ML19323D093

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-322/79-24 on 791211-800319.Noncompliance Noted:Failure to Identify Nonconformance & Improper Weld Rod Requisition Forms
ML19323D093
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 04/23/1980
From: Christopher R, Mcgaughy R, Remaklus L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19323D091 List:
References
50-322-79-24, NUDOCS 8005210075
Download: ML19323D093 (61)


See also: IR 05000322/1979024

Text

____ _ - _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

i

'

.

800521007 5

O

'

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION I

Report No.

50-322/79-24

Docket No.

50-322

License No.

CPPR-95

Priority

--

Category

B

Licensee:

Long Island Lighting Company (LILCO)

175 East Old Country Road

,

Hicksville, New York

11801

)

Facility Name:

Shoreham Ruclear Power Station, Unit 1

Investigation At:

Shoreham, New York

Investigation Conducted:

December 11, 1979 through March 19, 1980

M-ll- 90

Investigators:

O.

J/

^

C. O.

11ina,' h.D.,

Investigation Specialist

date

C

Y//y/Ao

L. M. Narrow Reactor Inspector

date

Nk4j

W W TD

j

p.P.eDurr,ReactorInspector

d6 e

'

beskM

L y se

S. D. Reynoldih, Jr. , Reactor Inspector

date

// N

w

. C. Higg~iits, S . R sident Reactor Inspector

'

dte

4]$l.

+

I4

20

'

F) H. Nicholas,

ctor Inspector

I date

.

- /b8 d

i

1/

R. K. Christoph

' Investigation Spec'f alist

date

'

Wtt<L

1

v'

Y ll$b

L. /P. Remaklus, Ihvdstigation Specialist

date

,

d MT

9 ' 13 ' O

Reviewed By:

'

%

R. W. McGaughy/Cnfef, Project Section

date

RC&ES Branch

l

'

Region I Form 143

.

,

l

(Rev. October 1977)

i

._

.-_ __ -

_.

.

__

_ _ - - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -

- - ______

.

-

.

.

-

Investigation Summary:

Investigation from December 11, 1979 through March 19, 1980 (Investigation

Report Number 50-322/79-24)

Areas Investigated:

The investigation covered thirty (30) allegations related

to construction irregularities at the Shoreham site.

The allegations were

made via court testimony, personal interviews, magazine articles and alleged

phone calls by third parties to one of the known allegers. The investigation

involved 410 man-hours on-site by three (3) NRC investigators and (5) NRC in-

spectors.

Results:

Of the thirty (30) allegations investigated, none were found to be

substantiated.

During the course of the investigation, two (2) items of

noncompliance were identified: (1. Infraction - failure to identify nonconfor-

mance, Paragraph D.2; 2. Infraction - improper weld rod requisition forms,

Paragraph D.10)

!

!

I

2

__

_

..

-

.

'

TABLE OF CONTENTS

I. BACKGROUND

i

A.

Reason for Investigation

B.

Identification of Involved Organizations

II. SU M RY OF FINDINGS

,

A.

Allegations and Investigation Findings

B.

Items of Noncompliance

l

C.

Management Meeting

III. DETAILS

A.

Introducti..n

B.

Scope c' Investigation

l

C.

Perso .s Directly Interviewed and/or Contacted During the NRC Investi-

gatr on

D.

NRe., Investigation Findings and Conclusions Related to Allegations

IV. EXHIBITS

A.

Referenced Codes, Specifications and Procedures

B.

Notice of Investigation

!

i

3

__ -

-

_ -- _

.-_

_

.

___ -

. _ _

_ _ _ -

.

-

,

.

.

I. BACKGROUND

"

A.

Reason for Investigation

,

The Nuclear Regulatory Commission (NRC), Office of Inspection and Enforce-

ment, Region I, was first informed of potential construction irregularities

at the Shoreham Nuclear Power Station (SNPS) on December 1,1979 when the

NRC's Resident Inspector at the Shoreham site was contacted by Mr. Leighton

Chong, one of the defense attorney's for an individual charged with

trespassing at the Shoreham site during an anti-nuclear demonstration in

June of 1979.

During the week of December 3 through 10, 1979 additional

information concerning these irregularities was presented by Mr. Chong

j

and Mr. John Hall, a local independent TV producer. In addition, testimony

presented during the above referenced trial on December 6, 1979 and local

newspaper coverage thereof on December 7,1979 was also made available by

the NRC's Public Affairs Office. Based on the information received, the

NRC initiated an investigation into alleged construction irregularities

i

at the Shoreham site on December 11, 1979.

4

B.

Identification of Involved Organizations

1.

LONG ISLAND LIGHTING COMPANY (LILCO)

,

175 East Old Country Road

Hicksville, New York 11801

An electric utility licensed by the NRC to construct a nuclear power

plant under NRC Construction Permit No. CPPR-95. (Occket Number

50-322)

2.

STONE AND WEBSTER ENGINEERING COMPANY (S&W)

245 Summer Street

P. O. Box 2325

Boston, Massachusetts 02107

A company contracted by the licensee to perform various construction

management activities at the Shoreham site.

3.

GENERAL ELECTRIC COMPANY (GE)

175 Curtner Avenue

San Jose, California 95125

.

A company contracted by the licensee to provide the nuclear steam

supply system and related components at the Shoreham site.

,

4.

GENERAL ELECTRIC COMPANY, I&SE DIVISION (GE)

777 West Putnam Avenue

i

P. O. Box 6850

Greenwich, Connecticut 06830

4

- - -

_.___

-

..

- -

.

.

.

_ . . - _ . _

_.

- - _ _

__

._ - ___ ___

_ _______

_

_-_

___

e

,

l

'

A company contracted by ,he licensee to provide the turbine generator

and related components at the Shoreham site.

5.

DRAVO CORPORATION (DRAVO)

Neville Island

Pittsburgh, Pennsylvania 15225

A company contracted by the licensee to perform various construction

activities at the Shoreham site.

6.

COURTER & COMPANY (COURTER)

317 West 13th Street

New York, New York 10014

A company contracted by the licensee to perform various construction

activites at the Shoreham site.

7.

L. K. COMSTOCK & CO. INC. (COMSTOCK/ JACKSON)

155 East 44th Street

New York, New York 10017

i

A company contracted by the licensee to perrorm various construction

activities at the Shoreham site.

i

8.

REACTOR CONTROLS, INC. (RCI)

1245 South Winchester Boulevard

San Jose, California 95128

A company contracted by the licensee to perform various construction

activities at the Shoreham site.

'

9.

PROTECTIVE SPR/.Y PLASTICS, INC. (PSP)

1130 Crose Avenue

,

New York, New York 10472

.

A company contracted by the licensee to perform various construction

activities at the Shorehan site.

l

10.

REGOR CONSTRUCTION CO., INC. (REGOR)

P. O. Box F

i

East Northport, New York 11731

i

A company contracted by the licensee to perform various construction

activities at the Shoreham site.

'

11.

JOHN GRACE & COMPANY (GRACE)

34 Washington Parkway

Hicksville, New York 11801

5

. .

.-

.

-.

.

,

.

A company contracted by the licensee to perform various construction

activities at the Shoreham site.

12.

C. P. BENNETT/F&G CO., INC. (C. P. BENNETT)

231 Russel Street

Brooklyn, New York 11222

A company contracted by the licensee to perform various construction

activities at the Shoreham site.

13.

KTA-TATOR ASSOCIATES (KTA-TATOR)

3020 Montour Street

Coraopolis, Pennsylvania 15108

A company contracted by the licensee to perform selected QA/QC

j

activities at the Shoreham site,

i

)

<

e

6

.-

-

.

.

- ,

. _ - .

.

. . - - .

.

.

II. SUMMARY OF FINDINGS

A.

Allegations and Investigation Findings

This investigation involves allegations that were introduced by various

methods by several individuals.

The investigation was initiated on

December 11, 1979 as a result of the testimony of two individuals testi-

fying on behalf of the defendant in a trial related to trespassing charges

incurred at the Shoreham site in June of 1979.

On December 12, 1979 an

allegation was received in connection with the Shoreham site from an

unidentified alleger through a local shopkeeper. This allegation is

described and numbered 1 below.

On December 17, 1979, NRC investigatort

met with Witness A in the above referenced trial.

Witness A's allegations

are described and numbered 2 through 9 below.

On December 17, 1979 NRC

investigators met with Witness B in the above referenced trial.

Witness

B's allegations are described and numbered 10 through 18 below.

On

December 17, 1979, defense attorneys in abova referenced trial presented

NRC investigators with allegations from other witnesses who were not

called to testify and who wished to remain anonymous. These allegations

are described and numbered 19 through 21 below.

On December 17, 1979,

the defense attorneys also presented NRC investigators with allegations

from a former boilermaker F.t the site.

These allegations are described

and numbered 22 through 25 below*.

On January 9,1980, NRC investigators

met again with Witness A who presented three (3) additional .llegations

allegedly received by anonymous phone calls.

These allegat1ons are

described and numbered 26 through 28 below.

On February 26, 1980, NRC

investigators met again with Witness B at his request at which time

another allegation was introduced.

This allegation is described and

numbered 29 below.

Throughout the initial investigation, defense attorneys

reported that pressure was being applied by the licensee (LILCO) and/or

related unions in order to prevent workers from coming forth to the NRC

with information.

This matter was covered as a separate allegaticn and

numbered 30 below.

  • Knowledge of the existence of these allegations was made known to the NRC

Resident Inspector at the Shoreham site on or about December 12, 1979 and

appeared, in part, in an article published in Seven Days, Volume III, No.12,

dated October 26, 1979.

7

_

_

s

.

.

Allegations

NOTE:

The allegations listed below have been summarized for clarity. The

actual allegations are cited in detail in Section III of this investi-

gation report.

1.) Inspection of the N-11 steam lines revealed cracks which may require that

the entire system be replaced.

The NRC investigation found no evidence and/or information to substantiate

this allegation. (Details, Paragraph D.1)

2.) Following concrete placements for the Reactor Pedestal and Reactor Building

Primary Containment Wall, heaters were not used as required for curing

during the winter months of 1973-1974.

Similar conditions were allowed

to occur in the Radwaste Building during the winter months of 1974-75 and

1975-76.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.2)

3.) Following concrete placements for the Reactor Pedestal, Primary Containment

Wall, and Radwaste Building, forms were improperly stripped on the day

following concrete placement instead of the required seven (7) days.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.3)

4.) Following the stripping of concrete forms for the Reactor Pedestal and

Primary Containment Wall, large cracks, honeycombing deep enough to

,

expose the rebar and through-cracks were patched over with mortar prior

to inspection by QC.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.4)

5.) Cadwelds for rebar in the concrete located in the Reactor Building were

in some cases found to be loose with concrete poured over the loose

cadwelds.

The NRC investir tion found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.5)

6.) Rubber waterstops between concrete layers in the Radwaste Building were

'

not installed properly and sometimes omitted entirely.

1

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.6)

8

.

.

7.) A carpenter was permitted to weld studs to embedment plates used for pipe

supports in the North wall of the Radwaste Building even though he had

failed the welding test seven (7) times.

.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.7)

8.) Threaded tie rods without sleeves used as form ties for the Reactor

Pedestal were pulled from the concrete after it had set, leaving a void

in the wall. In some cases, large amounts of concrete were pulled from

the pedestal wall in this manner.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.8)

9.) Several through-cracks were observed in the Turbine Building wall that

separate it from the Reactor Building.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.9)

10.) During the first three weeks of February 1979, several dissimilar metal

welds were made with ER-308 and/or ER-316 weld rod instead of the required

ER-309 weld rod because welders claimed that it was too cold to return to

their foreman and have incorrect weld rod requisitions changed.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.10)

11.) In a covert attempt to use substandard materials, E-6018 electrodes were

used rather than the required E-7018 electrodes.

The NRC investigation found no evidence and/or informat!cn to substantiate

this allegation.

(Details, Paragraph D.11)

12.) A large scale repair on the feedwater condenser jacket was performed by a

Regor boilermaker instead of the usual Courter and Company steamfitter in

order to avoid having the crack reported to Courter QA personnel which

would have raised the issue as to the integrity of the entire jacket.

The NRC investigation found no evidence and/or information to substantiate

i.iis allegation.

(Details, Paragraph D.12)

13.) Due to the impraper estimation of the depth of the water table by LII.CO,

salt water is seeping through the Secondary Containment wall at the 8

foot level and around-the-clock efforts are being undertaken to pump the

water out.

9

,

i

I

!

_

-.

.__

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

.

.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.13)

14.) Stone and Webster lost its general contractor duties when it repeatedly

complained to LILCO about the incompetence and corrupt practices of its

contractors, such as Regor and Courter, which LILCO insisted on using.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.14)

15.) In addition to seven (7) major failures of hydroflushes of the primary

closed loop piping system, a gross failure on or about June 15, 1979

caused valves to pop and s section of pipe to be ejected 50 feet into the

air.

