Forwards Cover Ltrs W/Correct Dates & Incorrect Dates for IE Insp Repts 50-338/80-13 & 50-339/80-14 on Corrected Dates of 800324-27
ML19331C306
Person / Time
Site: North Anna  
Issue date: 06/17/1980
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Ferguson J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML19331C307 List:
References
NUDOCS 8008140528
Download: ML19331C306 (1)


See also: IR 05000338/1980013

Text

O

.

J

ja acroy'o,

y/!b,

8

UNITED STATES

8

~1

NUCLEAR REGULATORY COMMISSION

s

i

<E

REGION 11

M ^IS8

0,

[

101 MARIETTA ST., N.W., SUITE 3100

e

J

%,*****

o-

's19

ATLANTA, GEORGIA 30303

g

In Reply Refer To:

.

RII:EHW

50-338/80-13

50-339/80-14

Virginia Electric and Power Company

Attn:

J. H. Ferguson

Executive Vice-President, Power

P. 9. Box 26666

Rit nond, VA 23261

Gentlemen:

Due to a typographical error on page 1 of our letter dated April 11, 1980,

the dates of the inspection at the North Anna facility for inspection

report 50-338/80-13 arid 50-339/80-14 were incorrectly identified as

March 17 through 21, 1980. The enclosed cover letter corrects this

error to show the correct dates of March 24 through 27, 1980. We request

you replace the original inspection letter with the enclosed letter.

We apologize for the inconvenience of this error.

E.c.

R. C.

ewis, Acting Chief

Reactor Operations and Nuclear

Support Branch

Enclosure:

Cover Letter

cc:

W. R. Cartwright

Station Manager

Box 402

Mineral, VA 23117

P. G. Perry

Senior Resident Engine'r

e

Post Office Box 38

Mineral, VA 23117

, , -

+