EOSTON EDISON COMPANY G e=s ma6 Orreces v Savomrom Svedst B osTON. M ASSACHURCTT3 Q2199 BECo Ltr. #80- 268 A. VICTOR MORIst macta m:ctram onmar ons scnoir nen"""T October 29, 1980 Mr. Darrell G. Eisenhut, Director Division of~ Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555 License No. DPR-35 Docket No. 50-293 Status of NUREG-0578 Categorv B Items
Dear Mr. Eisenhut:
The purpose of this letter is to inform you of the status of Boston Edison's NUREG-0578 " Category B" Items. Additional requirements imposed by I&E 3;11etin #79-01B, that Electrical components be environmentally qualified in accordance with IEEE 3!4-1974 has placed added constraints on our implementation schedule for NUREG-0578 "Cuagory B" Items. Our current schedule for implementation with delivery dates identified is provided as an Attachment to this letter. Material descriptions, lead times, delivery dates and vendors are listed.
We trust this information is adequate to demonstrate to the NRC that Boston Edison is making every effort to meet the NRC's schedules. The completion dates for these items are contingent upon receipt of material already ordered. Should you desire additional information or clarification of our expediting efforts, please feel free to contact us.
Very truly yours,
>. < ; ;.; w 3
\\
0
\\
U"T"L L
Attachment to BEco Ltr. #80- 268 NUREG-0578 Category "B" Items Status and Implementation Dates Position 2.1.2 - Performance Testin2 for Relief and Safety Valves Boston Edison Company has subscribed to the GE BWR Owners Group Recommendations and Test Program. The scheduled completion date is July 1,1981.
Position 2.1.3.b - Instrumentation for Detection of Inadequate Core Cooling Boston Edison Company concurs with the BWR Owners position that existing in-strumentation is adequate for detecting inadequate core cooling.
However, we are evaluating improvements which could be made to that instrumentation.
These improvements are beyond the requirements of Position 2.1.3.b of NUREG-0578, and are not yet scheduled for implementation.
Position 2.1.5.a - Dedicated Penetrations for External Recombiners or P3st Accident Purge Systems Boston Edison installed dedicated penetrations during the 198Q Refueling Outage.
This item is complete.
t Position 2.1.6.b - Design Review of Plant Shielding
~
l The Initial Design has been completed. A remote closure capability is being installed on the Reactor Truck Lock Door. Modifications are scheduled for completion onNovember 18, 1980.
In addition, modifications required by
)
NUREG-0578 Items 2.1.8.a. Post Accident Sample System installation and 2.1.9 New 3, Containment Hydrogen and Oxygen Monitoring are directly related to re-ducing radiation exposure in p1 at vital areas. The schedule for completion of these two items follows.
Position 2.1.8.b - Increased Range of Radiation Monitors High range noble gas effluent monitors were installed during the 1980 Refueling Outage.
Installation of containment high radiation monitors are scheduled for completion onDecember 6,1980.
Position 2.1.9 - Analysis of Design and Off Normal Transients and Accidents Boston Edtson is awaiting NRC approval of the BWR Owners' Group Recommendations.
The schedule for completion of this item depends upon the NRC approval of the recommendation.
Position 2.1.9 New 2 - Containment Water Level Monitoring Modifications to provide the capability of monitoring the containment water level over a wide range is scheduled for completion before November 26,1980.
Position 2.2.2.b - On-Site Technical Suncort Center An interim Technical Support Center was established and equipped during the 1980 Refueling Outage. As the requirements for Emergency Response Facilities becomes more clearly defined, Boston Edison will make the necessary improvements to meet the intent of those requirements. We will advise you of the degree to which we can meet those requirements.
0 s
0 Position 2.1. 8. a - Post Accident Sampling System Installation of Post Accident Sampling System is scheduled for completion on February 28, 1981.
The installation is considered to be interim as discussed in the note following.
Position 2.1.9 New 3 - Containment Hydrogen and Oxygen Monitoring S~ystem Completion of the H &0 Moni toring System is scheduled for February 28,_1981, 2
9 with the interim installation.ns discussed in the note following.
NOTE: The implementation c:f a Post Accident Sampling uystem (Section 2.1.8.a) and Containnent Hydrogen and Oxygen Monitoring System (2.1.9 New 3) necess::tates the upgrading of the Emergency Power Distribution System. Availability of equipment qualified to i
IEEE'344-1974 impacta the completion of above modifications.
Premium prices are being paid to expedite the long lead items l
listed in the chart below. The completion date for a fully qualified Post Accident Sampling Sys' tem and Hydrogen and Oxygen Monitoring System is estimated to be October 1981.
ESTIMATED DELIVERY ITEM LEAD TIME DATE VENDOR (Purchase Orders Issued)
Vent Fans 32-40 weeks 8/18/81 Buffalo Forge 480 Motor Control Centers 24-32 weeks
- 2/13/81 Westinghouse
- Distribution Transformers 20 weeks
- 1/02/81 Westinghouse
- 120V/240V Distribution Panels 20-22 weeks 1/09/81 Systems Control Control Panels 18 weeks 11/17/80 Mercury Control Switches 20-24 weeks 12/15/80 GE
- Purchase Order will be issued shortly.
,.-