Final & Interim Deficiency Repts CP-89-029 Re Unauthorized Part Substitutions That Constitute Design Changes.Initially Reported on 891019.Issue Not Reportable for Unit 1 & More Evaluation Required to Determine Safety Significance for 2
ML19332B881
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 11/15/1989
From: William Cahill
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CP-89-029, CP-89-29, TXX-89798, NUDOCS 8911210216
Download: ML19332B881 (2)


Text

y, - .

, , . f M

F, EE Log # TXX-89798 File i 10110

= = .

**' ***' l nlELECTRIC-f November 15, 1989 waa s.co m.se. ,

. . raa se vu rna,a.  :

1. , >
  • U. $. Nuclear Regulatory Commission i

. Attn: Document' Control Desk

, -Washington; D. C. 20555 t

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STAYION (CPSES)

DOCKET NOS, 50 445 AND 50-446 l INAPPROPRIATE DESIGN CHANGES  !

SDAR: CP 89 029 (FINAL REPORT - UNIT 1)

(INTERIM REPORT - UNIT 2) i 5

REF: 1) Notice of Violation (NOV) 445/8935-V-01

2) SDAR: CP-89 010. "AFW Pump Motor Fan Bolts" Gent 1'emen: i

-On October 19, 1989. TU Electric verbally notified the NRC of a deficiency involving unauthorized part substitutions that constitute design changes. I After further evaluation, it has been determined that this issue is not  !

reportable for Unit I under the provisions of 10CFR50.55(e). Further j evaluation-is . required to determine the safety significance of this deficiency  :

for Unit'2.

-In response to Reference 1, a deficiency report (DR) was written to document  !

.the failure to comply with procedures which control item substitution of material, parts and components. The original improper substitution was determined to be not reportabl. by Reference 2. The DR disposition required that Maintenance Engineering Evaluations (MEE's) be evaluated for similar j~

occurrences. No other potentially safety significant Unit 1 substitutions were identified.during the MEE review. Among 600 MEE's reviewed, only one  ;

l- . ' Unit' 2 MEE was identified as potentially safety significant. This Unit 2 MEE >

involved' substitution of mounting bolts for a Unit 2 centrifugal charging pump [

. auxiliary lube oil pump. The auxiliary lube oil pump, although not safety related, requires qualified mounting bolts for seismic qualification of the 9 pump / motor. However, non-qualified bolts were improperly substituted for this application.

u ff>l l' /,

L 8911210216 8.91115 PDR ADOCK 05000445 s;_ PDC-P. O. Box 1002 Glen Rose. Texas 76043-1002 i

+-- . , , , . - - . _ . ~ ., - , , . - - ~ . ~ ,..n,

un ., .. - - . . .

~

E

! s  ;

L 1os('-

i

,a TXX-89798 Page 2 of 2 The safety significance of this Unit 2 condition will be addressed in the next ,

report.on this issue which will be submitted after resumption of the balance of Unit 2 engineering activities, j

Sincerely, hilliam J.'Ca ill, Jr. /

DAR/cp c - Mr. R. D. Martin,' Region IV Resident Inspectors, CPSES (3) i e