VIHOINIA ELecraic AND Powen Co>tmNy Hrcumono,Vruora sA 20261 July 10, 1980 Mr. Harold R. Denton, Director Serial No. 610 Of fice of Nuclear Reactor Regulation N0/FHT:ms Attn:

Mr. B. Joe Youngblood, Chief Docket No. 50-339 Licensing Branch No. 1 License No. NPF-7 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Denton:

NORTH ANNA POWER STATION UNIT NO. 2 ADDITIONAL 'IMI - RELATED DATED REQUIREMENTS In response to a request from your staff, Virginia Electric and Power Company hereby commits to completing action on the following dated requirements by

),

January 1,1981:

A.

Item I.C.6, Procedures for Verification of Correct Performance of Operating Activities.

We will review and revise, as necessary, procedures for verifying the correct performance of operating activities.

'B.

Item II.K.3.C.3.2, B & O Task Force Final Recommendation.

We will submit a report documenting the various actions that have been taken to decrease the probability of a small-break LOCA caused by a stuck-open FORV and how, these actions have constituted a significant improvement in safety.

C.

Item II.K.3.C.3.5, B & O Task Force Final Recommendation.

We will submit an evaluation of alternative meant of meeting the requirements of 10 CFR 50.46 other than by tripping the reactor coolant pumps following a small-break LOCA.

8007140l$7

o Vaaoista EtzcTa:C AND Powra CowrAn T Mr.

Harold R.

Denton 2

D.

Item II.K.3.C. 3.17, B & O Task Force Final Recommendation.

We will propose Technical Specification changes that would limit the cumulative outage times for ECC systems based on operating experi-ence with similar systems.