October 19, 1989 3 ocket No. 50-289 D
Mr. Henry D. Hukill, Vice President and Director - TKi-1 GPU Nuclear Corporation P. O. Box 480 Middletown, Pennsylvania 17057
Dear Mr. Hukill:
SUBJECT:
POST-flRE SAFE HUTDOWN METH0 OLOGY - GENERIC LETTER 81-12 FESPONSE 1MI-1 TAC NO. 04951 The NRC staff, with technical assistance from its consultant, has completed itsreviewofGPUNuclear's(GPUN)responsestoGenericLetter81-12onthe i
subject of alternate plant shutdown capability following a fire as discussed i
in Section !!!.G.3 of 10 CFR 50 Appendix R.
With the exception of three open i
issues as discussed below, the staff has concluded that the THI-1 provisions l
for alternate shutdown capability conform to the guidance in Generic Letter i
81-12. The results of the staff's review of this matter are contained in the enclosedTechnicalEvaluationReport(SAIC-89/1147).
l ort Section 2.8) discusses the history of Technical TheenclosedrefTS)
Ssecifications or equipment associated with alternate shutdown cap-l ability. The present staff position is that these TS are required. TMI-1 has no such TS. This issue is being pursued on a ger.eric basis as part of i
the TS Improvement Program. Therefore, this issue is likely to remain open pending completion cf the generic effort. The other two open issues irnolve overcurrent protection for associated circuits and are presently under review by the staff. The results of that review will be reported in a future letter i
to you.
i Sincerely,
/V Ronald W. Hernan, Senior Project Manager l
Project Directorate 1-4 i
Division of Reactor Projects 1/II Office of Nuclear Reactor Regulation i
Enclosure:
1 As stated cc w/ enclosure:
i g
03$88If IM[c,g*
See next page M
? Plant File BBoger RHernan EJordan(HHBB3302) ACTS (10)
NRC & LPDRs SVarga(14L4) $Norris OGC BGrimes (9A2)
[GENLTRTAC64951]
pFoi PM:PDI-4,h D
i l
LA I@
ta f PD:PI SN s
RHerman:dr Pto '
10 89 10fy/89 16///89
[s
~
" I[ f.,h o
UNITED STATES
{
'h NUCLEAR REGULATORY COMMIS$10N I
)!
i wasswotow. o. c. rosss October 19. 1989 Docket No. 50-289 l
.l Mr. Henry D. Hukill, Vice President I
and Director - TNI-1 i
GPU Nuclear Corporation i
P. 0. Box 480 Middletown, Pennsylvania 17057
Dear Mr. Hukill:
t
SUBJECT:
POST-FIRE SAFE SHUTDOWN METHODOLOGY - GENERIC LETTER 81-12 I
RESPONSE TM1-1 (TAC NO. 64951) t i
I The NRC staff, with technical assistance from its consultant, has completed its review of GPU Nuclear's (GPUN) responses to Generic Letter 81 12 on the subject of alternate plant shutdown capability following a fire as discussed in Section !!!.G.3 of 10 CFR 50 Appendix R.
With the exception of three open issues as discussed below, the staff has concluded that the TMl-1 provisions l
for alternate shutdown capability conforta to the guidance in Generic Letter t
81-12. The results of the staff's review of this matter are contained in the enciesed Technical Evaluation Report (SAIC 89/1147).
i The enclosed report (Section 2.8) discusses the history of Technical l
Specifications (TS) for equipment associated with alternate shutdown cap-
.. l ability. The present staff position is that these TS are required.
TMI-1 has no such TS. This issue is being pursued on a generic basis as part of the TS Improvement Program. Therefore, this issue is likely to remain open i
pending completion of the generic effort. The other two open issues involve overcurrent protection for associated circuits and are presently under review by the staff. The results of that review will be reported in a future letter l
to you.
Sincerely.
} VY RonaldW.Hernan,SeniorPo$tManager Project Directorate I-4 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page
y C
'l Mr. Henry D. Hukill Three Mile Island Nuclear Station, L
GPU Nuclear Corporation Unit No. 1 cc:
G. Broughton Francis 1. Young 0&M Director, TMI-1 SeniorResidentInspector(TMI-1)
GPU Nuclear Corporation U.S.N.R.C.
Post Office Box 480 Post Office Box 311 Middletown, Pennsylvania 17057 Middletown, Pennsylvania 17057 Richard J. McGoey Manager PWR Licensing (PU Nuclear Corporation U.f.ional Administrator, Region I Re Nuclear Regulatory Comission l
- 00 Interpace Parkway 475 Allendale Road Parsippany, New Jersey 07054 King of Prussia, Pennsylvania 19406 C. W. Smyth Robert B. Borsum TMI-1 Licensing Manager Babcock & Wilcox GPU Nuclear Corporation Nuclear Power Generation Division Post Office Box 480 Suite 525 Middletown, Pennsylvania 17057 1700 Rockville Pike Rockville, Maryland 20B52 Ernest L. Blake, Jr., Esq.
Governor's Office of State Planning Shaw, Pittman, Potts & Trowbridge and Development 2300 N Street, N.W.
ATTN: Coordinator, Pennsylvania Washington, D.C.
20037 State Clearinghouse Post Office Box 1323 Harrisburg, Pennsylvania 17120
~
Sally S. Klein, Chairman Thomas M. Gerusky, Director Dauphin County Comissioner Bureau of Radiation Protection Dauphin County Courthouse Pennsylvania Department of rront and Market Streets Environmental Resources Harrisburg, Pennsylvania 17120 Post Office Box 2063 Harrisburg, Pennsylvania 17120 Kenneth E. Witmer, Chairman Board of Supervisors of Londonderry Township 25 Roslyn Road Eilzabethtown, PA 17022 Mr. Henry D. Hukill, Vice President and Director - TMI-1 GPU Nuclear Corporation P. O. Box 480 Middletown, Pennsylvania 17057