Forwards Summary of 800627 Meeting W/Util in Atlanta,Ga Re HPCI & Reactor Core Isolation Coolant Sys Malfunction & List of Attendees
ML19326E255
Person / Time
Site: Hatch  
Issue date: 07/15/1980
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
References
NUDOCS 8008010011
Download: ML19326E255 (3)


Text

r

+

'o UNITED STATES 8

NUCLEAR REGULATORY COMMISSION o

g

<r REGION 11 j

0, 101 MARIETTA ST., N.W., SUITE 3100

%..... o ATLANTA, G EORGIA 30303 JUL 151980 In' Reply Refer To:

RII: PAT 50-321 50-366 Georgia Power Company Attn:.

J. H. Miller, Jr.

Executive Vice President 270 Peachtree Street Atlanta, GA 30303 Gentlemen:

This refers to the meeting cos. ducted at your request in the Region II office on June 27, 1980. This meeting related to activities authorized by NRC license numbers DPR-57 and NPF-5 and was attended by members of the Region II staff and R. J. Kelly and members of your company.

The subjects discussed at this meeting are described in the enclosed meeting summary.

It is our opinion that this meeting was beneficial and has provided for a better understanding of inspection and enforcement issues.

In accor-dance with section 2.790 of NRC's " Rules of Practice", Part 2, Title 10, Code of Federal Regulations, a copy of this letter and enclosures will be placed in the NRC's Public Document Room.

Should you have any questions concerning this matter, we will be pleased to discuss them.

Sincerely, E c.

R. C. Lewis, Acting Chief Reactor Operations and Nuclear l

Support Branch

Enclosures:

1.

Meeting Summary 2.

Attendance List cc's w/encls:

M. Manry, Plant Manager C. E. Belflower, Site QA Supervisor W. A. Widner, Vice President and General Manager 80080108//

m

I j.

4 MEETING

SUMMARY

Licensee: Georgia Power Company Facility: Hatch 1 and 2 License Nos.: DPR-57 and NPF-5 Docket Nos.: 50-321 and 50-366

Subject:

High Pressure Coolant Injection (HPCI) and Reactor Core Isolation Coolant (RCIC) System Malfunction On June 27, 1980, representatives of Georgia Power Company met with NRC Reg' ion II t

personnel in Atlanta, Georgia. The purpose of the meeting was to discuss with the licensee their schedule and planned corrective actions regarding the failure of the HPCI and RCIC systems to perform as designed following a reactor trip on Hatch 1, on June 26, 1980.

The licensee gave a presentation which outlined programs for determining the cause for system failures, the review of plant practices and activities which may affect system performance and a comprehensive test program to ensure that a

HPCI and RCIC systems perform as designed. An NRC representative acknowledged Georgia Power Company's presentation and emphasized the need to closely review for adequacy the surveillance procedures, the test requirements and personnel technical training as they apply to the HPCI and RCIC systems.

It was noted that a followup meeting would be held in Region II office to discuss the results of the licensee investigations and retest programs.

4 CY &

V/4Av F. A. Taylor Date Signed

Aj.

j ATTENDANCE LIST Attendance at the GPC-NRC meeting on June 27 1980, at the Region II Office.

Office of Inspection and Enforcement, Region _II James P. O'Reilly, Director F. J. Long, Deputy Director

. R. C. Lewis, Acting Chief, Reactor Operations and Nuclear Support Branch C. A. Julian, Reactor Inspector P. 0. Taylor, Reactor Inspector Georgia Power Company R. J. Kelly, Vice President, Power Generation W. A. Widner, Vice President and General Manager, Nuclear Generation J. T. Beckman, Manager of Nuclear Generation z

b..
  • '