Forwards IE Insp Repts 50-010/75-02,50-237/75-03 & 50-249/75-03 on 750227.No Noncompliance Noted
ML19340A695
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 02/21/1975
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
Shared Package
ML19340A696 List:
References
NUDOCS 8009030700
Download: ML19340A695 (2)


See also: IR 05000010/1975002

Text

/

,

,

- - . -

. . . , -

D

,'

,

a,

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION lli

,

799 ROOSEVELT RO AD

GLEN ELLYN, ILLINOIS 60137

.. .

9

"9

7 1 1975

t'a==anwealth Edison Cw==y

Docket No. 50-10

ATIN:

Mr. Byron Lee, Jr.

Docket No. 50-237

Vies President

Docket No. 50-249

P. O. Box 767

chiemgo, Illinnis

60690

Gentlemen:

This refers to the inspection conducted by Mr. Jorgensen of this office

,

on January 27, 1975 of activities at the Dresden Nuclear Power Station,

Unita 1, 2 and 3 authorized by NRC Operating Licenses No. DPR-2, DPR-19

and DPR-25 and to the discussion of our findings with lfr. Butterfield

and others of your staff at the conclusion of the inspection.

'

A copy of our report of this. inspection is enclosed and identifies

the area av==ined during the inspection. Within this area, the inspection

-

consisted of a selective awa=4 nation of procedures and representative

records, interviews with plant personnel, and observations by the

inspector.

No items of noncompliance with NRC requirements were identified within

the scope of this inspection.

'

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2 Title 10, Code of Pederal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you or your contractors

believe to be proprietary, it is necessary that you make a written

application to this office, within twenty days of your receipt of this

letter, to withhold such information from public disclosure. Any such

application must include a full statement of the reasons for which it is

clai=ad that the information is proprietary, and should be preparad so

the proprietary information identified in the application is contained

in a separate part of the document. Unless we receive an application to

withhold information or are otherwise contacted within the specified

time period, the written tasterial identified in this paragraph w111 be

placed in t'se Public Document Room.

oLuT g

e

e

b

h

I

'%.,#

8000o307 0 0

__

_

.

M

_m

. .--

- .

,.c#2

O tQ

-

l

.. .

,

REB 2 1 1975

~

Commonwealth Edison Company

-2-

No reply to this letter is necessary; however, should you have any

questions concerning this inspection, we will be glad to discuss them

j

with you,

i

Sincerely yours,

Gaston Fiore111, Chief

Ranctor Operations Branch

Enclosure:

IE Inspection hports

No. 050-010/75-02, No.

050-237/75-03 and No.

05G-249/75-03