Forwards Insp Rept 50-346/70-02 on 700610-11.Results Indicate Program Adequate Except Responsibility for Interfacing W/Becthel
ML19329B221
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/02/1970
From: Vetter W
US ATOMIC ENERGY COMMISSION (AEC)
To: James O'Reilly
US ATOMIC ENERGY COMMISSION (AEC)
Shared Package
ML19329B199 List:
References
NUDOCS 8001310569
Download: ML19329B221 (1)


Text

.,

O July 2, 1970

~

J. P. O'Reilly, Chf ef, Reactor Inspection and Enforcement Branch Division of Compliance, Headquarters TOLEDO EDISON COMPANY (DAVIS-BESSE)

DOCKET Nu, 50-346 The subject facility home offices, located in Toledo, Ohio, were visited on June 10 and 11, 1970, to conduct an Initial QA Audit.

The results of the audit indicate that the applicant's QA program documentation is adequately consistent with Part 50, Appendix B, and that the QA program has been satisfactorily implemented as related to the progression of the project to date. Moreover, it appears that sufficient planning and staffing will exist to assure timely QA program development, i.e., program completion well in advance of needs.

A possible exception to the above involves QA program responsibility

)

interfacing (Bechtel-to-Toledo. Edison) and line responsibility consider-gd ations within the Bechtel organization. We intend to review this matter further, with the applicant, during the QA audit management interview which is currently scheduled to occur on, or about, July 16, 19'10.

j

~

W. E. Vetter Senior Reactor Inspector

Attachment:

CO Rpt No. 346/70-2 by G. Gower, F. Dreher, and J. Sutton dtd 7-1-70 (17 mats) f