Appendix A NOTICE OF VIOLATION Docket No. 50-237 Commonwealth Edison Docket No. 50-249 Company Based on the inspection conducted on June 6-8, 15, 16, 20, 21, it appears that certain of your activities were and 27-29, 1978, The item in noncompliance with NRC requirements, as noted below.
identified is an infraction.
Units 2 and 3 Technical Specifications, Section 6.2.A.7 require that serveillance and testing requirements which could have an effect on the safety of the facility shall have detailed written procedurer which shall be prepared, approved and adhered to.
28, 1978, the licensee performed Contrary to the above on April a valving operation not in accordance with DOS 6600-6, " Bus Undervoltage and ECCS Integrated Functional Test for 2/3 Diesel Generator," which caused the "A" LPCI and Core Spray Subsystems for Unit 2 to be rendered inoperable for approximately four hours.
The licensee's corrective action to prevent occurrence has been reviewed and appears adequate; therefore, no further response is required.
O l
8009200 I