It was also alleged that the hydrostatic test of the system in

September of 1979 could not have been valid since it occurred too soon

after the gross failure in June 1979 to have permitted proper shutdown

and repair.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Par graph 9.15)

16.) The outfall pipes for the circulating water systems have n-ver been

properly anchored and due to the tidal action in Long Island Sound, have

shifted, broken and separated from the line itself.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.16)

17.) NDE technicians were not adequately qualified for the jobs they were

performing.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.17)

18.) Large quantities of green dye used for dye penetrant testing were being

discharged by b LCO without proper approval and are polluting Wading

River siellfish.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.18)

19.) Supervision of trade workers is inadequate and being performed by unquali-

fied indiJiduals.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.19)

20.) Qualification and training of subcontractor personnel at the Shoreham

site is inadequate.

10

__

- _ _ _ - _ _ _ _ - _

.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.20)

21.) Workers painting the inside of the Reactor Primary Containment were not

qualified and when discovered by the NRC, most workers were layed off but

the substandard work was not inspected and allowed to remain. It was

further alleged that the remaining workers completed the jobs and on one

occasion worked a 30-hour shift on methedrine.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.21)

22.) Tube support sheets in the condenser box were so misaligned that titanium

tubing which should fit loosely, was hammered into place resulting in

damage severe enough to cause a tube to break with the possibility of a

radioactive spill.

The NRC investigation found no evidence and/or information t9 substantiate

this allegation.

(Details, Paragraph D.22)

23.) Radiographic tests revealed that the longitudinal seam welds for the con-

denser box were improperly done and when opened for rework were found to

contain dirt, rubbish and weld rod stubs.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.23)

24.) Misalignment of the condenser tube support sheets required re welding so

often that in some cases the " mother material" around the weld had to be

cut out and replaced with a fresh substitute section.

The NRC investigation found no evidence and/or information ta substantiate

this allegation.

(Details, Paragraph D.24)

25.) Welds to be inspected are pre-marked by QA in order that the best welders

can be assigned to these jobs while other welds are made by lesser quali-

fied welders and never inspected. This resulted in a degradation of the

overall quality and resultant safety factors at the Shoreham site.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.25)

26.) Turbine foundation bolts were installed so far out of alignment that it

was necessary to chop out the concrete around the bolts, heat the bolts

and bend them into a "Z" shape in order to fit them to the foundation

plates.

11

.

.

,

.

.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.26)

27.) When concrete was placed in a cold joint on the 63' level of the Reactor

Primary Containment, a large amount of rubbish and trash was permitted to

remain within the form and the concrete placed on top of it.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.27)

28.) Soil percolation testing results were falsified and test results withheld

in LILCO's submission of this information to the NRC.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.28)

29.) Welder performance qualification records were postdated for welders who

qualified after performing welds for wh.ih they had not been qualified.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.29)

)

l

30.) Pressure was applied to construction workers by LILCO, its subcontractors

and/or related construction unions in order to prevent and/or discourage

J

workers from coming forth to identify construction defects and/or irreg-

i

ularities to the NRC.

The NRC investigation found no evidence and/or information to substantiate

this allegation.

(Details, Paragraph D.30)

8.

Items of Noncompliance

During the course of the investigation,'two (2) items of noncompliance

were identified related to concrete records and dissimilar metal welds.

Item No. I was corrected prior to the completion of the investigation.

1.) (79-24-01) Contrary to Criterion XVI of Appendix B of 10 CFR 50, the

licensee failed to identify the nonconformance of Concrete Placement

RS-4-12 with respect to curing requirements and consequently failed

to take appropriate corrective actions at the time.

(Details,

Paragraph 0.2)

2.) (79-24-02) Contrary to Criterion V of Appendix B of 10 CFR 50, the

licensee issued two (2) Weld Material Requisitions which indicated

ER-308 weld material instead of the required ER-309.

(Details,

Paragraph D.10)

12

..

_

_

______ _

l

,

,

i

l

C.

Management Meeting

,

A management meeting was held on March 19, 1980 with licensee representa-

tives at the conclusion of the investigation in order to discuss the

NRC's investigation findings. The following individuals were in attendance.

L. Narrow, Reactor Inspector (NRC)

J. C. Higgins, Sr. Resident Inspector (NRC)

J. P. Novarro, Project Manager (LILCO)

'

W. J. Museler, Assistant Project Manager (LILCO)

T. F. Gerecke, QA Manager (LILCO)

W. Hunt, Project Engineer for Construction (LILCO)

J. M. Kelly, FQA Manager (LILCO)

T. Arrington, FQC Superintendent (S&W)

A. F. Earley, Attorney (Hunton and Williams)

s

13

.

.--

. _ _ . _ _

. _ _

. _ _ _ _ _ .

._

_

.

.

!

III. DETAILS

l

A.

Introduction

This investigation was initiated as a result of the NRC-Region I being

i

informed of various alleged construction irregularities at the site of

the Shoreham Nuclear Power Station (SNPS).

The exact number of allegers

could not be determined due to the manner in which the allegations were

.

received, i.e., court testimony, personal interviews, magazine articles

and alleged phone calls by third parties to one of the known allegers.

The primary initiating event of the investigation was the testimony

provided on December 6, 1979 by two (2) former construction workers at

the Shoreham site who were defense witnesses for an individual charged

i

with trespassing during an anti nuclear rally at the Shoreham site in

June of 1979.

B.

Scope of Investication

This investigation included an examination of pertinent documents and

records at the Shoreham site and at the NRC Regional Office; interviews

and contacts with several licensee and contractor personnel (present and

former employees); observations by the investigators as well as independent

i

testing as applicable by the NRC through an outside testing laboratory

.

(The Franklin Research Center).

'

'

C.

Persons Directly Interviewed and/or Contacted During the NRC Investigation

During the course of this investigatior, representatives of various

subcontractors at the Shoreham site were contacted in order to set up

4

interviews with their employees.

The subcontractors contacted have been

delineated in Section I-B of this report.

The principal licensee repre-

sentatives were identified in Section II-C of this report.

l

Several licensee and' subcontractor personnel, present and former workers,

at the Shoreham site were interviewed by the NRC in investigating the

allegations contained herein.

In order to protect the identity of those

'

individuals, alphabetic designations have been assigned to individuals

noted within the context of the report only when such designations are

required in order to differentiate between the statements of one or more

,

l

of the individuals. Otherwise, descriptive designations (e.g. QC inspector,

welder, etc.) are used.

Throughout the investigation, sources of information were not identified

by name to persons being interviewed unless (a) such person was identified

by another independent document or person other than the source or (b)

the person being interviewed independently acknowledged the identity of

the source to the NRC. All' individuals interviewed were notified of the

voluntary nat.ure of the interview, the right to have another person of

their choice present during the interview, and the confidentiality provi-

sions of tMs investigation.

14

,

_

-

. _ .

_

. .

.

.

. . -

.

. .

.

_

_- _ _ - _ _ - - _ -

.. - _ __

- _

_

i

,

g

!

0.

NRC Investigation Findings and Conclusions Related to the Allegations

1.

Allegation No. 1

a.

Allegation

A random visual inspection of the Main Steam Line System (N-11)

revealed cracks which had to be repaired.

No further inspections

of the N-11 System have been undertaken, and it is alleged that

there are many other cracks in the system.

It was further

alleged that the entire N-11 System may be unfit and may have

to be repaired or replaced.

b.

NRC Investigation Findings

NRC investigators identified the extent of the N-11 System

referred to in the allegation by a review of all of the N-11

System isometric drawings, including a review of the history of

the piping from the steel mill to site ecection.

QA documents

on pipe irregularities were also reviewed as well as an inspection

of the piping itself.

The subject piping is that piping which carries main steam from

the isolation valve outside of Primary Containment to the Main

Steam Stop Valves for the Turbine.

This pipe is 24" 0.D., 900

psig rated SA-106, Grade B seamless carbon steel material

j

obtained for spool piece fabrication by DRAVO from U. S.

1

Steel.

The piping system was designed by S&W to ASME Section

III, Class 2 requirements.

The site welding was performed by

)

COURTER with inspections by COURTER and S&W surveillance in-

spection groups.

j

The NRC noted that manufacturing linear surface indications are

i

to be expected in pipe of this large a diameter and these

indications were acknowledged along with acceptance and repair

methods in Paragraph 20 of the material specifications for the

l

pipe. ASME NC-2550, 2551 and 2558 also indicate the acceptance

and repair methods for surface indications in this type of

pipe. NDE surface examination is not required by the code.

j

!

The NRC noted that the 0.D. of the pipe was visually examined

l

during site fabrication, prior to the installation of required

insulation material.

A total of fifty eight (58) COURTER

,

l

Deficiency Correction Orders (DCOs) were written describing the

surface irregularities as linear indications.

These documents

were included into COURTER Nonconformance Reports (NRs) NR-466

and NR-466A.

The disposition and correction of the problem was

also documented in S&W Engineering and Design Coordination

j

Report (E&DCR) F-18716 and F-22478.

The NRC determined that

l

the disposition was in accordance with SA-106 and NC-2250 code

'

l

15

.

requirements and included grinding to remove the vast majority

of the surface indications and repair welding of some defects

shown by ultrasonic testing (UT) to encroach on the minimum

wall dimensions.

NRC investigators interviewed the cognizant engineer who had

provided the disposition of E&DCR F-18716 and who was knowledge-

able of E&DCR F-22478.

The NRC also interviewed one of the

COURTER welders who worked on the repair of the linear indications.

Both individuals independently stated that the linear indications

identified were not cracks, but rather those types of metal

forming irregularities acknowledged in the material specification.

The S&W engineer indicated that the steam lines were completely

examined by visual methods and all linear indications were

dispositioned without any difficulties being encountered.

An NRC investigator visually examined all N-11 piping not

covered by insulation and found no signs of " linear indications"

but a large number of ground out areas as expected from the

DCOs.

One complete steam line had been previously inspected by

the NRC and this inspection was documented in NRC Inspection

Report No. 50-322/78-03. No items of noncompliance were identi-

fled in this area.

The NRC determined that the " cracks" ;a the main steam line as

reported in the allegation were in all probability a misinterpre-

tation of the normally occurring seams and laps found in material

of this kind and were not cracks, per se.

The disposition of

these visually observed linear indications more than satisfied

the minimum code requirements and no other deficiencies were

observed by the NRC in the N-11 System.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

1

'

2.

Allegation No. 2

a.

Allegation

Following concrete placements for the Reactor Pedestal and

Reactor Building Primary Containment Wall during the winter

months of 1973-1974, heaters used to maintain the required

curing temperatures were either not used, or when used were

permitted to go out for extended periods of time during the

night shifts.

It was also alleged that ice was allowed to form

on the concrete, a condition noticed when workers arrived in

the morning.

It was also alleged that the same conditions were

allowed to occur in the Radwaste Building during the winter

months of 1974-75 and 1975-76.

16

- ..

- _ - _ _ _ _ .

.

__

..

,

.

i

b.

NRC Investigation Findings

'

The NRC investigators reviewed applicable sections of S&W

specifications and QC procedures, including American Concrete

Insititute (ACI) standards referenced in these specifications.

These, as well as other selected specifications, standards and

procedures reviewed during this investigation are referenced as

Exhibit A of this investigation report.

The documents reviewed established as a requirement for the

winter curing of concrete that the temperature be maintained at

40* F or higher for mass concrete (pours in excess of 30" in

thickness) and 45* F for other concrete placements (pours in

excess of 8" in thickness).

The time period for this temperature

maintenance ranged from 2 to 3 days depending upon the concrete's

'

exposure to the elements, with a maximum allowable drop of 20*

F within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the removal of heat.

The NRC investigators irtterviewed several LILCO site QA personnel,

S&W QC personnel, S&W construction engineering and supervisory

personnel as well as ORAVO craft and supervisory personnel, all

of whom had been involved with concrete curing from 1973 through

1976.

From a review of procedures, documentation and these

interviews, the NRC was able to establish that the winter

control of curing temperatures was accomplished in the following

manner:

Concrete placements were contained within temporary enclo-

--

sures fabricated prior to placement of the concrete.

Heaters within the enclosure were provided.

These heaters

--

were maintained within the enclosures by laborers assigned

to each of the areas.

In the case of the failure of a

heater, it was either repaired immediately or replaced by

spare heaters provided for this purpose.

In the case of

damage to the enclosure itself, supervisory personnel were

notified immediately and crews were assembled to effect

the repairs.

Construction engineers took three (3) sets of temperature

--

measurements, (a) outside ambient, (o) ambient within the

enclosure and (c) concrete surfaca temperatures.* These

temperatures were taken daily inc;. ding weekends at not

less than 6-hour intervals.

In addition, the outside

"These surface temperatures were considered to be conservative since the

actual bulk temperatures of the concrete pour would have been somewhat higher

than the surface temperature due to the heat of hydration released during the

curing process.

l

17

.

_

__

. _ _ _ _ .

-

._.

.

..

.___ _ . - _ -

_ - _ _ _ - _ - _

-__

.

.

ambient temperature was obtained daily from a thermometer

which indicated the maximum and minimum temperature ex-

perienced during that time period.

The daily minimum

concrete and outside ambient temperatures were recorded on

specially designated Curing Reports.

Construction engineers

also stated that during extremely cold weather, additional

temperature readings were frequently taken. Temperature

,

readings below the minimum specified were reported to

Field QC personnel.

i

,

Field QC personnel performed periodic reviews of all

--

curing records to assure that the temperatures of the

concrete met curing specification requirement:.

