Forwards IE Insp Rept 50-245/80-08 on 800602-06 & Notice of Violation
ML19337A964
Person / Time
Site: Millstone Dominion icon.png
Issue date: 07/15/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Counsil W
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML19337A959 List:
References
NUDOCS 8010010089
Download: ML19337A964 (2)


See also: IR 05000245/1980008

Text

- - _ _

___

_ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

(\\,-

.

4

UNITED STATES

8

-

g

g

NUCLEAR REGULATORY COMMISSION

3

j

REGION I

g

&

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

+9

. . . . ,o

jut 15.1980

Docket No. 50-245

Northeast Nuclear Energy Company

ATTN:

Mr. W. G. Counsil

Senior Vice Prasident - Nuclear

Engineering and Operations

P. O. Box 270

Hartford, Connecticut 06101

Gentlemen:

Subject:

Inspection No. 50-245/80-08

This refers to the routine inspection conducted by Mr. N. Blumberg of this office

on June 2-6, 1980, at Millstone Nuclear Power Station Unit 1 of activities autho-

~

r;.i' by NRC License DPR-21 and to the discussions of our findings held by

Messrs. E. Greenman and N. Blumberg with Mr. E. Mroczka of your staff at the

conclusion of the inspection, and to subsequent telephone discussions between

Mr. N. Blumberg and Mr. R. Herbert on June 9 and 10, 1980.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Our inspector also verified the steps you have taken to correct the items of

noncompliance brought to your attention in letters dated June 14, 1978 and

January 14, 1980.

We have no further questions regarding your action at this

time.

Based on the results of this inspection, it appears that certain of your activi-

ties were not conducted in full compliance with NRC requirements, as set forth

in the Notice of Violation, enclosed herewith as Appendix A.

These items of

noncompliance have been categorized into the levels as described in our corre-

spondence to you dated December 31, 1974.

This notice is sent to you pursuant

to the prov,isions of Section 2.201 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to

this office, within twenty (20) days of your receipt of this notice, a written

statement or explanation in reply including:

(1) corrective steps which have

been taken by you and the results achieved; (2) corrective steps which will be

taken to avoid further items of noncompliance; and (3) the date when ful? com-

pliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

t

!

8 o lo o 1o 039

. _.

--_

._

-

.

.

g j c 19e

Northeast Nuclear Energy Company

2

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure.

Any such

application must be accompanied by an affidavit executed by the owner of the

information, which identifies the document or part sought to be withheld, and

which contains a statement of reasons which addresses with specificity the

items which will be considered by the Commission as listed in subparagraph (b)

(4) of Section 2.790.

The information sought to be withheld shall be ircorpo-

rated as far as possible into a separate part of the affidavit.

If we do not

hear from you in this regard within the specified period, the report will be

placed in the Public Document Room.

Shoulti you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

)

?

'

1

n . Brunner, Chief

Re ctor Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement

Inspection Report No. 50-245/80-08

l

cc w/ encl:

J. F. Opeka, System Superintendent Nuclear Operations

!

E. J. Mroczka, Station Superintendent

l

D. G. Diedrick, Manager of Quality Assurance

)

J. R. Himmelwright, Licensing Safeguards Engineer

{