Forwards IE Insp Rept 50-285/80-12 on 800728-31.No Noncompliance Noted
ML19337A954
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 08/19/1980
From: Madsen G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: William Jones
OMAHA PUBLIC POWER DISTRICT
Shared Package
ML19337A955 List:
References
NUDOCS 8010010064
Download: ML19337A954 (2)


See also: IR 05000285/1980012

Text

7 /O

a atow

o

UNITED STATES

j * ", s g ,i

NUCLEAR REGULATORY COMMISSION

k [ d'

[

611 RYAN PLAZA DRIVE. SUITE 1000

-

c

REGION IV

% . . .' [. ,o#

S,

ARLINGTON, TEXAS 76012

August 19, 1980

In Reply Refer To:

bocket No. 50-285/80-12

Omaha Public Power District

ATTN:

Mr. W. C. Jones, Division Manager -

Production Operations

1623 Harney Street

Omaha, Nebraska

68102

Gentlemen:

This refers to the inspection conducted by Messrs. J. P. Jaudon and L. A.

Yandell of this office during the period of July 28-31, 1980, of activities

authorized by NRC Operating License DPR-40, and to the discussion of the

findings with members of your staff at the conclusion of the inspection.

Principal areas examined during the inspection were the licensee's:

(1)

organizational structu

nd the qualifications /expcrience of personnel in

key management positions and (2) 1.ne calibration program for safety-related

instrument systems.

Within these areas, the inspection consisted of selective examination of

procedures and representative records, interviews with personnel, and

observations by the inspectors.

1

'

During this inspection, members of the Region IV staff and a representative

of NRR's Division of Project Management met with you and your staff on July 31,

1980. The purpose of this meeting was to discuss the region's first annual

evaluation of OPPD activities at the Fort Calhoun Station.

This evaluation was

made in accordance with the requirements of Task I.B.2 of the "5RC Action Plan

Developed as a Result of the TMI-2 Accident" (NU.2G 0660) and the NRC's program

entitled the Systematic Assessment of Licensee Performance (SALP).

The results

of the evaluation are documented in enclosure 2 to this letter.

There will

be no further changes in the scope or frequency of our inspection activities

at the Fort Calhoun Station as a result of this evaluation.

Within the scope of this inspection, no items of noncompliance were identified.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document Room.

8010010 Of

-

-

.

'

.

Omaha Public Power District

-2-

August 19, 1980

If this report contains any information that you or your contractors believe

to be proprietary, it is necessary that you make a written application

within 20 days to this office to withhold such information from public

disclosure.

Any such application must include a full statement of the

reasons for which it is claimed that the information identified in the

application is contained in a separate part of the document.

If we do

not hear from you in this regard within the specified period, the report

will be placed in the Public Document Room.

Should you have any questions concerning this. inspection, we will be pleased

to discuss them with you.

Sincerely,

b 'WG $&v"

G. L. Madsen, Chief,

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

IE Inspection Report No. 50-285/80-12

2.

Performance Evaluation, July 1980

cc w/ enclosures:

S. C. Stevens, Manager

Fort Calhoun Station

P. O. Box 98