Significant Deficiency Rept 369-370/80-02 Re Steam Generator narrow-range Level Transmitter Cable Failure to Meet Environ Qualification Requirements.Cable in Unit 1 for Steam Generator Level Transmitters Replaced in Aug 1980
ML19343C507
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 03/17/1981
From: Parker W
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8103240396
Download: ML19343C507 (2)


Text

.

DUKE Powun COMPANY Powna Butt.ntxo 422 SocTn Cucacu STazzT CHARI.OTTE, N. C 20242 wi we. o. a^ a a c a. s a.

March 17, 1981 WCE PettictNT it.ta=CMt; Ae ta 704 Secame PeoovetioM 371-4083 Mr. James P. O'Reilly, Director c$i' U. S. Nuclear Regulatory Commission k

Region II

y%

/Q' bl(lU 101 Marietta Street, Suite 3100

&l' V l }

M.

'I'-

Atlanta, Georgia 30303 I7 MAR 2 31981 * '

s v.s. g 8j y '

  • Re: McGuire Nuclear Station

%j)>.

Units 1 and 2 Docket Nos. 50-369 and 50-370 N,

Dear Mr. O'Reilly:

Per Mr. T. D. Gibbons request in IE Inspection Report 50-369/81-04, 50-370/81-01 please find attached an amended Significant Deficiency Report SD 360-370/80-02.

Very truly yours, h61/20n 0- lM h 6 lK

. William O. Parker, Jr.

/

RWO:ses

. Attachment cc: Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 S

I(

81082.4039(o s

. / ' #

DUKE POWER COMPANY MCGUIRE NUCLEAR STATION UNITS 1 & 2

' Report Number:

SD-369-370/80-02 Report Date: March 17, 1981 Facility: McGuire Nuclear Station - Units 1 and 2

. Description of Deficiency:

During review of environmental qualification documentation for safety-related i

electrical equipment, it was determined that the steam generator narrow-range level transmitter cables did not meet the environmental qualification require-ments. These cables had been certified for 30 days of post-accident condi-t

-tions instead of the required 120_ days. Sixteen cables in Unit No. I contain-ment are' involved. The cables for Unit No. 2 have not been installed.

- Analysis of Safety Imolication:

~

The cable. cercification does not provide adequate assurance that the cables would function properly for the required 120 days in a post-accident environ-ment.

Corrective Action:

The cable in Unit'No. 1-for steam generator level transmitters was replaced

- in August 1980 with new cable having sufficient qualification documentation.

The new cable with a; unique cable identification will also be installed in Unit No. 2 during the normal construction process.

Since the new cable conductor insulation diameter is smaller than the grommet openings in ;the electrical penetration connectors, pigtails of qualified single conductors'with a larger diameter are used to make the' transition between the

{

new cable and the electric penetration connectors. The conductors are spliced j

in the electric penetration-junction boxes using Raychem WCSF-N splices-following 1

.the guidelines:of an existing field installation specification.

4 4