Appendix A NOTICE OF VIOLATION Unicn Electric Company Docket No. 50-483

" As a esult ~of the ' inspection conducted on January 5-30, 1981, and in accordance with the Interim Enforcement Policy, 45 FR 66754 (October 7,

~

.1980), the following violation was identified:

10. CFR. 50, ' Appendix B, Criterion V and SNUPPS PSAR paragraph 17.1.5 states:

" Activities affecting quality shall be prescribed by documented instructions and shall be accomplished in accordance with these in-structions."

1 J

Contrary. to the above: - (1) There ~is no procedure for the repair of damaged

-electrical cable jackets-(instructions.are contained on drawings only).

(2) Daniel' International Work Procedures requiring that installed cables be

. kept-free of construction-materials and other debric were not followed.

This-is a severity Level OI violation (Supplement II)

Pursuant to the provisions of 10 CFR 2.201, you are required to submit to this office within twenty-five days of :the date of this -Notice a written statement or; explanation. in reply, including for each item of noncompliance:

.(1) corrective action-taken and the.results achieved; (2) corrective action to be.taken to' avoid further noncompliance; and (3) the date when full com-

.pliance will be achieved. Under the. authority of Section~182 of the Atomic 7'

Energy Act of 1954, as amended, this response shall be submitted under oath

.or affirmation.

/rekt bA-dad G. Fiorelli,? chief Reactor Construction and h

Engineering. Support Branch V