. OPERATING DATA REPORT.
4
.J'"
DOCKET NO.._50-354 UNIT > Hope Creek
~
D DATE'10/16/89 COMPLETED'BY'
_H.
'Jensen t
-TELEPHONE (609) 339-5261
.CPERATING' STATUS' L1'. LREPORTING PERIOD September 1989_ GROSS HOURS IN REPORTING PERIOD 720 Up 2.
- CURRENTLY AUTHORIZED' POWER' LEVEL-(HWt) 3293
~ ' ' '
1 MAX' DEPEND. CAPACITY, (MWe-Net).
1031 s.
DESIGN ELECTRICAL RATING-(MWe-Net) 1067 MAX,~ DEPEND. CAPACITY ~(MWE-GROSS) 1076 13. iPOWER LEVEL TO WHICH RESTRICTED (IF ANY). MWe-Net)
None
(
4.<
REASONS:FOR RESTRICTION-(IF ANY) t THIS-YR.TO-MONTH DATE CUMULATIVE
, y. :5.
NO'.iOF HOURSLREACTOR WAS CRITICAL _ 356.9 5739.0 20,686.6
/
6.-
REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 Y7.
HOURS GENERATOR ON LINE 345.1 5,721.9 20,354.0 J
8..
UNIT. RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 9.>
GROSS THERMAL ENERGY GENERATED (MWH)t 800,240-17,736,164 63,739,878 10.
GROSS: ELECTRICAL ENERGY
. GENERATED (MWH) 263,450_
5,840,079
_21,066,525 11'1..- ' NET ELECTRICAL' ENERGY GENERATED (MWH) -
244,303
_5,576,898 20,126,918 6
12.-
REACTOR ~' SERVICE FACTOR 49.6 87.6 84.8 c 13." REACTOR AVAILABILITY FACTOR 49.6 87.6 84.8 "14.
- UNIT SERVICE FACTOR 47.9 87.3 83.5__
15. UNIT AVAILABILITY FACTOR 47.9 87.3 83.5 f16. ' UNIT CAPACITY FACTOR i
'(Using MDC) 32.9 82.6 80.1 i
17..
UNIT CAPACITY FACTOR l
(Using Design HWe) 31.8 79.8 77.4 18 '.
UNIT FORCED OUTAGE RATE 4.5
- 1. 2._
5.7 E19.
SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION):
NONE
- 20.. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:
11/10/89 h[d A b