Notice of Violation from Insp on 890908-1020.Violations Noted:Cognizant Initiating Supervisor Did Not Enter Applicable Limiting Conditions Imposed in Entry Block 9 of MR 89-8419 & Failure of Shift Supervisor to Sign Worksheet
ML19332D440
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 11/16/1989
From: Chaffee A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML19332D434 List:
References
50-344-89-27, NUDOCS 8912010202
Download: ML19332D440 (2)


Text

m 7 -.

-i*

i~

APPENDIX A 5

~

NOTICE OF VIOLATION

'P'ortland General Electric 1 Company Docket No. 50-344 Trojan Nuclear Plant.

License No. NFF-l'-

DUring an NRC inspection conducted from September 8 through October 20, 1989,-

violations of NRC requirements were identified.

In accordance with the A>

" General' Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR ohrt 2, Apoendix C (1989), the violations are listed below:

10 CFR 50',- Appendix B, Criterion V states in part, " Activities' affecting ff quality shall-be prescribed by documented instructions, procedures, or i

4 drawings, of a type appropriate to the circumstances and shall be.

accomplished in accordance with these instructions, procedures, or drawings.'"

A.

Trojan Administrative Order (A0) 3-9, " Maintenance Requests,"

Revision'32, dated August l', 1989, section 4.4.1.b. states "The Cognizant Initiating Supervisor or designee shall-enter the 3

applicable Technical Specification section, and the number of any Limiting Conditions imposed in entry block 9 of the MR."

~ Contrary to the above, on September 6, 1989, The Cognizant Initiating Supervisor did not ~ enter the applicable Limiting Conditions-imposed in entry block 9 of MR 89-8419. Consequently.

- a Residual Heat Removal (RHR) pump was rendered inoperable and Limiting Condition of Operation 3.5.2.d. was unknowingly entered when a flow switch, FIS-611, was removed from service for uaintenance.

This is a Severity Level-IV violation (Supplement I).

B.

Trojan Administrative Order (A0) 3-14. " Control-of Safety-Related Equipment Outages," Revision 22, dated June 21, 1989, states in part in section 4.4.3.c., "The Shift Supervisor shall sign and date the Worksheet on line 7 indicating approval of the outage."

~

Contrary to the above, on September 8,1989, the Shift Supervisor did not sign and date the worksheet indicating-approval of the outage to work on the flow switch, FIS-611, associated with RHR pump; howem r, he authorized the FIS-611 outage.

l This is a Severity Level IV violation (Supplement I).

s s

891201020g Q (( PDC l

344 ADOC gDR e

r.

r-l.

- Pursuant to the provisions of 10 CFR 2.201, portland General Electric Company is hereby required to submit a written statement af explanation to the U.-3.

Nuclear Regulatory Commission,. ATTN:

Document Control Desk, Washington, DC 20555 with a cory to the Regional Administrator Region V, and a copy to the

. NRC Senior Resident Inspector, Tro [an, within 30. days of the date of the

-letter transmitting this Notice.

his reply should be clearly marked as a

" Reply to a Notice of Violation" and should include ~ for each violation::(1) the' reason for the violation if admitted, (2) the corrective steps that-have been taken and the results achieved, (3) the cortective steps that will-be taken to avc'd furtho' violations, and (4) the date when full compliance will be achievad.

If an adequate. reply,is not received within the time specified in this!

' ~

.v1 ceder may be issued to.shos cause why the license should not be mt

.d suspended, or revoked or why such other action as may be.

, f' proper should act bo 1.aken.

Consideration may be given to extending the

. response time tr w d cause shown.

+

FOR THE NUCLEAR REGULAIORY COMMISSICN h,

% A b b e % [ce--

A, E. Chaffee, Acting Chief

{

RactorProjectsBranch Cated at Walnut Creek, California

.this /pfday of November 1989 5