Requests Time Extension to Replace Barton Transmitters to Third Refueling Outage of Unit 1,Lot 1.Replacement of Unit W/Refueling Consistent W/Current Transmitter Availability as Previously Discussed
ML19326E019
Person / Time
Site: North Anna  
Issue date: 07/22/1980
From: Sylvia B
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton
Office of Nuclear Reactor Regulation
References
646, NUDOCS 8007250415
Download: ML19326E019 (2)


Text

VrworNIA ELucrunc Axn l'owen Co>tmxy Rucusioxo,VxuoxxxA nacon July 22, 1980 Mr. Harold R. Denton, Director Serial No. 646 Office of Nuclear Reactor Regulation N0/FHT:jmj Attn:

Mr. Robert A. Clark, Chief Docket Nos. 50-338 Operating Reactors Branch No. 3 50-339 Division of Licensing License Nos. NPF-4 U.S. Nuclear Regulatory Commission NPF-7 Washington, D.C.

20555

Dear Mr. Denton:

NORTH ANNA POWER STATION UNIT NO. 1 REPLACEMENT OF LOT 1 BARTON TRANSMITTERS

?^

Based on discussions with members of your staff, we are requesting an extension of the time to replace the North Anna Unit 1 Lot 1 Barton Transmitters to the third refueling outage of the unit. The current commitment calls for trans-mitter replacement at the second refueling outage.

We have discussed the replacement of North Anna Unit 2 Barton Lot 1 transmitters and your staff has agreed that rep k_ement at the second Unit 2 refueling is consistent with current transmitter availability.

Since the current commitment to replace the Unit 1 transtaitters at the second refueling outage (late Fall, 1980) cannot be achieved due to the unavailability of qualified transmitters, we wish to delay replacement until the third re-fueling. This would put replacements at both units in the same time period and insure the availability of qualified transmitters.

We believe that this schedule is the best that the availability of transmitters can support and will not compromise the reliability of the presently installed transmitters.

8007250'//6

vlucixia EncTunc up Powru COMPANY TO Mr. Harold R. Denton 2

If you have questions,-or require additional information, please contact us.

Very truly yours, f

B. R. Sylvia 8

i Manager - Nuclear Operations and Maintenance cc:

Mr. B. Joe Youngblood, Chief Licensing Branch No. 1 Division of Licensing Mr. James P. O'Reilly Of fice of Inspection and Enforcement Region _II

1 L