O Appendix A NOTICE OF VIOLATION Union Electric Company Docket No. 50-483 As a result of the inspection conducted on November 3-7 and 12-14, 1980, and in accordance with the Interim Enforcement Policy, 45 FR 66754 (October 7, 1980) the following violations were identified:
1.
10 CFR 50, Appendix B, Criterion XVI, stated in part, " Measures shall be established to assure that... defective material and equipment and nonconformances are promptly identified and corrected.
In the case of significant conditions adverse to quality, the measures shall assure that the cause of the condition is determined and corrective action taken to preclude repetition."
Contrary to the above, inadequate corrective action was taken in the following instances:
a.
Surveillance report 9/79-12 dated September 25, 1979, was closed on November 12, 1980, even though two questions raised in the surveillance report requesting guidance on acceptance-criteria frer measuring defects remained unanswered.
b.
In the " Corrective action to preclude repetition" column on NCR 2 SN-1141-E, "No Daniel action required" was entered even though Daniel performs functions such as site procurement, receipt inspection and installation inspections which could preclude repetition of identified problem.
c.
In the " Corrective action to preclude repetition column" on NCR 25N-2236-E dated July 28, 1980, "No Daniel action required" was entered precluding Daniel inspecting other switchgear to ascertain whether " Suitable flexible wiring" was used over door 4
hinges where leads may be subjected to flexing.
d.
Even though, a deficiency report dated September 11, 1979, documented that nitrogen pressure was being lost on electrical penetration assembly No. 0712, followed by loss of nitrogen pressure in several other electrical penetrations, corrective action was not taken in a timely manner to replace the identified
. defective valves to assure a dry environment.
This is a Severity Level V violation (Supplement II).
iB102270% A 4
Appendix A 2.
10 CFR 50, Appendix B, Criterion VII, stated in part, " Measures shall be established to assure that purchased mate:ial, equipment and services whether purchased directly or through contractors and subcontractors, conform to procurement documents. These measures shall include provisions as appropriate, for... examination of products upon delivery. Documentary evidence that the material and equipment conform to the procurement requirements shall be available at the nuclear power plant or fuel reprocessing plant site prior to instal-lation or use of such material or equipment."
The following examples were contrary, to the above:
Written receipt inspection requirements with specific acceptance a.
criteria were not established to receipt inspect unistruts for potential " Forming Tears" defects.
The licensee stated that receipt inspections were performed without the benefit of specific written procedures.
Prior t'o the conclusion of the inspection, Receiving Instructions File No. B12.01 dated November 14, 1980, was developed.
b.
Certificates of compliance from GE which merely. stated "All materials used in this shipment as called for in the above Purchase Order have been processed by GE-PSMBD comply with ANSI product performance specification requirements" were accepted for the relays supplied; these certificates did not explicitly state that the relays met the requirements of ANSI C-37.90/1971,
. and therefore, did not meet the minimum requirements of para-graph 10.2.1 of ANSI 45.2.13.
c.
Documentation that the following tests, prescribed in Specification E-051(Q), were performed on the battery chargers was not available at site:
(1) Temperature raise test 1
(2) Short circuit test (3) Effeciency test (4) Transient voltage withstand test (5) Stability and response test This is a Severity Level V violation (Supplement II).
9 L
/
Y s
/
3ppendix A /
f
,/'
Pursuant to the provisions of 10 CFR 2.201, you are required to submit to this office within twenty-five days of the date of this Notice a written statement or explanation in reply, including for each item of noncompliance:
(1) corrective action taken and the results achieved; (2) corrective action to be taken to avoid further noncompliance; and (3) the date when full com-pliance will be achieved.
Under the authority of Section 182 of the Atomic Energy Act of 1954, as amended, this response shall be submitted under oath or affirmation.
l T&_d_0$k Dated
/ /
G. Fiorelli, Chief Reactor Construction and Engineering S pport Branch I