Forwards IE Insp Rept 50-333/80-10 on 800514.No Noncompliance Noted
ML19330A414
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 06/17/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Pasternak R
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML19330A415 List:
References
NUDOCS 8007280071
Download: ML19330A414 (2)


See also: IR 05000333/1980010

Text

. ___ . - _ _ _

'

"

TA

'

%g$

g

UNITED STATES

[

NUCLEAR REGULATORY COMMISSION

~

j

,, j

REGION 1

et

'g

431 PARK AVENUE

q

-

KING OF PRUS$1 A. PENNSYt.V ANI A 19406

JUit 1 7' G

.

DN 50-333

Power Authority of the State of New York

James A. FitzPatrick Nuclear Power Plant

ATTN: Mr. R. J. Pasternak

4

Resident Manager

P. O. Box 41

Lycoming, New YC.k 13093

,

Gentlemen:

Subject:

Inspectiv. No. 50-333/80-10

T!iis refers to the inspection conducted by Mr. A. Finkel of this office on May

14, 1980 at the James A. FitzPatrick Nuclear Power Plant, Lycoming, New York oi

activities authorized by NRC License No. DPR-59 and to the discussions of our

findings held by Mr. Finkel with Mr. V. Childs of your staff at the conclusion

of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10. Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room.

If this report contains

any infomation that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must be

accompanied by an affidavit executed by the owner of the infomation, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790. The information sought to be withheld shall be incorporated as far as

possible into a separate part of the affidavit.

If we do not hear from you in

this regard within the specified period, the report will be placed in the Public

Document Room. -

80872 80 C>7 /

..

.

Power Authority of the State of New York

2

No reply to this letter is required; however, should you have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely.

-

~r~

/ klY

o ert T. Carlson, Chief

Raactor Construction and Engineering

Support Branch

Enclosure: Office of Inspection and Enforcement Inspection

Report Number 50-333/80-10

cc w/ encl:

George T. Berry, President and Chief Operating Officer

P. W. Lyon, Senior Vice President-Nuclear Generation

A. Klausmann, Director, Quality Assurance

M. C. Cosgrove, Quality Assurance Supervisor

J.<F. Davis, Chairman, Safety Review Committee

V. J. Pratt, Assistant General Counsel

G. M. Wilverding, Licensing Supervisor

l

l

l