7-s gl
- .. <g f November. 29, 19891 n
.c 60cketNo.50-344 MEMORANDUM FOR: George' W. Knighton, Director Project Directorate V Division of Reactor Projects - III, IV, Y and Special Projects
$ ROM::
Roby Bevan, Pr4 ect Manager Project Directorate'V-Division of Reactor Projects - III, IV, V and Special. Projects
SUBJECT:
LICENSEE CONFIRMATION OF ITS RESPONSE TO NRC GENERIC LETTER'89-07' L By letter' dated November '7,1989, Portland General Electric (the licensee)-
respondedtoGenericLetter(GL)89-07.
In its response, the licensee confirmed that activities required to address the issues discussed in the a
Generic. Letter have been performed. -Therefore, we consider this action-complete..
By-copy ~ of-this memorandum, Region V is advised of the licensee's position
.on this matter.
original signed by r
Roby Bevan, Project Manager Project Directorate V Division of Reactor Projects - III, IV, V and Special Projects cc:. Eric Leeds, NRR/PD1-3 DISTRLBUT ON
. Q* DOCReM1:leg 53':
NRC"& LPDRs 9-PD5 Reading
'JZwolinski JLee.
m
'RBevan OGC ~
E.. Jordan-(MNBB.3302)
~
-lACRS (10)
CONTACT:.
Roby Bevsn, NRR
-492-1361-q P/PD5 b
van:dr ij o 11/g/89 t
[MPA 89/01]
8912070374 891129 PDR ADOCK 05000344 P
y, 4
~ ~
3 t,n
.[!
/ [,
0, L8 L
NUCLEAR REGULATORY COMMISSION l
a f
' y w > {o wAsHiwoToN,D.C 20666 5
... +
November 27, 1989.
' Docket No.: 50-344 g
MEMORANDUM FOR: -George W; Knighton, Director Project Directorate V m
b" '
Division of Reactor Projects --III,
~
IV, V and Special Projects 4
FROM:
Roby Bevan,, Project Manager u
Project Directorate V-J Division of Reactor Projects.- III, IV, V _ and Special-Projects
SUBJECT:
LICENSEE CONFIRMATION OF ITS RESPONSE TO NRC GENERIC LETTER'89-07 a
- By letter dated November 7,1989 Portland General Electric (the licensee)
. responded to Generic Letter (GL),89-07_.
In its response, the licensee confirmed that activities required to address the issues discussed in the Generic Letter have-been performed. Therefore, we consider this action
' complete'.
By copy of this memorandum, Region V-is advised of' the' licensee's position on this matter.-
': _ - s Roby Bevan, Project Manager Project Directorate V Division of Reactor Projects - III, IV,_V and Special Projects l'
cc: Eric Leeds, NRR/PDI-3 CONTACT:
Roby Bevan, NRR
.492-1361
._,..-m-._
.m
...