Forwards IE Insp Rept 50-327/80-29 on 800706-31.No Noncompliance Noted
ML19339A838
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 09/08/1980
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19339A839 List:
References
NUDOCS 8011050507
Download: ML19339A838 (2)


See also: IR 05000327/1980029

Text

[/G_..

B

/

o

UNITED STATES

g

8

NUCLEAR REGULATORY COMMISSION

o

$

.I

REGION 11

g

,f

101 MARIETTA sT., N.W., sulTE 3100

.....[

ATLANTA, GEORGIA 3o3o3

In Reply Refer To:

h WTC- - - .

$p

gg

J0-327/80-2d

Tennessee Valley Authority

ATTN:

H. G. Parris

Manager of Power

500A Chestnut Street Tower II

Chattanooga, TN 37401

Gentlemen:

This refers to the inspection conducted by W. T. Cottle of this office on July 6

through July 31, 1980 of activities authorized by NRC Operating License No.

DPR-77 for the Sequoyah facility, and to the discussion of our findings held

with J. H. Ballentine at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

seltctive examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

>

Within the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information thct you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is claimed that

the information is proprietary, and should be prepared so that proprietary infor-

mation identified in the application is contained in a separate part of the

document.

If we do not hear from you in this regard within the specified period,

the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Siacerely,

E.C.

R. C.

ewis, Acting Chief

Reactor Operations and Nuclear

Support Branch

Enclosure:

See Page 2

8011050 Se'!

,

Tennessee Valley Authority

-2-

,

Enclosure:

Inspection Report No. 50-327/80-29

cc w/ encl:.

,

G. G. Stack, Projere. Manager

J. M. Ballentine, Plant

Superintendent

J. F. Cox, Supervisor, Nuclear

Licensing Section

M. J. Burzynski, Project Engineer

H. N. Culver, Chief, Nuclear Safety

Review Staff