UNITED STATES
'
g},~,,
j
NUCLEAR REGULATORY COMMISSION
c
REGION 11
- c
~
f
101 MARIETTA ST., N.W., SUIT E 3100
o,
AT LAN T A, GEORGI A 30303
'v
j
- ...*
DEC 191980
In Reply Refer To:
RII:ALC.
50-518/80-19
CO
/ C r)y
'50-519/80-18
)
-
7' 50-520/80-19
,.jp
g
-
-
~ 50-521/80-17
J.Y
~
,
N//;> .? .
.-
,__
m o.s,
. /'g8
p.
- Dg/ g
Tennessee Valley Authority
y
ATTN:
H. G. Parris
Manager of Power
k
y/
s
Md
500A Chestnut Street Tower II
4/
Chattanooga, TN 37401
ru l
-
Gentlemen:
This refers to the inspection conducted by A. L. Cunningham of this office on
October 28-31, 1980, of activities authorized by NRC Construction Permit Nos.
CPPR-150, CPPR-151, CPPR-152 and CPPR-153 for the Hartsville facility, and to
the discussion of our findings held with R. T. Hathcote at the conclusion of the
inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were disclosed.
We have examined actions you have taken with regard to previously reported
unresolved items. The status of these items is discussed in the enclosed report.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
,
inspection report will be placed in the NRC's Public Document Room.
If this
I
report contains any information that you (or your contractor) believe to be
l
proprietary, it is necessary that you make a written application within 20 days
I
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasons on the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate part of the document. If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
I
f
d
Tennessee Valley Authority
-2-
DEC 191980
.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
J. Philip Stohr, CF
f
Fuel Facility and Material
Safety Branch
Enclosure:
Inspection Report
Nos. 50-518/80-19, 50-519/80-18
50-520/80-19 and 50-521/80-17
cc w/ encl:
R. T. Hathcote, Project Manager
J. F. Cox, Supervisor, Nuclear
Licensing Section
J. E. Wills, Project Engineer
H. N. Culver, Chief, Nuclear Safety
Review Staff
--