Nonconforming conditions were written up on Nonconformance

--

and Disposition (N&D) reports for evaluation and disposition

by Engineering. Nonconforming temperatures reported by

Construction Engineering personnel were also written up on

N&D reports.

NRC investigators reviewed in detail over 150 written curing

reports for the time period from 1973 through 1976.

The areas

of the pours included concrete placements in the Reactor Pedestal,

the Reactor Building Primary and Secondary Walls anJ the Radwaste

Building.

During the course of this review, one (1) concrete

placement in the Reactor Secondary Wall (RS-4-12) was identified

i

with a recorded temperature of 38* F on December 3, 1974, the

second day of curing.

The NRC investigators reviewed in detail

all N&D reports for 1973 through 1976 written for failure to

maintain the required temperature during the curing period.

Six (6) N&D reports were found in this regard but it was noted

that Placement RS-4-12 had not been identified as nonconforming.

The dispositions of the six (6) N&Ds identified required the

l

removal of defective concrete if necessary and the testing of

the concrete with a Windsor Probe in order to demonstrate that

the compressive strength of the concrete conformed to the

'

construction specification.

The NRC identified no problems in

the disposition of these six (6) N&Ds.

The NRC investigators noted, however, that the failure to

identify the nonconformance of the RS-4-12 Placement with

respect to curing requirements and the failure to take necessary

corrective action was considered an item of noncompliance with

respect to 10 CFR 50, Appendix B, Criterion XVI which states,

in part, " Measures shall be established to assure that conditions

adverse to quality such as...nonconformance are promptly identified

and corrected."

(79-24-01)

!

18

4

Prior to the completion of the investigation, the licensee

reviewed the curing reports for all concrete placements made

from November of 1973 through February of 1980 (2156 in number)

under winter conditions (818 pours) and summer conditions (1338

pours).

Eight (8) additional placements were identified where

either (a) no temperature was indicated for a given day (b)

temperatures were identified which did not meet specification.

The lowest temperature recorded during the time periods of the

referenced winter placements was 37* F.

The referenced place-

ments were identified on N&D No. 2877 and 2909 and Windsor

Probe tests were performed and witnessed by Field QC.

Two (2)

tests of three (3) shots each were made on each placement.

Calibration procedures and test results were reviewed by NRC

investigators and no irregularities were noted.

In each case,

the average of three (3) shots showed the compressive strength

of the placements in question to range from 5200 psi to 6900

psi, well in excess of the design strength of 3000 psi.

The

item of noncompliance was considered resolved and NRC investi-

gators noted that the minor deviations identified would only

retard the early strength developed by the concrete and not

cause any permanent damage, a conclusion further verified by

the Windsor Probe tests.

NRC investigators could find no instances where concrete had

been exposed to freezing temperatures, a condition that would

I

have been evident even after the fact as the freezing would

cause the surface of the concrete to chip and flake away.

Of

all the individuals interviewed, none could remember any circum-

stances relating to freezing conditions on the concrete and/or

forms.

One laborer foreman stated " Occasionally one (heater)

would fail but it would be repaired quickly.

Laborers would be

circulating constantly to check on the heaters." He also stated

that in critical Meas additional laborers were assigned over

and above those making the rounds in order to keep the heaters

in operation.

c.

NRC Conclusion

Although the NRC identified isolated instances where heaters

had failed, this condition was to be expected and was corrected

by licensee contractors in a timely manner.

The NRC investigation found no evidence and/or information to

substantiate this allegation.

3.

Allegation No. 3

a.

Allegation

Following concrete placements for the Reactor Pedestal and

Reactor Primary Containment Wall as well as concrete placements

in the Radwaste Building made from the end of 1973 through the

19

. _

. _

_ . _

__

.

.

i

i

beginning of 1976, forms were improperly stripped on the day

following the concrete placement instead of the required seven

<

(7) days after placement.

l

b.

NRC Investication Findings

>

i

NRC investigators examined applicable S&W specifications and

ACI standards as referenced in Exhibit A of this report.

It

was noted that under ordinary conditions, when form removal is

not controlled by specification, wall forms may be removed

within 12 to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following concrete placement.

S&W specifi-

cations state that wall forms may be removed when the concrete

has achieved a minimum compressive strength of 500 psi and that

this strength should be achieved within one (1) day.

,

.

l

NRC investigators examined several recordc of the 24-hour tests

i

of concrete cylinders of 3000 psi concrete.

These tests indicated

that a range of from 789 psi to 1497 psi and an average strength

of 1173 psi had been achieved after 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

NRC investigators examined several curing reports and conducted

,

interviews with several S&W QC, construction engineering and

construction supervisory personnel, as well as DRAVO craft and

,

supervisory personnel involved in the piecement and stripping

of forework from 1973 through 1976.

Thase records and interviews

indicated that wall forms were removed after 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and that

this time period was closely monitored by QC and engineering

personnel.

The NRC noted that there was no ACI requirement or specification

requiring these forms to remain in place for seven (7) days,

although on occasion, forms were kept on for periods in excess

of the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> requirement.

This latter case was usually

dictated by work or location requirements such as when forms

could not be removed from the lower areas of the Reactor Pedestal

due to space limitations in that area;

Although various indivi-

duals noted that there might have existed some engineering

request for this particular extended support, the NRC could not

confirm that fact by any written engineering documentation.

No

irregularities were noted in this area.

The NRC noted that although the alleger claimed that the seven

(7) day stripping requirement was part of his training as a

carpenter's apprentice, no substantiation of this fact could be

obtained in the interviews of various craft personnel. As noted

earlier, the seven (7) day requirement did not exist.

c.

NRC Conclusion

The NRC investigation found no evidence and/or information to

substantiate this allegation.

'

4

20

._

__

_

_

_

.

_ _ _ - .

.

..~

.

.

_ _ .

_ _ _ _

.____ _ ..

. _ _ _ _

_.

__________ _

____ -_

.

.

d

4.

Allegation No. 4

a.

Allegation

,

j

!

Following the stripping of forms from concrete placements for

the Reactor Pedestal and Primary Containment Wall, large cracks,

honeycombing deep enough to expose the rebar and possible

through-cracks (cracks appearing at the same azimuth location

on both sides of the wall) were all patched over with mortar

prior to inspection by QC.

It was alleged that the patching

was performed by laborers in order to complete the work before

QC had an opportunity to inspect the concrete surfaces and the

patch work was done improperly, covering the honeycomb or crack

with a loose mortar mixture.

It was further alleged that

patching in this fashion was a common, almost daily practice

during the time that the alleger worked on site from 1973

through 3976.

b.

NRC Investigation Findings

NRC investigators examined applicable S&W specifications, ACI

standards and procedures for the repair of concrete (see Exhibit

A). The NRC also examined in detail all N&D reports of concrete

related defects in the Reactor Support and Primary Containment

Walls covering the period in question (1973 through 1976) and

interviewed several S&W QC inspectors, construction engineers,

construction supervisors as well as DRAVO craft and supervisory

personnel involved in the stripping of concrete formwork and

concrete repair.

All of the individuals interviewed were emphatic in stating

that the concrete repairs could not have been performed by

laborers. .The NRC noted that repair work of this type was under

the jurisdiction and contract of the cement finishers and that

the assignment of this work to laborers, or any attempt on the

part of laborers to perform this work, would in all probability

have resulted in a jurisdictional dispute which in turn would

have caused the job to be shut down by the involved unions.

Although the NRC realized the possibility of these conditions

and questioned the alleger if possibly he had meant the masons

.

(cement finishers) instead of the laborers, the alleger insisted

that it was the laborers and not the masons who had performed

the unauthorized repairs.

S&W QC personnel informed the NRC that they were required to

inspect all concrete surfaces after stripping and that they had

all been given verbal instructions to perform the inspection

within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the forms had baan removed.

QC inspectors

i

21

.

. .-.

-.

-

.

-

.-

.

.

I

1

stated that due to the nature of the repair work and mortar

i

used, any attempt at an unauthorized repair would " stick out

like a sore thumb" and lead the inspector to chip into the

patch in order to determine if a significant problem existed.

All personnel interviewed confirmed the repair of any honeycomb

or cracks prior to QC inspection would have been obvious to

'

anyone experienced in concrete work because of the difference

in surface color and texture between the poured concrete and

the patched area.

This was later confirmed by NRC investigators

as they examined various concrete pours throughout the plant.

Investigation of the aforementioned concrete related N&D reports

'

indicated that a report had been written for any honeycomb

which exposed rebar to one half of its diameter. A review of

the disposition of the N&D reports indicated that they included

a detailed repair procedure approved by Engineering.

The

repairs were inspected throughout by QC inspectors in order to

insure the removal of all defective material down to sound

concrete and subsequent repair in accordance with the specified

repair procedure.

Defects which did not expose the rebar

within the concrete were considered to be surface defects and

although not requiring a specific N&D report, were repaired

under QC supervision in accordance with ACI-301 and utilizing a

special concrete bonding agent.

The above repair requirements were confirmed by interviews with

involved cement finishers who stated "(There was) no way that

repair work could have been done without QC seeing it as soon

as the forms were raised. QC would be all over it."

Another

cement finisher stated "We won't touch a thing until QC has

looked at it. We never do any repair work on our own.

QC

watches everything, how the mortar is mixed, placed and set -

everything."

The NRC also noted through its interviews of several involved

personnel and related N&D reports that through-cracks were

unlikely due to the amount of rebar and due to concrete pouring

,

techniques. No through cracks were identified at the Shoreham

'

site in the areas examined.

c.

NRC Conclusion

The NRC investigation found no evidence and/or information to

-

substantiate this allegation.

!

.

22

.____

.. --

.__ _

__

.

__

_

._

.

5.

Allegation No. 5

a.

Allegation

Cadwelds of the rebar in the concrete located in the Reactor

Building were never x rayed and were in some cases found by the

alleger to be loose.

It was further alleged that several loose

cadwelds were found in the Reactor Building Outer Wall (Secondary

Containment).

b.

NRC Investigation Findings

NRC investigators examined applicable S&W specifications,

General Procedures and QC procedures for cadwelding (see Exhibit

A). These documents require that a specific number be assigned

to each cadweld and this number is stamped on the sleeve of the

individual cadweld. Each cadweld is subsequently inspected by

QC and marked to identify it as either satisfactory or unsatis-

factory and the sleeve number, welders symbol and result of the

final inspection are marked on a Cadweld Control Record.

In

addition to the inspection of completed cadwelds, QC is required

to monitor in process cadwelding activities on a random basis.

The location of all cadweld splices are noted on drawings by

Field QC and these drawings are maintained in the QC file.

NRC

investigators noted no irregularities or deficiencies in these

areas.

NRC investigators interviewed QC inspectors who had performed

inspections of cadwelding during 1973 through 1976.

It was

noted that each individual interviewed stated independently

that they had inspected each completed cadweld in addition to

pet .'orming several in process. inspections on a random selection

af cadwelos throughout the time period in questions. The NRC

noted that problems identified were infrequent and when identified

were corrected in accordance with accepted procedures.

The NRC

also noted that although no x-rays of cadwelding was required,

the integrity of the cadwelds could be determined satisfactorily

by mechanical and visual means. The NRC also determined that

the control, inspection and documentation procedures made it

unlikely that a loose cadweld would have been missed.

General Procedure W-300 provides for protective measures to be

taken if cadwelding which is in process cannot be completed by

the end of the shift. At first, it appeared that perhaps the

alleger may have observed a partially completed cadweld left

for completion on the next shift and assumed that it had been

completed and accepted.

This assumption had to be discounted

,

as a possible explanation for the alleger's observation since

l

it was determined that such occasions were infrequent and the

'

cadweld would have been wrapped in plastic clearly identifying

it as "in process" and incomplete.

i

23

'

l

.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

6.

Allegation No. 6

a.

Allegation

Rubber water stops between concrete layers in the Radwaste

Building were not installed properly (not sealed or nailed to

keys) and sometimes omitted entirely.

b.

NRC Investigation Findings

NRC investigators examined applicable S&W specifications, and

procedures for preplacement inspections i.e., inspections

performed prior to the placing of concrete (sco Exhibit A).

These documents require that prior to release for concrete

placement, the Field QC inspector shall complete the preplacement

inspection portion of the Field Data Sheet and sign the " Release

for Pour" block of the Concrete Pour Card. The "Preplacement

Inspection" portion of the Field Data Sheet includes waterstop

installation as one of the items to be inspected.

NRC investigators examined several Field Data Sheets and Concrete

Pour Cards for Radwaste Building concrete placements for 1973

through 1976, the period of employment of the alleger.

The NRC

identified no deficiencies or irregularities in this area as

all waterstop inspections had been performed as required and

the pour cards had been properly signed by QC.

In order to confirm these findings, NRC investigators interviewed

several S&W QC inspectors, construction engineers and construction

i

super'.isors, as well as DRAVO craft personnel and supervisors.

All of the individuals interviewed had been directly involved

in the installation, supervision of installation and inspection

'

of waterstops in the Radwaste Building. The NRC noted that none

of the individuals interviewed could recall any problem with

the installation of waterstops.

Craft personnel described the

method of sealing the joints as well as methods of holding the

waterstops in position using wooden blocks and wedges.

