ML19338D523

From kanterella
Jump to navigation Jump to search
Safety Evaluation Supporting Amends 57 & 54 to Licenses DPR-39 & DPR-48,respectively
ML19338D523
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 09/09/1980
From:
Office of Nuclear Reactor Regulation
To:
Shared Package
ML19338D517 List:
References
NUDOCS 8009230394
Download: ML19338D523 (4)


Text

E

'2

' UNITED STATES 8

NUCLEAR REGULATORY COMMISSION

-o i

I wasmNoTou, o. c. rosss 4

Q/

?

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AfiENDMENT N0. 57 TO FACILITY OPERATING LICENSE NO. DPR-39 AND AMENDMENT NO. 54 TO FACILITY OPERATING LICENSE N0. DPR-48 i

COMMONWEALTH EDIS0N COMPANY ZION STATION, UNITS 1 AND 2 DOCKET NOS. 50-295 AND 50-304 Introduction Conmonwealth Edison Company (CECO) has determined that each of the six circulating water pumps at the Zion Station, Unit Nos.1 and 2 should be overhauled during the next sixteen months.

It is expected that each pump will be out of service for about 90 days.

The overhaul of each pump will require draining the associated forebay which is shared with a service water pump. Thus, the overhaul will disable a service water pump.

ThecurrentZionStationTechnicalSpecifications-(Reference 4) require all six service water pumps (three for Unit.1 and three for Unit

2) to be operable. 'If one pump is declared inoperable in one unit, the licensee has seven days _to restore the pump to its operable condition.

If these conditions cannot be met, the reactor shall be brought to hot shutdown within four hours and cold shutdown within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after that.

Thus, a temporary change to the Zion Technical Specifications is needed to ' allow continued plant operation while this extended maintenance is being performed on-the circui0 ting water pumps or on the service water pumps, if required.

In a letter dated August 15, 1980 (Reference 1), CECO requested an expeditious review and approval of an immediate temporary change to the Zion Technical Specifications.

The proposed change will allow one of the six service water pumps to _be out of service indefinitely and two of the six service water pumps to be out of service for a maximum of

seven days.

A' minimum of two pumps shall be available to each unit.

-The propose' change is temporary and will expire on about December 31, 1981.

Ciscussion.

The six' service water. pumps feed two separate main supply headers, one

. header for each unit with three pumps on each header.

The headers are cross-tied so that any combination of pumps can serve both units under h+

?800923'0 Jh t

+

,z.

-,t gy--:

s-2-

normal ' opera' ting ' conditions.

Normal-operation requires two pumps on

- i 1

each ' unit with the third pump serving as a standby.

The system pressure is. maintained between 55 and 752psig in the. main supply header as the-

, third pump will' automatically start when the header pressure drops to 50 psig.

I The Zion FSAR (Reference 2) and the NRC's SER (Reference 3) state that

- only two service water pumps are required for each unit for nornal oper-

. ation and that.only one service water pump is required for each unit

' for emergency shutdown or accident conditions.

Emergency ' requirements -

are less -because variouslnon-safety related systems are isolated during accident' conditions.

Evaluation Based on our review of CECO's proposal, as well as a review of the above noted references, we agree-that only five operating service water pumps will provide sufficient cooling for any postulated loss of coolant accident coincident' with a loss. of offsite power and with any other. single failure of an active components._ In addition, during this period, the main 48-inch service water headers for each unit will be in the cross-tied mode'thus allowing the service water requirements for one unit to '_'e satisfied by pumps from either unit.

. CECO is currently reviewing and possibly will propose adopting the NRC's current Standard Technical Specifications (STS) for Zion Station.

The current Zion-Station Technical Specifications are more conservative than our current STSs and require.the operability of 'all six service water.

pumps.

The NRC's STS if approved for Zion Station, in all. likelihood, would only require that two out of three service water pumps for each unit be operable.. We would not expect that the third, standby service water pump be operable ~ during normal operating conditions in each plant unless for other mitigating reasons'.

Therefore, based upon our. review, we conclucr that sufficient justification exists-to -grant' the licensee's. Technical Specification change.

However, this. Technical-Specification change is only temporary and will expire upon completion of the circulating water pump maintenance program scheduled for completion about December 31, 1981.

]

I 1

1 t

-7 3

r j

=

A g

N.~ -

Y:

.t J L

=--- -u

y v 3'-

Environmental Consideration We.have determined that the amen' ments do not authorize a change in effluent d

types or total amounts nor an increaseLin power level'and will not result in any;,significant environmental impact.-.Having made-this determination, we have further ~ concluded that the anendments involve an action which is. insignificant ~from the standpoint of environmental impact and, pursuant toL 10 CFR 51.5(d)(4), that an environmental. impact statement or negative declaration and environmental impact appraisal 'need not be prepared..in' connection with.the issuance of these amendments.

Conclusion We have conclu'ded, based on the considerations discussed above,-that:

(1) because the amendments do not involve a. significant increase in the probabilitf or consequences of accidents previously considered and do not involve a significant decrease in a safety margin, thel amendments do not involve a significant-hazards consideration, (2) there is reasonable assurance that'the health and safety of. the public will not be endangered by operation in ~the proposed manner, and-(3) such activities will be conducted in'cocpliance with the Commission's regulations and the issuance of these amendments will' not be inimical to the common defense and security or to the_ health and safety of the.public.

Date:

September 9,1980 P

9 9

~

="

g LC.

V'~

q

..,-f.

p ygg; 4

g..

x w v;.

~

g ", - -

3 Op

~.

t

~

1 4,

References

l.. Letter from Connonwealth Edison Corrpany (W.: F. Naughton) to U.S.N.R.C.

(H. R. 'Denton) dated August'15,fl980..

'2.

Zion Final-Safety : Analysis Report,. Section 9.6.

3.

NRC's-Safety Evaluation Rep' ort for Zion Station o unitL Nos.1 and 2,

' dated 0ctober 6,1972, pages 9-5 Land 9-6.-

^

~

4.' Zion Station Tech'nical Specifications,,ection 3.8.7.

Y T14

" -. s:)

4 4

b.

t

, s

'1

'l f,'

' +

~'e

~;;(..

__~~

ij.

~

y+

3_ -

v-7-

-g,

^

$ 32 k *

~'

n; z:

.vi~

.