Forwards IE Insp Rept 50-346/76-14 on 760713-15 & Notifies of Violation
ML19329B131
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/30/1976
From: Jordan E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Roe L
TOLEDO EDISON CO.
Shared Package
ML19329B132 List:
References
NUDOCS 8001300708
Download: ML19329B131 (2)


See also: IR 05000346/1976014

Text

- _ _ - _ - - - _ _ _ - _ _ _

_ - _ _ _

__- - -

__- __

_.--

. _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ - -

.

Elf 4

UNITED STATES

.

NUCLEAR REGULATORY COMMISSION

Py

O

4

REGloN lll

799 ROOSEVELT ROAD

'

QLEN ELLYN. ILLINQl5 60137

'

JUL 3 01976

-

Toledo Edison Company

Docket No. 50-346

ATIN: Mr. Lowell E. Roe

Vice President

Facilities Development

Edison Plaza

300 Madison Avenue

Toledo, Ohio

43652

c

Gentlemen:

This refers to the inspection conducted by Mr. K. R. Naida of

this office on July 13-15, 1976, of activitias at Davis-Besse

Nuclear Power Picat Station, Unit 1 authorized by NRC Construction

Permit No. CPPR-80 and to the discussion of our findings with

you and others of your staff at the conclusion of the inspection.

A copy of our report of this inspection is enclosed and identifies

O

the areas av =inari during the inspection. Within these areas,

the inspection consisted of a selective av==4 nation of procedures

and representative records, interviews with plant personnel, and

observations by the inspectors.

During this inspection, certain of your activities appeared

to be in noncompliance with NRC requirements, as described

under Enforcement Items in the Summary of Findings section of

the enclosed inspection report.

The' inspection showed that

action had been taken to correct the identified noncompliance

and to prevent recurrence. Consequently, no reply to this

noncompliance is required and we have no further questions

regarding this matter at this time.

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this

letter and the enclosed inspection report will be placed in the

NRC's Public Document Room, except as follows.

If this reports

contains information that you or your ccatractors believe to be

proprietary, you must apply in writing to this office, within

'

twenty days of your receipt of this letter, to withhold such

.

c**" %

!

5

s

.

!

k

h

800

3300 7c)6

.

p

l

we.#

.

O

.

-

.

.

.

- -

- . -

_ - . - - . .

_

_

_ _ _ _ _ _ - - _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

-

_

.

JUL 3 01976

Toledo Edison Company

-2-

information from public disclosure. The application must

include a full statement of the reasons for which it is claimed

that the information is proprietary, and should be prepared so

the proprietary infor=ation identified in the application is

contained in a separate part of the document. Unicss we receive

an application to withhold information or are otherwisa contacted

within the specified time period, the written material identified

.

in this paragraph will be placed in the Public Document Room.

We will gladly discuss any questions you have concerning this

inspection.

'

Sincerely yours,

E. L. Jordan, Acting Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report