ML19340E804
| ML19340E804 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 12/11/1980 |
| From: | Davis A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Whiddon O DETROIT EDISON CO. |
| Shared Package | |
| ML19340E805 | List: |
| References | |
| NUDOCS 8101150810 | |
| Download: ML19340E804 (2) | |
See also: IR 05000341/1980021
Text
v - - - i
--
g
,
1
a
D
w
>-
~ , .
[o ne
,
'o
UNITED STATES
..
- '.
Nb
8'
NUCLEAR REGULATORY COMMISSION
,U:2
j
"
, , -
n
$
,E
REGION 111
ll
j
-
y
,
799 ROOSEVELT ROAD
.r.;;
g
o,
g;.
% .b' [
GLEN ELLYN,ILLINols 60137
,
_
M c:
r
- ..*
- 5
o
IWP. 1 1 WO
O
o
W
N
Docket No. 50-341
The Detroit Edison Company
ATTN:
Mr. O. D. Whiddon
Vice President Operations
2000 Second Avenue
Detroit, MI 48226
Gentlemen:
This refers to the routine inspection conducted by Mr. L. J. Hueter of
this office on November 19-21, 1980, of activities at Enrico Fermi Atomic
Power Plant, Unit 2, authorized by NRC Construction Permit No. CPPR-87
and to the discussion of our findings with Messrs. W. Holland, E. Hines,
W. White, and others of your staff at the conclusion of the inspection.
The enclosed copy of our inspection report identifies areas examined
during the inspection. Within these areas, the inspection consisted of a
selective examination of procedures and representative records, observations,
and interviews with personnel.
No items of noncompliance with NRC requirements were identified during
the course of this inspection.
However, we are concerned with the paucity of staffing in the Rad-Chem
Section and with the apparent status of the radiation protection training
program, considering your current plans for receiving fuel, fuel load, and
reactor startup.
Based on discussions with your representatives at the
site, we understand that staffing in this area and training will be
expedited.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC's Public Document
Room, except as follows.
If this report contains information that you or
your contractors believe to be proprietary, you must apply in writing to
this office, within twenty-five days of the date of this letter, to
withhold such information from public disclosure. The application must
include a full statement of the reasons for which the information is
considered proprietary, and should be prepared so that proprietary information
identified in the application is contained in an enclosure to the application.
810115 0 8l0
- .
.
-
_
_
..
_.
-
--
-.
'
\\
The Detroit Edison Company
-2-
tif f.
1 1 '/'i
We will gladly discuss any questions you have concerning this
inspection.
Sincerely,
1
dB
1
m
A. B. Davis, Chief
Fuel Facility and
Materials Safety Branch
Enclosure:
IE Inspection
,
Report No. 50-341/80-21
cc w/ encl:
4
Central Files
Reproduction Unit NRC 20b
!
AE0D
Resident Inspector, RIII
Local PDR
].
Ronald Callen, Michigan
Public Service Commission
,
l
Eugene B. Thomas, Jr.,
Attorney
>
1
!
.
$
,
.
-
-.
.
.
. .
m
..
.m
- ..m .
.
.
.
. .
...
1
-