Forwards IE Insp Repts 50-445/80-14 & 50-446/80-14 on 800513-16.No Noncompliance Noted
ML19329F831
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/23/1980
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Gary R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML19329F832 List:
References
NUDOCS 8007110229
Download: ML19329F831 (2)


See also: IR 05000445/1980014

Text

. _ _

__

_

_ . _ . .

-____ -

- - _ - - - - - - -

_

?

C

.

UNITED STATES

P "otg'o

NUCLEAR REGULATORY COMMISSION

.

O 'i ,

.

611 RYAN Pt.AZA DRIVE, SUITE 1000

'

REGloN IV

5 g,j @. ij

ARLINGTON, TEXAS 76012

E

o

h

o, - y

4 ..v

May 23, 1980

...

In Reply Refer To:

RIV

Docket No. 50-445/Rpt. 80-14

50-446/Rpt. 80-14

i

Texas Utilities Generating Company

ATTN:' Mr. R. J. Gary, Executive Vice

President and General Manager

2001 Bryan Tower

Dallas, Texas

75201

Gentlemen:

This refers to the inspection conducted by Mr. L. D. Gilbert of our staff during

the period May 13-16, 1980, of activities authorized by NRC Construction Permits

No. CPER-126 and 127 for the Comanche Peak facility, Units No.1 and 2, and to

the discussiou of our findings with Mr. R. G. Tolson of your staff at the

conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examination of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of the inspection, no iteme of noncompliance were identified,.

'

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

"

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room. If.the

report contains any information that you believe to be proprietary, it is

necessary that you submit a written application to this office, within 20 days

of the date of rhis letter, requesting that such information be withheld from

public disclosure.

The application must include a full statement of the reasons

why it is claimed that the information is proprietary. The application should

i

be prepared so that any proprietary information identified is contained in an

enclosure .to the application, since the application without the enclosure will

also be placed in the Public Document Room.

If we do not hear from you in this

regard within the specified period, the report vill be placed in the Public

Document Room.

.

i

800711011Y

.

.-

- -

- - - -

-

..

--

.

Texcs Utilities Generating Company

2

May 23, 1980

Should you have any questions concerning this inspection, we will he pleased

to discuss them with you.

Sincerely,

/

W. C.

eidle, Chief

y

T'

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report No. 50-445/80-14

50-446/80-14

cc: w/ enclosure

Texas Utilities Generating Company

ATTN:

Mr. H. C. Schmidt, Project Manager

,

2001 Bryan Tower

Dallas, Texas 75201

-

..

,

..