Advises of Suspension of IE Bulletin 80-08 Review Due to Ongoing Feasibility Study.Review Will Resume If Study Indicates Continuing W/Facilities as Nuclear Units
ML19323G373
Person / Time
Site: North Anna  
Issue date: 05/28/1980
From: Brown S
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
IEB-80-08, IEB-80-8, NUDOCS 8006020277
Download: ML19323G373 (1)


Text

_

May 28. 1980 Mr. James P. O'Reilly, Director Serial No. 347/040780 Office of Inspection & Enforcement PSE&C/SGE:jpj U. S. Nuclear Regulatory 80 mission Region II Docket Nos. 50-404 101 Marietta Street, Suite 3100 405 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

I.E. BULLETIN 80-08 EXAMINATION OF CONTAINMENT LINER PENETRATION WELDS As you know, Virginia Electric and Power Company is perfonning a feasibility study of North Anna Units 3 and 4.

For the duration of this study, we have curtailed our activities, most notably in nuclear related areas. Therefore, we have suspended our review of the subject Bulletin.

We will resume our review of this Bulletin if the study indicates continu-ing with North Anna Units 3 and 4 as nuclear units.

If there are any questions, please cont,act us.

,,7 h

Very uly u

,j/

' 0 /l' C!l[ pap -

/

Sam,C. Brown, Jr' Senior Vice President - Power Station Engineering and Construction j cc: Mr. Victor Stello, Director Office of Inspection & Enforcement VMr. Harold R. Denton, Director Office of Nuclear Reactor Regulation 4

8 00602 o GNQ

.. -