ML19327A458
| ML19327A458 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 07/23/1980 |
| From: | Mcguire P BOSTON EDISON CO. |
| To: | NRC OFFICE OF MANAGEMENT AND PROGRAM ANALYSIS (MPA) |
| Shared Package | |
| ML19327A459 | List: |
| References | |
| 80-149, NUDOCS 8008060219 | |
| Download: ML19327A458 (1) | |
Text
.
+
N
' Edb4:n -
1.;R:M l.CL3 - ?C : :~
o p c,
, = -
1 p;v
,,,,s_,---
July 23, 1980 BECo Ltr #80-149 Director Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Docket No. 50-293 License DPR-35 Subj ect: June, 1980 Monthly Report (Revised)
Dear Sir:
In accordance with PNPS Technical Specification 6.9.A.2, a revised copy of the Operational Status Summary for Pilgrim Nuclear Power Station is attached for your information and planning.
This revision changes information on line 23 of the Operating Data Report and on the Unit Shutdowns and Power Reductions Report for the month of June 1980.
Respectfully submitted, P.J'. McGuire Station Manager Nuclear Operations
/js cc: Director Office of Inspection and Enforcement Office of Nuclear Regulatory Commission U. S. Nuclear Regulatory Commission Washington,' D.C. 20555 Direction of Region I Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 08 5
//
8088000,2/ 7
(