ML19327A420

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Rept 50-341/80-09 on 800610-13.No Noncompliance Noted
ML19327A420
Person / Time
Site: Fermi 
Issue date: 06/30/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Hines E
DETROIT EDISON CO.
Shared Package
ML19327A421 List:
References
NUDOCS 8008060180
Download: ML19327A420 (2)


See also: IR 05000341/1980009

Text

[

'o

UNITED STATES

~ , ,

'c

8

NUCLEAR REGULATORY COMMISSION

n

a

REGION ill

t

,

f[

799 ROOSEVELT ROAD

G

%,

,o '

GLEN Et. LYN, ILLINOIS 60137

rJUN 3 0 G80

Docket No. 50-341

The Detroit Edison Company

ATTN:

Mr. Edward Hines, Assistant

Vice President and Manager

Quality Assurance

2000 Second Avenue

Detroit, MI 48226

Gentlemen:

This refers to the inspection conducted by Mr. E. W. K. Lee of this office

on June 10-13, 1980, of activities at Enrico Fermi Nuclear Station, Unit 2,

authorized by NRC Construction Permit No. CPPR-87 and to the discussion of

our findings with you and others of your staff at the conclusion at the

conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of

a selective examination of procedures and representative records, obser-

vations, and interviews with personnel.

No items of noncompliance with NRC requirements were identified during

the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the en-

closed inspection report will be placed in the NRC's Public Document Room,

except as follows.

If this report contains information that you or your

contractors believe to be proprietary, you must apply in writing to this

office, within twenty days of your receipt of this letter, to withhold

such information from public disclosure. The application must include

1

a full statement of the reasons for which the information is considered

l

proprietary, and should be prepared so that proprietary information

identified in the application is contained in an enclosure to the appli-

cation.

l

'

8 o o 8 o 80 gibo

_.

.,

.e

The Detroit Edison Company

-2-

FJUN 3 01960

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

ovvu

G. Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection

Report No. 50-341/80-09

cc w/ encl:

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Ronald Callen, Michigan Public

Service Commission

Eugene B. Thomas, Jr.,

Attorney