770
<
.
.
UNITED STATES
[p "%,*o,,
NUCLEAR REGULATORY COMMISSION
- \\ '
ft
REGloN IV
E , ( d ,I
oo
611 RYAN PLAZA DRIVE, SUITE 1000
g % //pj
/
ARLINGTON, TEXAS 76012
June 23, 1980
.....
In Reply Refer To:
RIV
Docket No. 50-498/Rpt. 80-09
50-499/Rpt. 80-09
Houston Lighting and Power Company
ATTN:
Mr. E. A. Turner, Vice President
Power Plant Construction and
Technical Services
Post Office Box 1700
Houston, Texas
77001
Gentlemen:
This refers to the investigation conducted by Messrs. D. D. Driskill and
P. E. Baci of our staff during the period April 15-18, 1980, of activities
authorized by NRC Construction Permits No. CPPR-128 and 129 for the South
Texas Project, Units No. 1 and 2, concerning allegations of attempts to
intimidate QC inspectors and other employees and that the termination of
these employees was for reasons other than those stated by the contractor,
Brown and Root.
The investigation and our findings are discussed in t:
L enclosed investigation
,
'
report.
Within the scope of the investigation, no items of noncompliance or deviations
were identified.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
. , Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
I'.
investigation report will be placed in the NRC's Public Document Room.
If the
report contains any information that you believe to be proprietary, it is
necessary that you submit a written application to this office, within 20 days
of the date of this letter, requesting that such information be withheld from
public disclosure.
The application must include a full statement of the reasons
why it is claimed that the information is proprietary. The application should
be prepared so that any proprietary information identified is contained in an
enclosure to the application, since the application without the enclosure will
also be placed in the Public Document Room.
If we do not hear from you in this
regard within the specified period, the report will be placed in the Public
Document Room.
80072801 %
.
s
.
.
Houston Lighting and Power
Company
-2-
. June 23,1980
Should you have any questions concerning this investigation, we will be pleased
to discuse them with you.
Sincerely,
,
? f,
l
h
N.
4
K.V.Seyfrht
Director D
Enclosure:
IE Inspection Report No. 50-498/80-09