UNITED STATES
i .i
g,
ATOMIC ENERGY COMMISSION
+)
DIRECTOR ATE OF REGULATORY OPERATIONS
.
f
REGION lli
Tis O'
799 ROOSEVELT ROAD
ymg
GLEN ELLYN, ILLINOIS 60137
(312) 858 2660
SEP 131973
l
l
Consumers Power Company
Docket No. 50-329
J
ATTN
Mr. Stephen H. Howell
Docket No. 50-330
'
Vice President
212 West Michigan Avenue
.
Jackson, Michigan
49201
Gentlement
i
1
This refers to the inspection conducted by Messrs. Hayes, Rohrbacher and
i
Vandel of this office on July 23 - 26 and August 8 - 10, 1973, relative to
the Midland Plant, Units'I and 2, authorised by AEC Construction Permit
No. CPPR-81 and No. CPPR-82, and to the discussions of our findings with
j
Messrs. Kessler, Bills and others of your staff.
i
.
O
Areas awa= 4ed during the inspection are identified in the enclosed report.
Within the areas reviewed, the inspection consisted of selective examination
,
of procedures'and records, intarviews with personnel and observations by
the inspectors.
j
'
No violations of AEC regulations were identi*ied within the scope of this
inspection.
With regard to questions raised during this inspection,' and during a subse-
quant meeting held with you in the Region III office, on August 16, 1973,
we understand that you intend to review yet'r Quality Assurance organization
i
for the Midland Project and that your review will be based on our comments
relative to clarification of responsibilities and independence of the
Consumers Power Company Quality Assurance organization.
l
A copy of our report of this inspection is enclosed and, in accordance with
Section 2.790 of the AEC's " Rules'of Practice," Part 2, Title 10, code of
Pederal-Regulations, a copy of this letter with the enclosed inspection
,
)
report will be placed in the AEC's Public-Document Room. If the inspection
'
report contains information which you or-your contractors believe to be
.
proprietary,^it is necessary that you submit a written application to this
office, within 20 days of the date of this letter, requesting.that such
L
l
Linformation be withheld from pub 1_ic disclosure. If such an application is
submitted it must identify the basis for.which information is claimed to
be proprietary and should be. prepared so that proprietarv information
.
.80080&OMdf
'
-.
- -.
.
. .
.
.- . .
.
. .
.
.
_
_.
_ _ . _ .
. . _
__._____ .----_____ _ ___._ --
9
.
.
' - ~i
's
-
,
.
.
SEP 131973
.Coasemers Power Company
-2-
identified is contained in a separate part of the document since the appli-
cation, excluding this separate pert, will also be placed in the Public.
]
Docusent Room. If we do not receive an application to withhold information,
'
cc are not otherwise contacted within the specified time period, the enclosed
report will be placed in the Public Document Room with a copy of this letter.
Unless you wish to make applicatiou to withhold information, no reply to
this letter is necessary; however, should you have questions concerning
i
this inspection, we will be glad-to discuss them with you.
Sincerely yours,
f
I
James G. Kappler
Regional Director
Enclosure
'
RO Inspection Rpt No. 050-329/73-06
and No. 050-330/73-06
'
bec: R0 Chief, FS&EB