ML19341D322

From kanterella
Jump to navigation Jump to search
Forwards IE Mgt Meeting Repts 50-321/80-41,50-366/80-41, 50-424/80-16 & 50-425/80-16 on 801020.No Noncompliance Noted
ML19341D322
Person / Time
Site: Hatch, Vogtle  Southern Nuclear icon.png
Issue date: 01/29/1981
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML19341D323 List:
References
NUDOCS 8103050358
Download: ML19341D322 (2)


See also: IR 05000321/1980041

Text

/C

o ! a c:g

$

'

o,

UNITED STATES

8'

3.

NUCLEAR REGULATORY COMMISSION

$

c

REGION li

e,

f

101 MARlETTA ST., N.W.. SUITE 3100

ATLANTA. GEORGIA 303o3

\\ ..... [

JAN 2 91981

In Reply Refer To:

e

RII: PAT

<

50-366/80-41 I b

[

50-321/80-41

g

~

  1. g[f>y.

,/

.

0-424/80-16' f

3

,[

(J.

50-425/80-16

7

44

Georgia Power Company

/

"

4 p

ATTN:

J. H. Miller, Jr.

4

% 4

Executive Vice President

9 /

270 Peachtree Street

'

c;

Atlanta, GA 30303

Gentlemen:

This refers to the meeting held at your corporate offices in Atlanta, GA on

October 20, 1980, at our request. This meeting was related to activities autho-

rized by NRC License Nos. DPR-57, NFF-5, CPPR-108 and CPPR-109 for the Hatch ,and

Vogtle facilities.

Our evaluation as developed from the Systematic Assessment of Licensee Performance

(SALP) was presented and discussed. The results of this evaluation are included

in the enclosed inspection report.

1*. is our opinion that this meeting was particularly beneficial in that we were

able to present our evaluation of your activities, and in turn, you were able to

respond directly to these evaluations.

Your positive response to the presentation is appreciated and should enhance

communications with us in areas pertinent to safe reactor operations.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulation's, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

No reply to this letter is required; however, should you have any questions

concerning these matters, we will be glad to discuss them with you.

Sincerely,

D.' O $f 'Reilly

f

0

D ector

Enclosure:

RII Report Nos. 50-321/

.,

50-366/80-41, 50-424/80-16

and 50-425/80-16

cc w/ encl:

(See Page 2)

1810 30 5 u%B

R

,

4

>

.

JAN 2 91981

Georgia Power Company

-2-

cc w/ encl:

M. Manry, Plant Manager

C. E. Belflower, Site QA Supervisor

W. A. Widner, Vice President and

General Manager-Nuclear Generation

K. M. Gillespie, Construction Project Manager

E. D. Groover, QA Site Supervisor