These

individuals also denied the use of any nails for attaching

waterstops. The NRC also noted that training had been given in

this area prohibiting the use of nails. QC personnel stated

that the waterstop installation for each concrete placement was

checked against the appropriate construction drawings as part

of the preplacement inspection in the same manner as other

embedments.

The NRC noted that several craft individuals

expressed mixed frustrations at times because of the several QC

24

. _ .

. _ _ .

..

-

.

inspections which had to be performed as the overall concrete

placement operation progressed.

None of the individuals,

however, reported any irregularities in these operations whether

they pertained to water stops or other involved inspection

criteria.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

7.

Allegation No. 7

a.

Allegation

The alleger stated that as a carpenter he had been permitted to

weld studs to embedment plates used for pipe supports located

in the North wall of the Radwaste Building.

It is further

alleged that the welding was allowed even though the alleger

had failed to pass the welding qualification test seven (7)

times. The alleger also stated that the work was ordered by a

carpenter foreman who provided him (the alleger) with the

needed welding rod.

b.

NRC Investigation Findings

NRC investigators examined the construction drawings (FC-25F-6

and FC-25K-6) which show the wall elevations and details of the

Radwaste Building in the area described by the alleger.

Drawing

FC-25F-6 depicts the "V" line wall as the North wall.

The NRC

noted that the drawings do not specify any cmbedment plates to

be located in the Parth wall.

NRC invest'igators vis.

/ examined the North wall of the

Radwaste Building and a; adjacent walls and surrounding areas

and noted only three (3) locations where embedments were required,

two (2) were for waste treatment equipment and one (1) was for

a roll-up door.

The NRC noted that there appeared to be no

pipe support embedments on the North wall of the Radwaste

Building.

Further investigation of the Radwaste Building

revealed that pipe support embedments were used very sparingly

in the entire building and that most of the pipe supports in

the Radwaste Building were of the concrete expansion anchor

type.

25

- _ . -

__

___

_ _____ _ __ _ _____

___

-

.

The NRC investigators reviewed the quality assurance program in

this area and noted that embedments were normally prefabricated

in shops adjacent to the construction area.

The embedments

were made of structural shapes such as plates, channels or

angles and manufactured studs were welded in rows to these

shapes.

The NRC noted that the welding was performed with a

" gun" which secures the stud and welds it under controlled

electrical conditions.

These controlled electrical conditions

provide a fairly uniform and repeatable weld.

In contrast, a

manually performed weld on studs of this relatively small

diameter would be extremely difficult to make in a uniform

manner even by an experienced welder much less by an individual

who could not pass the welding test.

The NRC noted that the quality assurance program not only

limited the number of people authorized to perform this welding

but also limited the number of people authorized to receive

welding rod and to sign the welding rod withdrawal form.

From

the standpoint of welder qualification, a review of all appli-

cable records and interviews with several DRAVO craft and

supervisory personnel indicated that (a) the number of qualified

carpenter / welders was very limited,* (b) very few carpenters

were ever selected to take the test and (c) an individual could

only fail the test twice, for if he could not pass it on the

second attempt, he was not allowed to take the test again,

The

NRC was also able to determine that the alleger was never

selected to take the welders test and consequently could not

have failed it one time much less seven (7) times as alleged.

From the standpoint of weld red issue, the NRC noted that the

quality assurance system closely controlled the issue of welding

i

materials to qualified personnel only.

The contractor involved

in these areas had only four (4) indi <iduals authorized by

letter to sign welding material withdrcwal slips.

The issue of

welding material was controlled by an irdependent group who,

j

without proper authorization, would not issue welding materials.

The NRC noted that the signature authorizing the withdrawal of

welding materials must be authenticated.

This was considered

important due to the fact that the carpenter foreman who al-

1egedly ordered the unauthorized welding and who allegedly

1

provided the weldir.g material was not authorized to withuraw

the material.

t

"only th T een (13) carpenters had been qualified in the past seven (7) y rs

t

.

26

i

I

-

-

_

_

_ _ _ , .

..

._

.

.

.-_

-

- . _ .

_.

_

_ ._

_ _ _ _ _ _

i

.

The NRC noted, therefore, that in addition to the fact that

there were no embedment plates used to hold pipes on the North

wall of the Radwaste Building, the alleger was not selected to

take the welding test, could not have failed it seven (7)

times, would have had difficulty obtaining welding rod because

he was unqualified and finally, determined that it was unlikely

he received welding material from a foreman who was not authorized

to sign weld rod withdrawal slips.

!

Ir order to further confirm the above findings, the NRC noted

that the Radwaste Building was designated as a Seismic Category

I structure, meaning that the quality assurance program applied

for safety related structures would require a "preplacement

inspection" for every concrete placement performed. 'This item

i

was documented on Field Data Sheets (Form T-S-31) and reviewed

by the NRC.

One of the attributes requiring quality control

inspectors sign-off was "Embedments".

The NRC interviewed five

i

(5) of the original QC inspectors for the Radwaste Building who

stated that all embedments were visually inspected for location,

i

conformance to drawing details, and restraint to avoid movement

!

during the actual placement of concrete.

Although interviewed

individually, all of the QC inspectors independ-ntly agreed

that a manually welded embedment would be readily :esognizable

and would have been immediately questioned.

To the best of

their knowledge no manually welded embedments were ever noted.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

'

8.

Allegation No. 8

a.

Allegation ~

The alleger stated that threaded tie rods were used as form

ties for the Reactor Pedestal along with she-bolts attached to

the rods to hold the forms in place.

It was further alleged

that whc.7 the she-bolts were removed, in many cases the threaded

rods would slide out of the concrete and a small patch would be

j

put on the hole leaving a void in the center of the concrete.

i

4

In some cases, it was alleged that when the she-bolts could not

j

be removed at one end, the entire tie rod was pulled through

'

the concrete pulling a large amount of concrete off the pedestal

wall.

It was alleged that rods were pulled through the concrete

approximately twenty (20) to fifty (50) times in this fashion.

,

27

-.

..

.- .. - .-.

- .

.

_ . - _ _ _ _ _ _ _ , - . ..

-

- . - -

_ _ _

___

_

_ _ _

.

.

,

b.

NRC Investigation Findings

NRC investigators examined several slides showing the actual

concrete forms in various stages of installation for concrete

placement for the Reactor Pedestal.

The NRC also interviewed

several QC and construction personnel in order to obtain infor-

mation concerning the use of threaded bolts for form ties.

The

information obtained indicated that in general, standard manu-

factured (Williams) form ties and she-bolts were used.

Although

threaded rods and she-bolts may have been used in certain

locations where the standard form ties did not fit the required

configuration, interviews with the above referenced individuals

could not determine these locations exactly.

The NRC noted

that either type of tie rod was acceptable, hence the matter

was not pursued further.

The MRC also noted that the alleger's statement that the threaded

rod would slide out of the concrete when the forms were stripped

appeared to indicate that the rods were installed in sleeves, a

fact which the alleger denied, stating that threaded rods not

in sleeves were pulled from the concrete after the concrete had

set. This was in apparent conflict with all of the individuals

interviewed who stated that even when threaded rods were used,

they were not in sleeves as the alleger stated but that they

definitely remained in the concrete after the forms were stripped,

ir. conflict with the alleger's statement.

l

The NRC did not attempt to pursue the matter further in order

to resolve the conflict due to the fact that (a) either method

of installation (with or without sleeves) was acceptable in the

Reactor Pedestal and (b) if the rods were installed without

sleeves as stated emphatically by the alleger, it would have

been physically impossible to remove them from the concrete

once it was set.

The NRC determined that the alleger's state-

ment that tie rods without sleeves were pulled out of the

concrete could not be considered as credible.

The NRC also

noted that had sleeves been used, patching the holes would not

have affected the structural integrity of the Reactor Pedestal,

nor was the Reactor Pedestal designed to maintain airtight

integrity.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

.

28

,

--

w

--

_

- - - -

-

,

- - , - -

r

~

w+,

. _ _ _ .

_ _ .

__.

- _ - _ _

_

_

.

.

9.

Allegation No. 9

a.

Allegation

Several through-cracks were observed in the Turbine Building

wall that separates it from the Reactor Building.

It was

further alleged that the cracks were so wide one could see

through to the other side of the wall.

b.

NRC Investigation Findings

The NRC noted that although the Turbine Building has a sheet

metal roof and upper wall which are designed to blow off during

a design basis tornado, the overall Turbine Building is not

seismically designed nor is any credit taken for leak tightness.

The design of the Turbine Building Ventilation System calls for

it to exhaust air from lesser to progressively greater potentially

contaminated areas to a monitored final exhaust.

Thus even if

a crack did exis t, its significance would be minimal. The NRC

noted further ttat there was no common wall between the Turbine

Building and the Reactor Building so a crack in the Turbine

Building wall wo11d not mean a crack in the Reactor Building.

In addition, any crack large enough to see through would be

difficult to patch on any permanent basis without the crack

opening up periodically.

On February 21, 1980, the NRC inspected the entire South wall

of the Turbine Building, the wall facing the Reactor Building.

Although several temporary openings were noted (cpenings scheduled

to be closed at a later date), no significant cracks were

identified.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

10.

Allegation No. 10

a.

Allegation

During the first three weeks of February 1979, welders were

asking for ER-309 weld rod in lieu of the ER-308 and/or ER-316

weld rod specified on their weld rod requisitions for scheduled

work oa dissimilar metal welds. When refused by the weld rod

clerk due to the improper designation on the weld rod requisition,

i

the welders stated that it was too cold to return to have the

I

requisition corrected to the required ER-309 and that the

j

l

29

. -

..

.. .--

.

1

-

.

ER-308 and/or ER-316 would be utilized in its place.

It was

!

alleged that these instances occurred two to three times each

l

day during the three week period in February of 1979.

The systems alleged to have been involved were the Control Rod

Drive System at Elevation 7C' in the Reactor Building; the Flow

and Pressure Instrumentation Lines in the T-?8 Primary Control /At-

mospheric Control System, the G-33 Reactor Water Clean-Up

System; and the G-41 Fuel Pool Cooling System.

b.

NRC Investigation Findings

NRC investigators reviewed in detail the flow diagrams of the

four (4) alleged systems involved in the allegation as well as

seven (7) additional systems.

These flow diagrams depict

material specification changes and pipe line numbers which can

be traced to a specific weld. This review identified (12)

dissimilar metal welds.

The document packages for each of

these welds were examined to verify that ER-309 weld rod was,

in fact, used to make the specified weids.

The result of this

examination revealed that one of the welds (Weld Joint Number

1G-33-WD9-3-1-FW "0") was welded on May 19, 1979 using ER-308

material.

No utilization of ER-316 was identified during this

review.

The licensee was informed that 10 CFR 50, Appendix B, Criterion

V requires in part, that " Activities affecting quality...shall

be accomplished in accordance with these instructions, procedures,

or drawings".

The COURTER and CO. Welding Procedure Specifi-

cation NW-100-01-08011AA, Revision 0, specifies that the filler

metal for this weld be AWS Class ER-309.

Contrary to the

foregoing, Wald Material Requisition No. 55780 was issued to

weld joint 1G-33-WD9-3-1-FW "D" specifying ER-308 material.

This was considered an item of noncompliance (79-24-02).

Based on this finding, two (2) separate and distinct reviews

were initiated by ooth the NRC and the licensee. All Category I

piping isometric drawings were reviewed and all dissimilar

l

metal welds were identified.

In addition, all Task Engineering

Component Checklists were checked and it was found that all

dissimilar metal welds were listed.

A cross check of these two

sources of information indicated that all dissimilar metal

welds had been identified. Four hundred and twenty two (422)

dissimilar metal welds were identified and cross checked in

this manner

The document packages for each of the 422 dis-

dicil: metal welds were examined in order to verify that

ER-309 material had been used as required.

The results of this

examination identified one additional weld (Weld Joint Number

30

.

.

.

_ _ _

____ -. .

_ _ _ _ . - - _________ ___

-

.

.

M50-CW3-3-99) welded on April 12, 1979 that also had been

welded utilizing ER-308 material.

None of the dissimilar metal

welds were identified as involving ER-316 material.

As an independent verification of the above findings, and due

to the fact that ER-308 material was found in two (2) of the

422 welds examined, NRC investigators listed all of the identi-

fiable ER-308 weld rod issues for the month of February 1979

from the weld rod control log.

This log listed the date and

use for each wald rod issue.

The weld rod issues were cross

referenced against the appropriate piping isometric drawing

which would identify any dissimilar metal welds.

Even if the

pipe line d'd not represent a dissimilar metal weld joint, on

isometric crawings which show more than one pipe line number,

any dissi.nilar metal weld depicted on the drawing was examined

in order to verify that ER-309 was in fact used. This independent

verification of over six hundred (600) log entries dispositioned

indicated no further discrepancies.

Independent cross checks

were also made by the NRC investigators on the completeness of

the dissimilar weld ter, ting and no discrepancies were identified

in this area.

NRC investigators interviewed all available principals involved

in the above referenced item of noncompliance.

Interviewees

included the Assistant Construction Manager, the welders who

made the welds, involved weld rod checks, welding supervisors,

area supervisors, assistant area supervisors and deputy foremen.

