r
710
,
.
UNITED STATES
/'s# "Go,%,
NUCLEAR REGULATORY COMMISSION
Oi
. / 1
R EGloN IV
' ) # ( !
'o
611 RYAN PLAZA DRIVE, SUITE 1000
7
,
3-
'
.' j j
ARLINGTON, TEXAS 76012
- Y
August 11, 1980
In Reply Refer To:
RIV
Docket No. 50-458/Rpt. 80-07
Gulf States Utilities
ATTN:
Dr. E. Linn Draper, Jr.
Vice President-Technology
Post Office Box 2951
Beaumont, Texas 77704
Gentl'emen:
This refers to the inspection conducted by Messrs. A. B. Beach and J. I. Tapia
of our staff during the period July 15-18, 1980, of activities authorized by
NRC Construction Permit No. CPPR-145 for River Bend, Unit No.1, and to the dis-
cussion of our findings with Mr. T. C. Crouse and other members of your staff
at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examination of procedures and representative records, interviews
with personnel, and observations by the inspectors.
During the inspection, it was found that certain activities under yo r license
appear to be in noncompliance with Appendix B to 10 CFR 50 of the NRC Regula-
tions, " Quality Assurance Criteria for Nuclear Power Plants." The items of non-
'
compliance and references to the pertinent requirements are identified in the
enclosed Notice of Violation.
This notice is sent to you pursuant to the provisions of Section 2.201 of the
NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office, within 30 days of your
receipt of this notice, a written statement or explanation in reply including:
(1)
corrective steps which have been taken by you, and the results achieved;
(2)
corrective steps which will be taken to avoid further noncompliance; and
(3)
the date when full compliance will be achieved.
During this inspection, it was also found that certain of your activities
appeared to deviate from commitments in the PSAR. The items and references to
the specific commitments are identified in the enclosed Notice of Deviation.
In your reply, please include your comments concerning the items, a description
of any steps that have been or will be taken to correct them, a description of
any steps that have been or will be taken to prevent recurrence, and the date
all corrective actions or preventive measures were or will be completed.
B'009250 N
-
.
.
Gulf States Utilities
2
August 11, 1980
We have examined actions you have taken with regard to previously identified
inspection findings.
The status of these items is identified in paragraph 2
of the enclosed report.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If the
report contains any information that you believe to be proprietary, it is
necessary that you submit a written application to this office, within 20 days
of the date of this latter, requesting that such information be withheld from
public disclosure.
The application must include a full statement of the reasons
why it is claimed that the information is proprietary.
The application should
be prepared so that any proprietary information identified is contained in an
enclosure to the application, since the application without the enclosure will
also be placed in the Public Document Room.
If we do not hear from you in this
regard within the specified period, the report will be placed in the Public
Document Room.
Should you' hav$ any questions concerning this inspection we will be pleased
to discuss them with you.
Sincerely,
'
s
, f . C. Seidle, Chief
(
Reactor Construction and
Engineering Support Branch
Enclosures:
!
1.
Appendix A, Notice of Violation
2.
Appendix B, Notice of Deviation
3.
IE Inspection Report No. 50-458/80-07
1
l