Ack Receipt of 800515 Interim Deficiency Rept Re post- Tensioning Anchorhead Failure.Requested Extension Until 800630 for Submittal of Final Rept Is Acceptable
ML19323G480
Person / Time
Site: Byron  
Issue date: 05/23/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
References
NUDOCS 8006020564
Download: ML19323G480 (1)


Text

-.

~

TIC c,m m'o UNITED STATES

[,.\\ g-g NUCLEAR REGULATORY COMMISSION

.a t r REGION 111 o

799 ROOSEVELT ROAD GLEN ELLYN, ILLINOIS 60137 WAY 2 3 900 Docket No. 50-454 Docket No. 50-455 Commonwealth Edison Company ATTN:

Mr. Cordell Reed Vice President Post Office Box 767 Chicago, IL 60690 Gentlemen:

Thank you for your interim report dated May 15, 1980, pursuant to 10 CFR 50.55(e) regarding post-tensioning anchorhead failure.

We will complete our review during a future inspection when your final report and significant test data are available.

Based on review of the interim report, your requested extension to June 30, 1980 for submittal of the final report on this matter is acceptable.

Your cooperation with us is appreciated.

Sincerely, y" h

~

G. Fiorelli, Chief Reactor Construction and Engineering Support Branch cc:

Mr. D. L. Peoples, Director of Nuclear Licensing Gunner Sorensen, Site Project Superintendent Central Files Reproduction Unit NRC 20b PDR Local PDR

_ NSIC TIC Mr. Dean Hansell, Office of Assistant Attorney General Myron M. Cherry, Chicago 8006020 % f

.