ML19340E469

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept,Originally Reported on 801205,re Concrete Deficiences Discovered Near Surface of Reactor Bldg Dome.Further Evaluation Will Be Performed by Bechtel.Final Evaluation to Be Completed by 810401
ML19340E469
Person / Time
Site: Callaway  Ameren icon.png
Issue date: 01/02/1981
From: Bryan J
UNION ELECTRIC CO.
To: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, ULNRC-406, NUDOCS 8101140589
Download: ML19340E469 (1)


Text

_ _ _ _ -

~

~ January 2, 1981 Mr. Gaston Fiorelli, Chief Reactor Construction and Engineering Support B U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road .

Glen Ellyn, IL 60137 ..

UIJUtC-4 06 '

Dear Mr. Fiorelli:

POTENTIAL 10CFR50.55 (e) REPORT 5o-%

1 REACTOR BUILDING DOME CONCRETE CALLAWAY PLANT So- m On Friday, December 5, 1980 we provided Mr. H. M. Wescott and W. A. Hansen verbal notification of'a potential 10CFR50.55 (e) report regarding concrete deficiencies discovered near the surface of the Reactor Building Dome. The discrepancies apparently resulted from improperly consolidated concrete which was placed during the final pour of the dome.

Present indications'are that the deficiencies are not significant, however, further evaluation will be perforned by Bechtel Power Corporation to substantiace this. A final evaluation '

of this matter is expected to be completed by April 1,1981.

~

Very truly yours, ortsmai signed tw I JOHN K. BRYAN .

~

John K. Bryan DBS/jds -

cc: H. M*. Wescott, NRC Region III W. A. Hansen, NRC Resident Inspector Misscuri Public Service Commission 5.ctor Ste lo, Jr. ded to distribution list 1-3-81 O l$