States That Emergency Plan Implementing Procedures Were Submitted on 800722,per NUREG-0737,Item III.A.2.Procedures Are in Use & Support Current Station Emergency Plan
ML19341C887
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 02/27/1981
From: Baum E
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Clark R, Harold Denton
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-3.A.2.1, TASK-TM 125, NUDOCS 8103040385
Download: ML19341C887 (1)


Text

VIRG;NI A ELEC TRIC AND POeER COMP ANY RIC HMON D, VIRGINI A 2J26)

February 27, 1981 Mr. Harold R. Denton, Director Serial No. 125 Office of Nuclear Reactor Regulation SP/JEE:rab Attn:

Mr. Robert A. Clark, Chief Operating Reactors Branch No. 3 Docket Nos. 50-338 Division of Licensing 50-339 U. S. Nuclear Regulatory Commission License Nos. NPF-4 Washington, D.C.

20555 NPF-7

Dear Mr. Denton:

EMERGENCY PLAN IMPLEMENTING PROCEDURES NORTH ANNA POWER STATION The purpose of this letter is to state that the Emergency Plan Implementing Procedures, EPIP's, required by 10 CFR 50, Appendix E, Paragraph V, and by NUREG 0737, Item III.A.2 (Part 1) were sub-mitted on July 22, 1980 (Vepco serial number 639). These EPIP's are in use and support the current North Anna Power Stecion Emergency Plan.

Very t'.aiy yours.

As--

E. A. Baum Executive Manager Quality Assurance (10 copies)

/

4,

s. \\,i - }vg I~

7 cc: Region II (3 copies)

j-g 9

c MAR O 31981 *

~~~

q v,s. m y,; g "

/

4 A'

t0 8108040 % 5t