Provides Schedules Established for Completion of Eight long-term Corrective Actions Initiated by Util in Response to 890913 Event at Plant in Which Reactor Protection Sys Provided Abnormal delta-T Power Indications
ML19324B835
Person / Time
Site: Fort Calhoun 
Issue date: 10/31/1989
From: Morris K
OMAHA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LIC-89-991, NUDOCS 8911080360
Download: ML19324B835 (2)


Text

f Omaha Public Power District 1623 Harney Omaha, Nebraska 68102 2247 402/536 4000 October 31, 1989 LIC-89-991-U. S. Nuclear Regulatory Commission Attn: Document Control Desk 4

Mail Station PI-137 i

i Washington, DC 20555

References:

1.

Docket No. 50-285 2.

Letter OPPD (K. J. Morris) to NRC (Document Control Desk) dated October 4, 1989 (LIC-89-888) 3.

Letter NRC (J. L. Milhoan) to OPPD (K. J. Morris) dated October 20, 1989 Gentlemen:

SUBJECT:

Delta-T Power Anomaly Event - Long Term Corrective Actions This letter provides the schedules established for completion of eight long term corrective actions initiated by 0 PPD in response to an event at Fort Calhoun Station in which the Reactor Protective System (RPS) provided abnormal delta-T power indications. This event, which occurred on September 13, 1989, is detailed in Reference 2, and was further discussed at an OPPD/NRC conference held October 5,1989, in Arlington, Texas.

Reference 2 described preliminary corrective actions and indicated that additional corrective action was being i

considered. Subsequently, eight long term corrective actions were identified I

by OPPD and presented to the NRC at the October 5, 1989 conference.

The following schedule has been established for OPPD's long term corrective actions:

' Revise procedures on senior plant management notification - December l

a 31, 1989 Evaluate the schedule on Alarm Procedures Upgrade - November 30, 1989 m

Review procedures to clarify on-shift responsibilities - December 31, a

1989 Implement Technical Specif'. cation Interpretation procedure - January m

15, 1990 l

Investigate proceduralizing actions for future operability e

determinations - April 30, 1990 Improve the screening process for industry information - December 15, m

1989 gjlog>OCK360 e91032 N

050002e5 l

S PDC

-. ~ _

. as sin tmpioumgungoppommau

l r

(n.

  • O

' U. S. Nuclear Regulatory Commission LIC-89491 Page 2 Review Technical Specifications for actions needing time clarification e

- February 15, 1990 Review our investigative procedures to lower the threshold for m

initiating investigation - December 15, 1989 If you should have any questions on these schedules or the corrective actions initiated by 0 PPD, please contact me.

Sincerely,

/ ?!Y K.

. Morris Division Manager Nuclear Operations KJM/pje c:

LeBoeuf, Lamb, Leibv & MacRae R. D. Martin, NRC Regionel Administrator A. Bournia, NRC Project Manager P. H. Harrell, NRC Senior Resioent Inspector

.