- q_
e e
9 4 g OPERATING DATA REPORT 8911170041 891108 DOCKET NO. 50-301 PDR ADOCK 0"AOO266 R
FDC DATE October 12, 1989 COMPLETED BY C. W.
KRAUSE TELEPHONE 414 221 2001 OPERATING STATUS
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT UJIT 2
. NOTES
- 2. REPORTING PERIOD: SEPTEMBER 1989
- 3. LICENSED THERMAL POWER (MWT): 1518.5
- 4. NAMEPLATE RATING (GROSS MWE):
523.8
- 5. DESIGN ELECTRICAL RATING (NET MWE):
497.
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):
509.
- 7. HAXIMUM DEPENDABLE CAPACITY (NET MWE):
485.
8.
IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
NOT APPLICABLE
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANT (NET MWE): NOT APPLICABLE
- 10. REASONS FOR RESTPICTIONS, (IF ANY): NOT APPLICABLE THIS MONTH YR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 720 6,551 150,480
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 535.0 6,331.6 132,433.8
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.6 216.7
- 14. HOURS GENERATOR ON LINE 530.0 6,232.7 130,329.3
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 4.8 302.2
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 776,161 9,372,690 185,318,524-
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 265,520 3,216,010 62,889,710
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 252,200 3,070,816 59,925,238
- 19. UNIT SERVICE FACTOR 73.6 95.1 86.6 2C. UNIT AVAILABILITY FACIOR 73.6 95.2 86.8
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 72.2 96.7 81.4
- 22. UNIT CAPACITY FACTOR (USING DER NET) 70.5 94.3 80.1
- 23. UNIT FORCED OUTAGE RATE O.0 2.0 1.2
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
NONE
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: November 10, 1989 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22, 1977
.. ~.