As a result of these interviews, the NRC was able to determine

that the misuse of ER-308 weld rod materials were relatively

isolated occurrences rather than any significant breakdown in

the licensee's construction QC program. The problem appeared to

stem from paperwork errors related to the similarity of procedure

numbers (08011AA for ER-309 and 0811AA for ER-308) and not a

deliberate attempt by the welder to utilize the improper weld

rod.

The two welds in question were cut from the system in the

presence of the NRC on March 4 and 5, 1980.

The removed welds

were bisected and analyzed independently by both the licensee

and the NRC to confirm the composition of the weld rod material

contained therein.

By chemical analysis, performed at the

Franklin Research Center, the NRC determined that the weld

material was in fact ER-308. Similar results were obtained by

the licensee using spectrographic and chemical analyses.

The NRC determined that all welding performed on the control

rod drive mechanisms was performed by Reactor Controls, Inc.

(RCI) which maintained its own weld rod issue facilities,

31

_

_

__

__

,

_

_ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

-

,

totally separate from weld rod issues of COURTER for whom the

alleger was employed.

It was impossible therefore for the

alleger to hava dispensed weld rod utilized for the control rod

drive mechanism.

This system was included nonetheless in the

NRC review and no irregularities were noted.

NRC investigators noted that the identification of the two

welds containing the improper weld material while constituting

an item of noncompliance, did not substantiate the related al-

legation due to substantial differences in time frame, scope,

causality and magnitude. The NRC also noted that the use of

ER-308 in place of ER-309, while not in compliance with specifi-

cations, would not have a significant adverse affect on the

structural integrity of the two welds in question, a conclusion

confirmed by the Franklin Research Center which stated that

both welds were sound and that they were deposited without

excessive base metal dilution.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

11.

Allegation No. 11

a.

Allegation

Although taught that only E-7018 electrodes were to be used at

the Shoreham site, E-6018 electrodes were issued to a single

welder who continually drew weld wire separately from other

welders. It was further alleged that the above practice was

performed in order to covertly use substandard materials.

b.

NRC Investigation Findings

NOTE:

The NRC noted that the ASME Code,Section II C,

SFA-5.1 does not list an E-6018 electrode. It was

assumed that the alleger meant E-6010 electeddes

which are listed in the ASME Code and are in common

use within the industry.

The NRC conducted several interviews with S&W QC inspectors,

construction supervisors, weld rod control supervisors and weld

rod issue clerks.

These interviews disclosed that the only

E-6010 electrodes used at the Shoreham site were utilized in

connection with the carbon dioxide fire system installed by the

C. P. Bennett Company.

The NRC noted that extremely rigid

32

.

.

controls had been imposed on the issue, use, handling and

return of the E-6010 electrodes in order to assure that their

use was limited only to this fire system. Each weld electrode

issue was counted and verified by the rod issue clerk, the

welder, a LILCO QC representative and a representative of C. P.

Bennett.

A similar procedure was followed when the unused weld

electrode and weld electrode stubs (used electrode) were returned.

A LILCO Work Directive (WD-PS-4894) directed the Bennett Company

to hire "...one Quality Control Inspector. Inspector's sole

responsibility will be to ensure that the E-6010 Series Welding

Electrode is used exclusively on the CO2 System pipe welding."

NRC investigators conducted an additional interview with the C.

P. Bennett General Foreman in order to confirm the above re-

ferenced procedures. No discrepancies were noted.

The General

Foreman stated that possibly no more than two (2) 50 pound cans

were used for the CO System and that only three (3) employees

2

were authorized to sign for the E-6010 electrode issue.

NRC investigators noted that the allegation was presented in

such a manner as to indicate that the licensee was covertly

attempting to introduce substandard material into the con-

struction project. Coworkers of the alleger indicated that this

was not credible since all involved individuals (including the

a11eger) were carefully informed that the strict procedure was

required in order to comply with the increased QC requirement.

In fact, one supervisor stated that the alleger was fully aware

of the purpose of E-6010 electrode and he (alleger) complained

that the procedures were too strict.

The NRC did not pursue

these conflicts further as it did not affect the evaluation of

the validity of the allegation.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

12.

Allegation No. 12

a.

Allegation

A large scale repair of a 10 to 20 foot crack was performed on

the feedwater condenser jacket by a REGOR boilermaker instead

of the usual COURTER and CO. steamfitter in order to avoid

having the crack reported to COURTER QA personnel which would

have raised an issue as to the integrity of the entire jacket.

It was also alleged that an exceedingly large quantity of weld

l

electrodes had been drawn in order to effect this repair.

33

__

,

.

.

b.

NRC Investigation Findings

NOTE:

The NRC was informed by the alleger of the welder's

symbol and the Weld Rod Requisition Number, which was

170376.

An NRC review of plant equipment disclosed that what was referred

,

to as the "feedwater condenser" was in fact the Main Turbine

Condenser. This condenser is located in the Turbine Building

and parts are located at the 63 foot level where the alleged

irregularity occurred.

In reviewing the time period in question,

the NRC noted that the condenser was hydrostatically tested and

a leak was found on or about August 25-28, 1978.

The leak was

located in the general area of the interconnect between the

'

condenser shells. Weld Rod Requisition Number 170376 was

confirmed by the NRC to have been issued on August 29, 1978 to

the welder identified by the alleger. The requisition was for

100 each, 3/32" diameter, E-7018 welding elect-odes for " repair

weld condenser."

The NRC review indicated that the 3/8" fillet weld on the

interconnect had been leaking and approximately 10 linear feet

of this weld had been removed in order to repair the leak. The

NRC noted that there was no " crack" in the strict sense of the

word. Due to the fact that the area which was leaking was

inaccessible from the outside of the interconnect and that the

exact location of the leak could not be pinpointed, the weld in

the immediate area of the leak as well as additional weld

material on either side was removed by air carbon arc gouging.

It was noted that the removal of the weld by air carbon arc

gouging would also remove some of the base material therefore

adding to the volume of weld metal needed to replace the weld.

The rewelding procedure would involve a minimum weld size from

1/2" to S/8" instead of the original 3/8" fillet weld.

NRC investigators performed calculations in order to determine

the number of 3/32" diameter welding rods needed to fill a 3/8"

X 10 foot * weld groove. The NRC determined that the issuance of

100 each, 3/32" diameter electrodes was not excessive relative

to the volume of weld deposited in the prepared grove.

^ Includes the cutting and repair of various stiffners which had to be removed

in order to gain access to the leaking area

34

.

.

.

-

.

__.

.

_ _ - _ _ _

.

.

!

i

The NRC noted that since REGOR was contractually responsible

for the work on the condenser, they were assigned to perform

the repair work and that the job would not have been assigned

to COURTER in any event.

The NRC noted no deficiencies and/or

irregularities in the repair operation.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

13.

Allegation No. 13

a.

Allegation

Salt water is seeping through the Secondary Containment Wall at

the 8' level and around-the-clock efforts are being undertaken

to pump the water out.

It was further alleged that the seepage

occurred due to LILCO's improper estimation of the depth of the

water table under the plant.

b.

NRC Investigation Findings

,

NRC investigators questioned several individuals working at the

i

Shoreham site concerning the allegation and were unable to

j

obtain any confirmation that any seepage had occurred.

The NRC

reviewed construction descriptions of the various waterproofing

methods and other means of preventing water seepage and deter-

mined that the possibility of seepage in this area was highly

unlikely.

In order to confirm the above. finding, the NRC personally

examined the areas in question during high tide on January 31,

1980, a date where according to local marina owners, tides were

expected to be their highest due to the full moon.

The NRC

noted that there was absolutely no indication of leakage or any

signs (e.g., water marks) that seepage had occurred in the

past.

In fact, the NRC noted that dust accumulations ia some

parts of the 8' level floors of the Secondary Containment

indicated that the area had not seen water for some time.

Interviews by the NRC of various LILCO personnel indicated that

on infrequent occasions in the past that some water might have

reached the 8' level from within containment due to leakage of

the temporary drain system or leaks from various hydrotests

above that level within the plant but that to the best of their

knowledge, no through-wall seepage problems had occurred in

this area.

,

35

. _ - _ . .

.

-

-

-.. . -

__

..

_ - .

- .

.

_

-

.

.

,

1

i

l

Interviews by the NRC of various S&W construction personnel

confirmed the above observations but added that a minor problem

had been experienced in the past with rainwater leaking onto

the 8' level floor through an unsealed spare penetration during

periods of heavy and sustained rainfall. The water wcs not

extensive and merely flowed to one of the several permanent

sumps located on that level for such purposes. S&W personnel

stated that when sump pumps were operated, the water from the

sump was held up for chemical analysis and filtering prior to

discharge to the store drain system in accordance with EPA

guidelines. The NRC Resident Inspector was present at this

penetration during a recent heavy rainstorm and no leakage

>

problems were identified. S&W representatives stated that when

the pumps had to be operated, they were operated by a repre-

sentative of the operating engineers' union in accordance with

union agreements and this condition would in all probability

remain in effect until the pumps were transferred from the

construction to the start-up group at which time automatically

,

operating systems would be employed.

,

From the standpoint of other pump opceations, the NRC noted

<

that pumps outside of Secondary Containment were merely pumping

i

water from the temporary drain system within the building into

exterior drains and no irregularities were observed with respect

i

to this practice.

The pumping operation was due to be gradually

phased out as the permanent drains within the building were

integrated into the overall drainage system. The NRC also noted

that extensive pumping operations were undertaken when the

concrete was initially poured several years ago but that this

t

was part of the normal dewatering operations conducted during

'

construction work of this kind and did not indicate any seepage

or water leakage problems or problems with any codes or other

requirements.

'

c.

NRC Conclusion

,

The NRC found no evidence and/or information to substantiate

this allegation.

14.

Allegation No. 14

.

a.

Allegation

Stone and Webster (S&W) lost its general contractor duties when

it repeatedly complained to LILCO about the incompetence and

corrupt practices of its contractors, such as COURTER and

j

REGOR, which LILCO insisted on using.

In August of 1978, S&W

1

was relegated to design, drafting and general QA duties while a

dummy corporation, UNICO, assumed QC duties, and COURTER QA

personnel assumed the QA field inspection duties.

,

36

..

.-

,

.

. _ .

.

.-._ .. ---

- . -

.. .

. . _ _ _

. _ _ _ _ _ _

,

,

b.

NRC Investigation Findings

NRC investigators examined the various changes in the management

of the Shoreham project.

Among the items reviewed was a memoran-

dum dated March 8, 1977 which documented a meeting between

representatives of LILCO, S&W and the ASME Subcommittee on

i

Certification. The subject of the meeting was S&W's application

for NA and NPT Certificates of Authorization which would have

allowed S&W to perform ASME Code work at the Shoreham site.

The ASME Subcommittee agreed to grant the Certificates of

Authorization subject to certain conditions, among which was

the transfer of the contract between LILCO and COURTER and CO.

to a contract between S&W and COURTER and CO. This condition

was prompted by the fact that the ASME required QC operations

to be performed by the actual contractor and not the subcontractor.

)

N L' investigators were informed that at this time LILCO was

considering changes in construction management, and in a memoren-

dum dated August 11, 1977 recommended that LILCO assume the

leading role in construction management with S&W retaining

responsibility for engineering and quality assurance.

As of

September 12, 1977 LILCO did assume the leading role in construc-

tion management. This change was effected by having LILCO

1

assume leadership of the joint S&W/LILCO unified construction

team (UNICO) through the appointment of a LILCO Construction

Manager reporting to a LILCO Project Manager rather than the

S&W corporate construction organization.

LILCO also increased

its participation in the UNICO organization by the transfer of

a number of qualified construction supervisors to Shoreham from

other LILCO departments.

As part of this change, LILCO decided to retain the COURTER and

CO. contract directly rather than transfer it to S&W.

Since

COURTER was now the contractor, the ASME would not allow S&W to

perform the code work as either LILCO or COURTER had to obtain

the ASME Certificate of Authorization.

Therefore, COURTER was

directed to obtain the ASME Certificate and in order '- do so

was given the responsibility for quality assurance (or their

work on site.

The ASME transition date was January 1, 1978.

The only reference to any changes occurring in August of 1978

was a memo dated August 28, 1978 where some duplication in the

inspection of non-safety related mechanical equipment and

insulation was corrected by transferring the responsibility

from the Construction Inspection Program (CIP) and FQC to the

CIP alone.

There were no complaints involved in the memo, only

'

l

non-safety related equipment was involved and the NRC determined

l

that there was no problem or irregularity associated with the

transfer.

37

_

._

.

The NRC noted that UNICO was formed prior to March of 1977. The

change of QC fucctions from S&W to COURTER was occasioned

primarily as a result of ASME requirements and not due to any

actions by S&W and/or COURTER.

NRC investigators also interviewed

several individuals involved in the S&W QC and COURTER QC

organizations and the referenced transition and were not able

to identify irregularities or deficiencies, either past or

present, resulting from this transfer of responsibility.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

15.

Allegation No. 15

a.

Allegation

At least seven (7) major failures of hydroflushes of the Primary

Closed Loop Piping System have occurred and during the flushing

'

of the system on June 15, 1979, a gross failure of the primary

system occurred involving valves popping and a section of pipe

being thrown fifty (50) feet into the air.

