Responds to Re Delays in OL Application Reviews. Full Review Schedules Are Being Developed for Licensing of Docketed Applications.Delays Resulted from TMI-2 Accident
ML19331A268
Person / Time
Site: Wolf Creek, Callaway  Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 06/23/1980
From: Ahearne J
NRC COMMISSION (OCM)
To: Kassembaum N
SENATE
Shared Package
ML19331A267 List:
References
NUDOCS 8007110568
Download: ML19331A268 (1)


Text

_ _.

f,,)I -

lt UNITED STATES oe Z

j NUCLEAR REGULATORY COMMISSION

, 9, p,$ '

W ASHIN GTON, D.C. 20555

%j %<4,/

p ne U, M OFFICE OF THE CHAIRMAN The Honorable !!ancy Landon Kassebaum United States Senate Washington, D.C.

20510

Dear Senator Kassebaum:

In your letter of May 16, 1980, you expressed concern about delays in the Nuclear Regulatory Commission (NRC) review of_the operating license applica-tions for two nuclear power plants being constructed in Missouri and Kansas.

Specifically, you indicated the financial impacts which may result from licensing delays.

In addition, you requested that the NRC staff initiate ar.d develop a schedule for the timely review and licensing of the Callaway and Wolf Creek plants.

The Commission and its staff are concerned about the Callaway and Wolf Creek applications and have recently taken steps to minimize the potential for delays. The following actions have occurred for both plants:

(1) the Final Safety Analysis Report acceptance reviews were initiated during the week of May 5,1980, and the completion date for the acceptance review has been scheduled for July 1980, and (2) the environmental report acceptance review completion dates have been scheduled for September 1980.

We are currently developing the full review schedules for the licensing of all docketed applications, including the Callaway and Holf Creek 21 ants.

Although 11ere has t;een an unrecoverable dis ruption in our normal review process as a result of the TMI-2 accident, we are endeavoring to minimize further licensing delays as much as possible.

I am mindful of the economic hardship that can occur as a result of delays in the operation of nuclear power plants and am working to avoid any unnecessary delays while at the same time givino priority to my responsi-bilities to ensure continued protection of the health and safety of the public.

I am pleased to have had this opportunity to respond to your comments and trust that this information is responsive to your concerns.

ISin rely,,

(

3 j

Jo n F. Ahearne Chairman

-8007110568

.