.r~y Bechtel Power Corporation Engineers-Constructors 15740 Shady Grove Road Gaithersburg, Maryland 20760 301-258 3000
.u G2, r:r July 22, 19s0 JUL 2 81980 Of fice of Inspection & Enforcement cc:wce[.
-,..,c.,,.
U.S. Nuclear Regulatory Cocsission Region II 101 Marietta Street, N.W.
Suite 3100 Atlanta, Georgia 30303 Attention:
Mr. J. P. O 'Reilly, Director
Dear Mr. O 'Re illy :
Nuclear QA Is Applicable Middle South Energy, Inc.
Grand Gulf Nuclear Station Bechtel Job No. 9645 File:
0260/0512 Final Re port for Bechtel Power Corporation Deficiency Report No. J-80/01 in Compliance with 10CFR 21' V3-80/0268 Our letter of April 24, 1980, forwarded to you, in accordance with 10CFR Part 21, a report of a deficiency at the Grand Gulf Nuclear Station concerning Fase=ount 1151A pressure transmitters.
Our letter also stated that we are investigating -
the matter and would report further within 90 days.
Since that time, your of fice has issued IE Bulletin No. 80-16 which identifies the Rosemount 1151A pressure transmitter problem.
On the Grand Gulf Nuclear Station, further investigation has revealed that there are ten (10) each Rosemount ll51A transsitters on Unit 1 and Unit 2 purchased by the Bechtel Power Corporation which are basic cesponents and =ay produce erroneous outputs when over-ranged or under-ranged in their present applications. Our corrective action will consist of replacing these transmitters with new transmitters
.t.ich do not have this same ambiguous characteristic in the, over-range and under-range condition, and which are qualified in accordance with IEEE 223-1974 and 1EEE 344-1975.
Further details of the follow-up action specific to the Grand Gulf Nuclear Station (GCNS) will be su-=ari:ed in Bechtel Management Correc tive Ac tion Re po rt, GGNS-72 and will be available for your review at tha CGNS construction site,
i For other Eechtel Power Corporation projects with construction per=its, f urther reports will be provided to you in response to IE 3ulletin 30-16.
T g
I 1.
i 1
q g.
s 8008070$O
\\==,/
r i
e Bechtel Power Corporation U.S. Nuclear Regulatory Com::21ssion July 22 1980 Bechtel Job No. 9645 VB-50/02'68 This completes our response to the reporting requirements of 10CFR 21.
Should you require any additional info:mation, please so advise.
Very truly yours,
J.
. Jar P oject Manager JCClub b ec: J.
'P. McGaughy, Jr.
fil L. F. Dale, 2 C. K. McCoy T. H. Cloninger J J. Reaves A. Zaccaria J. M. Kocies B. K. Kanga Dr. D. C. Gibbs R. A. O 'Neil L. E. Ruhland D. M. Lake R. E. Brosm R. L. Scott
/