It was also alleged

that the hydrostatic test of the system in September of 1979

could not have been valid, since it occurred too soon after the

gross failure in June of 1979 to have permitted proper shutdown

and repair of the system.

b.

NRC Investigation Findings

The NRC reviewed all possible primary system hydrotesting

records and interviewed several involved personnel and could

not identify any major failures of the Primary Closed Loop

Piping System during the time period up through and including

June of 1979.

Examining the time frame around the alleged June

15, 1979 date, the NRC noted that on June 13, 1979, one minor

incident was identified where during the flush of the Core

Spray System, a temporary gasket in a bc1ted joint failed and

sprayed water over a large area.

There were no major failures

in the system, no valves failed nor were pipes thrown into the

air.

This review was documented in NRC Inspection Report No.

50-322/79-20.

The NRC investigators noted that the primary system hydrostatic

1

test was not conducted until September 21-22, 1979.

The NRC

reviewed all test procedures prior to the test, was present and

witnessed the actual performance of this test, and independently

38

_

, ---

. ._

_ _ .

_ - - _ _ _ _

_

.

.

.

verified the acceptability of the test results.

The NRC noted

no gross failures and the details of the test were documented

in NRC Inspection Report No. 50-322/79-15.

The NRC reviewed documents referred to them by the alleger and

found them to be outdated copies of normal check off sheets for

the hydrotests which he (the alleger) had taken off site prior

to his termination in May of 1979.

The NRC was unable to

reconcile the alleger's claim of having seen the gross failure

(June 1979) since he had terminated one month prior to its

allegedly having occurred. The NRC was also unable to reconcile

the alleger's statement that exclusive of repairs it would have

taken 4 to 6 weeks to shut down from the alleged failed test

due to the fact that the shutdown operation can be performed in

a matter of hours or at most days, depending on the procedures

utilized and the system involved.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

16.

Allegation No. 16

a.

Allegation

The diffuser (outfall) pipes for the circulating water system

have never been properly anchored and due to the tidal action

in Long Island Sound, have shifted, broken and separated from

the line itself.

It was further alleged that a LILCO QA map

documented the separated pipe pieces located in the Sound.

b.

NRC Investigation Findings

The NRC investigators noted that a similar 411egation had been

made by a contractor employee in 1978 and had been investigated

by the NRC in October of 1978.

The results of this former

investigation are documented in NRC Inspection Report No.

50-322/78-16.

i

NRC investigators pursued this matter further and interviewed

various individuals associated with the placement and securing

of the Offshore Discharge and Diffuser Pipe System.

The NRC

was able to determine that the fiberglas pipe sections were

placed on the floor of the Sound and then covered with a uinimum

of 3 feet of crushed stone (approximately 1.5" in size) and

then covered with a layer of armour stone (6" to 2' in size).

The NRC identified the fact that while the outfall was being

placed, prior to securing the outermost sections with stone,

storms caused various sections to work loose and suffer some

39

!

- _ .

. __

__ .

___

- -

_ _ - .

______

_ _ _ _ _ _ _ _

_ _ _ _ _ - _ _ _ _ _

.

.

damage.

A weekend storm of October 2-3, 1976 caused damage to

four (4) sections of the outfall,

This occurrence was covered

in N&D Report No. 1000.

Another storm from May 6 to 9,1977

caused damage to two (2) sections of the outfall, one of which

was ' replaced as documented in N&D Report No.1253.

In October

of 1977 an underwater inspection of the outfall verified that

it was secure but the inspection indicated minor damage to a

diffuser, a condition repaired and docun.ented in N&D Report No.

1466. The NRC identified no instance whereby secured sections

of the outfall had broken loose and separated from the system.

In attempting to determine the validity of the allegation with

respect to the map depicting the location of separated outfall

pieces, the NRC determined that a map of the outfall was po.ited

when the system was being placed and being secured by rock

The map and diagram indicated which sections had been covered

with the various sized rock and the flags indicated the lacation

of the barges containing the rock used to secure the pices and

'

not section of pipe which had broken loose.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

17. Allegation No.17

a.

Allegation

l

NDE technicians were not adequately qualified for the jobs they

were performing.

b.

NRC Investigation Findings *

NRC investigators examined prior NRC inspection reports for the

Shoreham site for the years of 1977, 1978 and 1979.

It was

noted that from January 1977 through June 1979, NRC inspectors

reviewed the qualification records and observed NDE technicians

performing tests during eight (8) inspections.

In addition, it

was noted that during welding inspections, NRC inspectors

- frequently include the inspection of the performance of nonde-

j

structive tests and also review the results of these tests,

'

observations that would not necessarily be reported unless

nononforming conditions were identified.

The NRC evaluation

indicated that no deficiencies in the qualifications or per-

'

formance of NDE technicians were identified during any of the

NRC inspections reviewed.

  • Due to the fact that no specific NDE technicians were identified by the

alleger, the NRC evaluated this allegation as it pertained in general to the

overall construction operation.

40

.

.

.

During this particular investigation, NRC investigators examined

a random selection of experience, training and qualification

records of NDE technicians currently at the Snoreham site.

This examination showed the men in question to have been ade-

quately qualified for the level of performance for which they

are certified and to a degree commensurate with their responsi-

bilities.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

18.

Allegation No. 18

a.

Allegation

Large quantities of green dye used for dye penetrant testing

were being discharged by LILCO without proper approval and that

this green dye was visible on the "outake" canal and polluting

Wading River shellfish.

b.

NRC Investigation Findings

l

The NRC assumed that since there is no "outake" canal at the

Shoreham site, that the alleger was infact referring to the

intake canal.

The NRC noted that LILCO had discharged

green dye to the Sound and that this matter had been identified

.by the NRC and dccumented in NRC Inspection Report No. 50-322/78-16.

During that inspection, the NRC inspector observed the green

color of the water in the intake canal at the screen wall and

\\ at the storm drain discharge in the canal.

The NRC requested

1 identification of the substance and examination of the discharge

permit provision which allowed the discharge.

LILCO representa-

tives identified the material as a fluorescent dye and identified

the individual within the New York State Department of Environ-

mental Conservation (NYS-DEC) with whom approvals had been

coordinated.

NRC environmental inspectors were notified and

subsequent contacts with NYS-DEC verified their cognizance of

the discharges and their acceptability.

NRC investigators examined the intake canal and adjacent shore-

fronts on Long Island Sound, including the most susceptible

areas of Wading River, and found no visible evidence of green

dye.

c.

NRC Conclusion

.

The NRC found no evidence and/or information to substantiate

this allegation.

!

41

I

.

.

-

i

.

19.

Allegation No. 19

.

!

a.

Allegation

Supervision of trade workers is inadequate and being performed

by unqualified individuals.

i

b.

NRC Investigation Findings *

!

During the course of this investigation, several construction

workers from various trades and crafts were interviewed privately

by NRC investigators.

During these interviews, selected workers

were asked their opinion not only of their own supervisors but

of other supervisors within their own craft.

The NRC noted

that the majority of workers believed their supervisors to be

qualified for their positions and in general providing an

!

adequate amount of supervision.

Although some workers did not

feel qualified or able to evaluate their supervisor's performance,

they did state that they did not have any problems in this area

at this time.

The NRC noted further that even in areas where

workers admitted to personal differences with their supervisors,

i

they still acknowledged their supervisor's ability to meet his

,

supervisory responsibility.

A random evaluation by the NRC of

various supervisor's qualification did not reveal any inadeca.cies.

!

1

In order to indirectly determine the adequacy of supervision on

site independent of workers interviews, NRC investigators

requested one of the contractors (COURTER) to provide an indi-

cation of the number supervisory and non-supervisory personnel

currently at the Shoreham site in construction related work

areas.

The NRC noted that the information provided indicated

that in the four construction areas reviewed (Radwaste, Reactor,

Instrumentation and Auxiliary / Yard Area), a supervisory individual

was provided for every 2.4 craft individuals.

Supervisory

personnel included Welding Department Supervisors, Deputy

Foremen, Area Foremen, General Foremen, Assistant Area Supervisors

and Area Supervisors.

If COURTER QC personnel were included,

there would be one (1) supervisor for every 1.9 workers.

The

NRC determined that this level of supervision appeared to be

commensurate with the extent of construction activities being

performed at the Shoreham site.

l

c.

NRC Conclusion

i

l

The NRC found no evidence and/or information to substantiate

this allegation.

"Due to the fact that no specific instances and/or individuals could be obtained

from the allegers, the NRC determined the validity of the allegation as it

pertained in general to the overall construction site.

42

--

.

- - .

.

.

.

-

-

-

. - . :

.

.

.

.

20.

Allegation No. 20

a.

Allegation

Qualifications and training of subcontractor personnel at the

Shoreham site is inadequate.

b.

NRC Investigation Findings

During the course of the investigation, several subcontractor

'

personnel were interviewed by the NRC.

During the course of

these interviews, individuals were informally questioned with

respect to their job responsibilities and past experience as

well as how various aspects of their particular jobs were

perfor:ned. The NRC noted that the workers interviewed appeared

to have a degree of knowledge (by experience and/or training)

commensurate with the job responsibilities given them, noting

also that this level of knowledge covered s wide area ranging

from the novice apprentice to the experienced journeyman.

Some

workers noted frustration in not being able to perform their

jobs as they were accustoraed due to the several QC checks which

'

were required and which would delay the job until the inspection

was performed and proper standards were met.

Although some

workers admitted not knowing all the standards in detail, they

]

stated that they had no problems in this area due to the fact

that their supervisors and QC inspectors would handle these

areas.

The NRC found no instance where a job requiring a high

degree of skill was performed by an individual not having the

qualifications and skills commensurate with the job.

The NRC also interviewed several QC inspectors and supervisory

personnel in a similar manner. as described above and were able

to determine that their knowledge of the appropriate standards

and procedural requirements was also commensurate with their

responsibilities.

No irregularities or deficiencies were

identified (see also Paragraph 17 of this section).

From the standpoint of the actual training of subcontractor

personnel by their own crafts, the NRC did not review the

actual apprenticeship program of the various crafts as this was

outside the purview of the NRC's responsibility.

The NRC did,

however, review the training provided by the subcontractors to

these individuals as it pertained to their activities and

responsibilities at the Shoreham site. The NRC reviewed a memo

by S&W to all subcontractors dated August 20, 1976 describing

the implementation of a site-wide training program, separate

43

_ _ _ _

_.

._

_

-

.

from other training requirements as described in the Field QC

Manual.

Each contractor was directed to provide a minimum

three (3) hour orientation program and to ensure that each new

employee attended the courses.

The NRC selected the Orientation

1

Manual for DRAVO and reviewed it in detail. No apparent defici-

encies were noted.

A check of an alphabetical listing of DRAVO

employees reflected the fact that all onsite employees were

recorded as having attending this particular training.

The NRC reviewed Orientation Manuals for other subcontractors

and determined that the DRAVO Manual was generally reflective

of all submitted manuals in terms of content and course design.

The NRC also conducted a random inspection of several of the

training records in various areas as given by various contractors.

For example, from April 26, 1977 through May 31, 1977 a one (1)

hour course was given several times on the installation and

inspection of wedge type anchor bolts which were installed in

concrete to secure various pipes and equipment. Approximately

660 workers were given this course over the time period stated

above.

Similar classes were noted in welding and other craft

activities on site.

The NRC was able to determine, therefore, that based on personnel

interviews and training records reviewed, that the training of

subcontractor personnel appeared to be adequate for their

duties at the Shoreham site.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

21.

Allegation No. 21

a.

Allegation

Workers who commenced the task of painting the inside of the

Reactor Primary Containment were not qualified.

It was further

alleged that an NRC inspection of worker qualifications resulted

in a majority of the workers being ordered off the job; however,

the substandard work that had been done to that point was

allowed to remain and was not inspected by the NRC inspector;

the remaining workers were ordered to complete the task on

overtime and on one occasion they worked a 30-hour shift while

on methedrine.

44

-.

.

.

--- _

._

.

-

.

.

b.

NRC Investigation Findings

NRC investigators noted that painting specifications, procedures

and records were reviewed, as well as an in progress inspection

performed, by an NRC inspector as documented in NRC Inspection

Report No. 50-322/79-20.

No items of noncompliance were identi-

fied by the NRC inspector and the performance of the work as

well as the QC inspection associated with it were considered to

be acceptable.

NRC investigators also reviewed all NRC inspection

reports for 1975 through 1979 and found no record of an NRC

inspector questioning painters qualifications at any time

during this period nor any report of painters being layed off

as a result of the NRC having questioned their qualifications.

The NRC interviewed S&W construction and QC personnel responsible

for painting as well as QC personnel working for KTA-TATOR

Associates, the consultant responsible for the inspection of

painting within the Suppression Poo1*.

The NRC noted that

during July through November of 1978, the painting of the

Suppression Pool required a large amount of overtime, with men

working 12-hour shifts, 7 days a week, using two (2) shifts per

day with a day off every two or three weeks.

The NRC could not

identify any 30-hour shifts worked at any time.

During this painting operation two (2) types of coating systems

were utilized in the suppression pool, an epoxy (K&L) system

above elevation 30 and an epoxy phenolic (Plasite) system t'elow

that elevation.

The NRC noted that painters were qualified

separately for each system in accordance with a proposed ASTM

qualification method.

