ML19331D732

From kanterella
Jump to navigation Jump to search
Notifies That Restrictions Re Facility Operation Resumption Not Necessary Per Review of Util 800805 Steam Generator Tube Insp Results.Conditions of 791130 Order & 800103 Mods to 791130 Order Remain in Effect.Safety Evaluation Not Encl
ML19331D732
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 08/08/1980
From: Case E
Office of Nuclear Reactor Regulation
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
Shared Package
ML19331D728 List:
References
NUDOCS 8009030501
Download: ML19331D732 (1)


Text

. __

RECEIVED AUG 2 0 tgag g>#

%,1 UNITED STATES O;8 NUCLEAR REGULATORY COMMISSION E

WASHINGTON, D. C. 20556 g

/

August 8, 1980 Docket No. 50-266 Mr. Sol Burstein

. Executive Vice President Wisconsin Electric Power Ccmpany 231 West Michigan Street Milwaukee, Wisconsin 53201

Dear Mr. Burstein:

The NRC staff has reviewed the results of the Point Beach Nuclear Plant, dated August 5,1980 in accordance with the April 4,1980 M November 30, 1979 Order.

Based on the results of that review and for the reasons stated in the attached Safety Evaluation Report, we find that the results are acceptable and, thus, it is not necessary to place any further restriction on the resumption of operation of the Point Beach Nuclear Plant, Unit No. 1.

We would like to emphasize that all the conditions of the November Order and the January 3,1980 Modifications to the November 30, 1979 30, 1979 Order remain in effect in accordance with their terms.

It is our understanding that Unit I will be removed from service November' 1980 for a refueling outage, and that during that outage, hydrostatic tests tubes, will be performed.and eddy current examinations of 100 percent of all unplu provide the NRC, within 15 days of your receipt of this letter, you and schedule for these steam generator tube inspections.

Following the staff's review of your proposed plans and schedule, consideration will be given to the necessity of issuing an Order confirming your pregram or modifying your program to establish additional requirements.

If you have any questions on this subject, please contact us.

Sincerely, v

Edson G. Case, Acting Director Office of Nuclear Reactor Regulatian

Enclosure:

Safety Evaluation cc w/ enclosure:

See next page

/

501 0