety Evaluation Report (SER), dealing with fire protection at Dresden Unit No. 1, was issued on August 9, 1979.
In Section 3 of the SER, nineteen items were identified as incomplete and requiring further information from the licensee and evaluation by the staff.
We have completed our review of information dealing with these incomplete items as provided by Comonwealth Edison Company (CECO) responses dated August 2, August 31, and December 4,1979, April 9,1980, and February ll, 1981.
The results of our review were described in NRC's July 9, 1980, November 24, 1980, and February 10, 1981 letters'which identified completed items acceptable to the staff and unresolved items which required further CECO action to satisfy NRC requirements.
Subsequent to the transmittal of our letters, the staff has concluded that several items previously listed as requirements have been satisfactorily resolved by subsequent licensee action. Enclosure 1 provides the staff's evaluation of these items. Enclosure 2 provides a listing of the current status of all items identified by the staff as requiring CECO action during the fire protection review.
Sin erely, y1 0 nnis.M. Crutchfie d, Chi' Operating Reactors Branch #5 Division of Licensing
Enclosures:
As stated above
.cc w/ enclosures:
See next page 810.4 0,9 0//f 7 f
1 i
l Mr. J. S. Abel March 25,1981 i
l cc w/ enclosures:
l Isham, Lincoln & Beale Director, Criteria and Standads Counselors at Law Division One First National Plaza, 42nd Floor Office of Radiation Prograss Chicago, Illinois 60603 (ANR-460) j U. S. Environmental Protection Mr. B. B. Stephenson Agenqy Plant Superintendent Washington, D.C.
20460 i
Dresden Nuclear Power Station Rural Route il U. S. Environmental Protection Morris, Illinois 60450 Agency Federal Activities Branch U. S. Nuclear Regulatory Commission Region V Office Resident Inspectors Office ATTN: EIS C0ORDINATOR Dresden Staticn 230 S'outh Dearborn Street RR #1 Chicago, Illinois 60604 Morris, Illinois 60450 Resident Inspector Susan N. Sekuler Dresden Nuclear Power Station Assistant Attorney General c.o U. S. NRC Environmental Control Division Rural Route il 188 W. Randolph Street Morris, Illinois 60450 Suite 2315 Chicago, Illinois 60601 Morris Public Library i
604 Liberty Street Morris, Illinois 60451 Chai rman Board of Supervisors of Grundy County Grundy County Courthouse Morris, Illinois 60450 Department of Public Health ATTN: Chief Division of Nuclear Safety 535 West Jefferson Springfield, Illinois 62761 1
l l
0 1