Qualification for the Plasite system was

considerably more difficulty because of the coating system

itself as well as the use of a more complex qualification

panel.

A .large number of painters who had qualified on the K&L

system could not qualify on the Plasite system panel.

As the

work in other areas neared completion, the men who had qualified

for both system were retained while other painters with lesser

qualifications were layed off.

!

7 the Suppression Pool is the lhwei portion of the Reactor Primary Containment

45

- . _ . - - .

_

-

.

Individuals interviewed by the NRC stated that the most visible

effect of the long hours was a decrease in productivity. They

stated further that the effect on quality was not identifiable

and the reject rate was little if any greater.

The NRC noted

that the requi,? rents for *-ection and testing before, during

and after applicati;..

-3

-lficient to identify any decrease

in quality. During this investigation, NRC observation of

in progress painting showed no irregularities or deficiencies.

As mentioned earlier, 30-hour shifts could not be identified by

NRC investigators.

From the standpoint of the methedrine

allegedly used during this shift, the NRC found no indications

of drugs being used in this manner whether in the area of

painting or other construction areas covered in other aspects

of this investigation report.

Although the NRC was informed

that the labor problems engendered by the aforementioned layoffs

may have initiated this allegation, this matter was not pursued

inasmuch as problems were not identified with the painting

operation itself,

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

22.

Allegation No. 22

a.

Allegation

,

i

Tube support sheets in the condenser box were so misaligned

that titanium tubing which is supposed to fit loosely through

the support holes was often hammered or twisted to fit through

the sheets.

It was alleoed further that the damage was extensive

enough to cause

tit- to break with the possibility of a

radioactive spill.

b.

NRC Investigation Findings

The NRC noted that the " condenser box" or Main Surface Condenser

is not a safety-related unit, nor is it classified as an ASME

Code Vessel as the shell side is under vacuum.

The unit itself

is pre-assembled without the tubes, disassembled for shipment

to the site, where it is reassembled, welded and tubed.

This

particular condenser was designed and shop assembled by Inger-

soll-Rand (IR) in accordance with S&W Specification SH 1-6

dated June 16, 1969 and revised on August 15, 1969 and february

27, 1970.

The NRC noted that the original specification called

for SB111, Alloy CA706 (Cu-Ni) tubes but that the decign was

modified to improve water-side corrosion resistance Ly employing

ASTM:8338, Grade 2 welded titanium tubes.

I

46

-

-

-

--

. - . .

__

.

,

-

.

.

I

i

i

The NRC noted further that at the time of the material change

to the improved titanium tubes, assembly of the condenser was

i

'

!

partially completed to the Cu-Ni design.

Since the maximum

unsupported span for the titanium tubes was approximately 20%

,

less than for the Cu-Ni tubes, the total number of supports had

i

to be increased by approximately 25%.

Due to the fact that the

original tube support plates had been installed, the decreased

unsupported span was achieved by the installation of additional

i

partial tube support plates between those already installeo.

S&W stated that such a procedure was a standard solution for a

retubed or partially built unit.

This was confirmed by the

NRC.

'

The resultant tube support plate system was reported by S&W to

contain approximately 60-70% more tube support plates than

'

would normally be necessary for a completely new design with

some tube support plates as close as 18 inches apart.

The unit

was also designed to accommodate the MAN in-service (brush

type) cleaning system by extending the tubes a minimum of 3/8"

beyond the tube sheets.

The NRC noted that the unit was reassembled and fabricated in

accordance with S&W Specification SH1-223 with surveillance

inspection recorded for nine (9) attributes on the " Condenser

i

Tube Installation Inspection Checklist." The NRC noted further

j

that the increased number and decreased span of the tube support

plates was recogr.ized early as potentially producing a tube

insertion problem prior to the tubing of the unit.

This fact

was documented in meeting minutes on the subject " Erection of

the Surface Condenser" dated November 13, 1975 with LILCO, S&W,

IR and REGOR (the condenser erector) in attendance.

It was

recognized at this point that the tubes would be scratched

during the tubing operation and a maximum 0.004" scratch was

permitted.

S&W indicated that the 0.004" was acceptable based

on equivalency to the current SB333 NDE Calibration Standard

(Paragraph 10.2.1.2) of 0.004" and the UT Calibration Standard

in the tubing Purchase Order Specification SH1-299.

As indicated

in an S&W 1etter dated July 22, 1976, a series of calibration

comparison scratches were prepared for use during tuoing in

,

order to the able to determine acceptable scratch depths,

i

The NRC noted that as anticipated, there was a tube insertion

!

problem due to alignment difficulties.

This fact was acknowledged

in the " Condenser Tube Installation Inspection Checklist"

review which indicated that tubes with scratches exceeding

0.004" were removed from the condenser and scrapped.

A detailed

examination of these records indicated that the A-2 section of

,

47

..

.

_

__ .

. . .

.

.

..

.

.

- .

j

.

.

1

the condenser was the most difficult to tube. S&W stated that

the unit was tubed from the outlet side and consequently the

outlet tube ends extending into the water box for the A-2

!

section of the condenser were visually examined by NRC investi-

1

gators. Only minor inconsequential nicks were found at the ends

1

of these tubes. S&W stated that no tube ends had required

reforming for the insertion of the closely fitting rolling

,

tool, a further indication that the tube ends were not deformed

during tubing.

Tubes accessible for *sisual examination on the

shell side of the A-2 section of the condenser were also visually

inspected by the NRC investigators.

Only minor scratches were

observed and these appeared to be in the 0.002" dimensional

range.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation insofar as the tube insertion problem had been

anticipated and was performed in an acceptable manner without

any significant damage to the tubes. The NRC noted that a tube

failure would not normally result in a radioactive spill. The

condenser is under vacuum, and a leak would result in water

from Long Island Sound leaking into the condenser rather than

radioactive water leaking out.

23.

Allegation No. 23

a.

Allegation

Radiographic tests revealed that the longitudinal seam welds

for the <:endenser box were improperly done and when opened for

reworkinJ, it was found that the welds often contained dirt,

rubbish and weld rod stubs.

It was alleged further that these

conditions were sometimes discovered when the condenser had to

be cut open to correct misalignment problems.

b.

NRC Investigation Findir.gs

The NRC noted that the condenser is not part of any safety-re-

lated system and is not clasified as an ASME Code Vessel as the

shell side is under vacuum.

The unit was reassembled on site

by a LILCO constructor (REGOR) in accordance with S&W specifi-

cations and with S&W performing surveillance quality control.

The specification requirement for nondestructive examination of

the welds was for visual examination only.

48

..

- _ .

__

_-____

-_

__ ____ . - _ _ _ - -_

__

_ _ - _ _ _

-

.

.

The NRC was informed through discussions with the S&W engineer

responsible for condenser fabrication that as a result of the

Field QC questioning the achievement of full penetration welds,

"information only" radiographic and ultrasonic examinations of

the welds were performed.

The results of these examinations

confirmed the lack of full penetration welds.

Field QC . ported

that the radiographic examination identified welding technique

problems including indications of slag, porosity and lack of

,

fusion, but showed no indication of foreign objects such as

rubbish and weld rod stubs.

'

The NRC noted that an S&W 1etter (SNPS No. 3850) dated April

19, 1976 describes the welding deficiencies and S&W E&DCR No.

F-5104, dated November 5,1976 submits the welding nonconfor-

mances to Engineering for review. Resolution of the E&DCR

required that all accessible welds be air carbon arc back

gouged and back welded.

Inaccessible welds were strenghtened

by the welding of a stiffner to the face of the weld in order

to provide the equivalent weld strength.

Conditions of this

type were not found when misalignment problems were corrected

although in certain instances arc back gouging and back welding

were performed as part of the realignment of installed partial

tube support plates.

The NRC noted further that in the majority

,

of cases involved, the orientation of the welds would have

1

inhibited the inclusion of any foreign objects.

l

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

j

this allegation.

24.

Allegation No. 24

a.

Allegation ~

Misalignment of the condenser tube support required rewelding

so often that in some cases, the " mother material" around the

weld had to be cut out and replaced with a fresh substitute

section.

b.

NRC Investigation Findings

The classification, fabrication and field assembly of the

condenser have been described in Paragraph 22 of this section,

together with the tubing changes and the installation of addi-

tional partial tube support plates.

Discussions by the NRC

with S&W personnel and a letter dated October 14, 1975 by

Ingersoll-Rand (IR) the condenser fabricator to their site

erection supervisor, established that the partial tube support

49

l

-

-.

__ _

__

-______

.

.

.

plates do not provide any structural support for the condenser

box.

These support plates are installed in order to mitigate

the flow-induced vibration of the titanium condenser tubes.

The NRC noted that the partial tube support plates were cut

into pieces at the shop, reassembled in the field and installed

by welding them to support hangers which spanned the distance

between the original tube support plates.

The difficulty

encountered in the tube insertion revealed some misalignment

problems between the original tube support plates and the

additional partial tube support plates.

The partial tube

support plates were then cut from the support hangers, recut

into sections and reassembled in order to improve the alignment.

In order to facilitate the reassembly of the partial tube

support plates and its attachment to the support hangers, flat

plates, similar to stiffner/ backing straps were installed for

ease of welding.

The NRC noted that this practice is in ac-

cordance with standard practices for the industry.

The NRC concluded that it was the stiffner/ backing strap-like

plates that were mistaken as the " fresh substitute section"

referred to in the allegation.

The NRC noted no unusually

<

1arge amount of rewelding associated with the realignment of

i

the partial tube sheet support plates.

The flat plates were

installed to facilitate reinstallation, the work was approved

by engineering and inspected.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

25.

Allegation No. 25

a.

Allegation

Welds are marked by quality control before welding in order

that the best welders can be assigned to these jobs.

This is

done to assure that they pass examination.

Other welds are

made by lesser qualified workers and never inspected, implying

a degradation in overall quality and resultant safety factors

at the Shoreham site.

b.

NRC Investigation Findings

The NRC noted that welds in safety-relatad syarems are required

by the NRC to meet varying levels of qutlity basci on their

importance to the safety of the reactor. These welds are

50

-

-

__

_

.

_ . _ -

____

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

-

.

.

required to conform to the applicable codes and standards.

For

example, at the Shoreham site, all safety-related pipe welds

must meet ASME III and ASME IX Codes. The reactor coolant

pressure boundary must meet ASME III Code, Class 1 by the NRC

regulatory requirement.

Welds of lesser sensitivity are permitted

to meet ASME III Code, Classes 2 and 3, again, based on their

relative importance to safety.

The ASME III Code specifies what testing methods are to be used

for each class of weld; surface examinations for Class 3,

radiography for Class 2 and a combination of these for Class 1

welds.

The execution of these welds is controlled by an approved

Nuclear Quality Assurance Manual which directs the project

engineer to predetermine the inspection requirements for each

weld on the component checklist.

These checklists are posted

at each weld where work is being performed, providing an addi-

tional indication of the classification of the weld involved

further insuring that the more sensitive welds receive appro-

priate attention as required.

i

The NRC noted that welders working on safety-related pipe are

,

qualified to the ASME IX Code.

This code only recognizes

" qualified" or " unqualified" welders with no grading system

within the " qualified" classification. The assignment of the

more skilled welders to the higher classification of welds

would mean that the best craftsmen are working on the more

sensitive jobs, a process consistent with good practice and

generally enhancing the safety of the general public.

The NRC observed that if the inspection requirements were

performed on a random sampling basis rather than the system

described above, then the activities as alluded to by the

allegation might have the potential of affecting the overall

quality of the job by alerting individuals to those safety re-

lated welds to be " randomly selected". Since all safety-related

welds are inspected, this concern is not justified.

c.

NRC Conclusion

>

l

The NRC found no evidence and/or information to substantiate

this allegation.

26.

Allegation No. 26

a.

Turbine foundation bolts had been installed so far out of

alignment that it was necessary to chop out concrete around the

bolts, heat the bolts and bend them into a "Z"

shape in order

to fit them to the foundation plates.

l

51

---

-

_

_

-

.

-

. . . - .

. . .

.

____

_ _ .

. _ _ _ _ _ - _ _ _ _ _ _ _ _ . -_ ______

_ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ .

_ _ _ _ _

.

b.

NRC Investigation Findings

NRC investigators interviewed S&W construction personnel and GE

Installation and Service Engineering Department (GE I&SE)

employees who were responsible for the turbine installation.

The NRC also examined relevant GE procedures for the setting of

the foundation plates.

These procedures require that 2 to 3

inches at the surface of the concrete foundation be chipped out

prior to setting of the foundation plates in order to permit

packing of grout under the plates.

GE representatives explained

that the centerline of the turbine must be aligned within

hundredths of an inch. In order to meet this requirement the

bolts were installed within sleeves so that they are free to

move within the sleeve once the concrete has set. This is a

conventional method of setting anchor bolts.

The GE and S&W personnel who were responsible for establishing

the alignment and for setting the foundation plates all stated

that there had been no problem with the alignment of the bolts.

The only problem encountered had been the cleaning out the

space between the bolts and sleeves to permit adjusting the

]

bolt location within the sleeve.

.

i

NRC investigators examined slides showing the actual chipping

,

of the concrete in progress and the installation of the foundation

l

plates.

No significant alignment problems were identified in

these slides.

The NRC noted that the planned chipping away of

2 to 3 inches of concrete was an extensive operation and may

have created the impression of improper alignment which was

responsible for this allegation.

The chipping of the concrete

was performed by laborers who would not be fully cognizant of

<

the foundation plate installation procedure further leading to

the misunderstanding.

l

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

l

this allegation.

27.

Allegation No. 27

a.

Allegation

When concrete was placed in a cold joint on the 63' level of

the Reactor Primary Containment, a large amount of rubbish and

trash was permitted to remain within the form and the concrete

placed on top of it.

!

l

52

.-.

-

.-_

. -

- - _

.

_

_ - _ _ _ _

____ _ ________

.

.

.

b.

NRC Investigation Findings

NRC investigators reviewed concrete inspection records and N&D

reports of concrete placements within the reactor building.

There were no records of any cold joints in the Reactor Contain-

ment Wall but N&D No. 594 identified a cold joint in the shield

wall at the 63' level.

A preplacement inspection of the area

had been made and documented prior to the placement of additional

concrete and no irregularities were noted.

The NRC questioned several S&W QC inspectors and construction

engineers as well as DRAVO craft and supervisory personnel

concerning a cold joint in the Reactor Primary Containment

Wall.

Some of the individuals questioned mentioned one or two

'

'

cold joints, including the one in the shield wall but were

unanimous in stating that there were no cold joints in the

Primary Containment Wall at or near the 63' level.

The NRC noted that the requirements for preplacement inspections

prior to the placing of concrete above a cold joint are the

same as for any concrete placement.

A review of preplacement

records by the NRC and interviews with several S&W and craft

personnel identified cleanliness as an item of major importance

during preplacement inspections to the extent that craft personnel

were frequently delayed in placing the concrete in order to

satisfy QC cleanliness requirements.

The NRC acknowledged that

while it was probable that the alleger mistakenly identified

the shield wall cold joint as being in the primary containment

wall there was nothing to support his allegation with respect

to the lack of cleanliness.

c.

NRC Conclusion

The NRC found no evidence and/or information to substantiate

this allegation.

28. Allegation No. 28

a.

Allegation

'

__

Soil percolation test results were falsified and test results

were withheld from LILCO's submission of this information to

the NRC.

1

b.

NRC Investigation Findings

Due to the nonspecificity of this allegation, the NRC examined

two (2) areas which appeared to have been responsible for the

allegation being made.

With respect to the soil percolation

53

-

.

--.

. .

,

.

_

_.

.

_

_

_

_

. - _

_ -_

_

.

.

,

tests themselves, the NRC noted that these tests are utilized

!

to size and locate septic systems and are not used with respect

i

to any structural design considerations. The NRC interviewed

LILCO representatives with knowledge of this area and noted

that the installation of the Office and Service Building septic

system coincided with investigations into the potential for

,

soil liquifaction under the service water system.

On one

occasion during the soil liquifaction boring program, and

!

subsequent to a heavy rainfall, the building service engineer

'

asked the geotech engineer to take borings in the vicinity of

,

the septic tanks to find out why they would not drain.

Three

(3) borings were taken and given to the building service engineer,

'

but the logs /results of these borings were not included in the

liquification information for the FSAR.

The NRC determined

that this request to withhold the nonrelated information might

have been misconstrued as a willful attempt to withhold infor-

mation from the NRC.

Th: other area evaluated by the NRC investigation was the soil

liquifaction work itself.

The NRC noted that this matter was

covered in the licensee's FSAR (Section 2.5) and Appendices 2A,

2I, 2J, 2L and 2M thereof and basically involved tests to

obtain additional information on the soil conditions in the

j

vicinity of the various components making up the service water

i

system in order to determine the liquifaction potential in the

event of a design basis earthquake.

The various components

making up the service water system included the service water

piping between the Reactor Building and the Screenwell, the

Screenwell, the wingwalls adjacent to the Screenwell and the

Intake Canal itself. During the investigation, the NRC investi-

gators did not evaluate the results of these tests as this had

already been performed by the NRC as part of the overall licensing

process.

The NRC did note, howaver, that the licensee's response to

Request 324.5 of the FSAR provided LILCO's response (March

1976) as to why test boring data had been changed from the PSAR

results.

The investigators noted further that the changes

primarily appeared to be minor accidental omissions of data

which occurred when unnecessary data was intentionally removed.

The NRC investigators found no intentional attempt on the part

of the licensee to withhold information from the NRC, although

someone not familiar with the matter again may have misconstrued

it as such.

c.

NRC Conclusion

,

The NRC found no evidence and/or information to substantiate

this allegation.

54

.-

.

.

___

.-

.-

.

. . -

.

-- - .-

-

.

29.

Allegation No. 29

a.

Allegation

Welder performance qualification records were postdated for

welders who qualified after parforming welds for which they had

not been qualified.

b.

NRC Investigation Findings

NRC investigators reviewed 1300 COURTER and CO. Nonconformance

Reports (NRs) for indications of welding by improperly qualified

welders.

One (1) NR was identified which showed welds performed

by an unqualified welder. NR-837 dated May 22, 1979, stated

that in accordance with the Procedure Qualification Test Method

(PQTM), the welder was required to qualify to Performance Test

(PT) C-1 in order to weld a P-8 to P-1 material socket fillet

weld in accordance to Weld Procedure Specification (WPS) 08011AA.

The NR was dispositioned to " accept as is" on June 11, 1979

since the weldar was qualified to (PT) C-11 for welding P-8 to

P-8 material.

ASME Section IX, QW 310.5 permits a welder

i

qualified to weld P-8 to P-8 to also weld P-8 to P-1. Since

j

ASME Section IX is the authority for welder performance qualifi-

catiuns, this permitted the welder to be authorized to weld on

the P-8 to P-1 joint in question.

The exception to the PQTM

was authorized as a specific case and the welder was not added

to the list as having passed the (PT) C-1 test.

The NRC identified

no problem in the disposition of this NR.

NRC investigators also interviewed the UNICO individual responsi-

ble for maintaining the listing of qualified welders who stated

most emphatically that there had not been any postdating of

welder performance qualifications.

Although stating that an

authorized mechanism existed for post qualifying a welder in

accordance with an E&DCR*, that this mechanism had never been

utilized at the Shoreham site and in any event would not involve

postdating any existing records.

To do so, she stated, would

require (in accordance with QAP-7.2) postdating and signing

authorizations on five separate documents prior to inclusion on

the qualified welders list and then the postdating of the

qualified welders list itself. The NRC noted that such a::tions

would be easily noticed if attempted.

c.

NRC Conclusion

The NRC found no evidence and/or information to support this

allegation.

^This mechanism is different from the disposition of the Courter NR as described

earlier.

In this later case, the welder would have to be actually requalified

on the weld type in question and if he could not be, the weld would be removed

from the system and performed by a qualified welder.

55

- . .

,

_ _ _

_

_____ _ ________ __ _

.

30.

Allegation No. 30

a.

Allegation

Pressure was applied to construction workers by LILCO, its

subcontractor and/or related construction unions in order to

prevent and/or discourage workers from coming forth to identify

construction defects and/or irregularities to the NRC.

b.

NRC Findings

In order to determine the validity of the allegation, NRC

investigators provided several pathways by which current or

former construction workers could contact the NRC with infor-

mation in this regard specifically (i.e. , intimidation) or or

with respect to construction defects in general.

The results

of these efforts are reviewed below.

1)

Public Notices

From January 3, 1980 through the end of the investigation

on site on March 12, 1980 (a period of 70 days) notices

were placed at several frequented locations at the Shoreham

site. This fact was confirmed by the NRC Resident Inspector

and NRC investigators on site throughout the course of the

investigation. A sample of this notice has been attached

as Exhibit B of this report.

The notice provided a minimum

of three (3) points of contact with the NRC, one of which

was manned on a 24-hour basis.

The 24-hour number was

also made public via a local newspaper, covering therefore,

off-site and/or former employees still remaining in the

area.

In each case, full confidentiality was offered and

workers had the option to call anonymously with their

concerns if they so desired.

During the 70 day period that this notice was published,

the NRC received two (2) phone calls.

One of the phone

calls was from a construction worker at the site who

stated that he had worked at other non-nuclear power

plants and that by comparison, Shoreham was "over-designed"

and " super-safe".

The other caller was a member of the

general public who had concerns about nuclear power in

general and specifically Shoreham because he lived in the

area of the plant.

Although his concerns were addressed,

he provided no information related to a construction

defect at the Shoreham site.

56.

'

.-

.

..

._,

.


. ..

.

- - - .

.- -

( ._

_

__

_

_ _ - _ - _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

ii)

Interviews of Construction Workers On-Site

During the course of the investigation, several workers

were interviewed.

All of the workers were interviewed in

private, some during the investigation of the other al-

legations, some specifically selected at random in order

to determine the validity of this particular allegation.

In the latter case, site representatives for various major

subcontractors on site were contacted by the NRC and asked

to provide a list of all current employees to NRC investi-

gators.

The investigators then selected at random a

sampling of carpenters, laborers, masens, welders, electri-

cians, boilermakers, teamsters, mi11 wrights, insulators,

steamfitters, sheetmetal workers, weld rod control clerks

and QC inspectors.

Through the sampling process, shop

stewards as well as workers were also selected. Each

)

individual was (a) interviewed in private, (b) informed of

confidentiality, (c) provided with information for a

callback to the NRC if desired and (d) was allowed to

express his concerns in any area (i.e., construction

defects) in addition to the specific area of intimidation

as stated in the allegation.

Every individual interviewed informed the NRC that none of

the workers had teen directly or indirectly intimidated by

any individual, union, contractor or licensee, in an

attempt to prevent taem from coming forth to identify

construction defects and/or irregularities to the NRC.

Each individual further informed the NRC that they had

neither observed nor heard of such actions being executed

on any of their friends or other, employees not directly

questioned.

The NRC did not receive any callbacks at

other' times from the individuals interviewed in this

regard.

Severe

of the workers interviewed volunteered statements

to the

C to the contrary of this allegation stating that

if anything, the opposite of the allegation was true.

Some of the statements made are included as follows:

Steamfitter A stated: "We never took a shortcut. ~his is a

Class A job.

Our relationship with LILC0 is good and they

cooperate fully with our concerns."

Mi11 wright A stated: "Our local is very conscientious with

nuclear energy.

This (RCI) is the most conscientious

outfit I've worked for."

57

.

,

_

.

,

,

w._

,

-,-.- - -

i

.

.

Boilermaker A stated:

"The union would be very supportive

of our complaints."

Boilermaker B stated:

"We've done our job right to the

specs."

Boilermaker C stated:

"If we ever found a problem it

would be taken care of. They (LILCO) check out everything."

Electrician A stated:

"Just the opposite.

Everyone is

concerned with QC.

I've seen some of the better workmanship

in the trade on this site."

'

Electrician 8 stated:

"I haven't seen any problems in 5

years."

Electrician C stated:

"No threats whatsoever. They (union

and contractors) promote safety, especially on a nuclear

job."

Electrician D stated:

"We are told to bring up safety-re-

lated issues.

Everyone is doing a Class 1 job.

We are

all going to suffer if something happens (when the plant

is operational) so we are all supersafe about our jobs."

Millwright D stated:

"Just the opposite. We are all told

to look for problems.

I haven't seen any so I don't know

how they'll handle it."

Boilermaker D stated:

"I would go to the NRC without

,

hesitation.

I live in the area and I wouldn't want anything

'

to go wrong."

Sheetmetal Worker A stated:

"They (foreman) tell us to

report everything suspicious to them.

I wouldn't be

afraid to speak up."

Sheetmetal Worker B stated:

"The company here (LILCO) is

far superior to any other company I've ever worked for."

Sheetmetal Worker C stated:

"Noone is afraid to come

forward. In my opinion the job is being done better than

it has to be."

Sheetmetal Worker D stated:

"Something like that (threats)

would get around fast, therefore no way they would do it.

This job is going slow because all the safety checks you

i

have to go through."

58

r

.

.

Sheetmetal Worker F stated:

"I'm a shop steward. We watch

who we send out there because it is a nuclear job.

If

they don't want to give quality work, they won't be kept

here.

I'm a shop steward and I have no fear of coming

forth to the NRC."

Carpenter B stated: "I never saw a better job in my life

and I've been in concrete for 26 years."

Mason A stated:

"This is one of the best built jobs I've

worked on."

Mason B stated:

"I've been encouraged to bring problems

to management. There would be more white hats (QC, S&W,

NRC) than we knew what to do with. The QC here is tough."

iii)

Resident Inspector

NRC investigators were informed by the NRC Resident Inspector

that during his entire assignment at the Shoreham site

(from October 1, 1979) even prior to the initiation of the

investigation, no workers at the site (licensee or contractor)

had ever approached him with any form of problem relative

,

to construction defects and/or pressure not to present

their concerns to the NRC.

The Resident Inspector stated

that he had made several tours of the site during this

time, not only during normal working hours, but also

during off-hours, weekends and holidays, and that to date

he had yet to be approached in this regard.

iv) Protective Agreement

Attorneys for various allegers claimed that several other

workers wished to present information on construction

defects but would not do so without a formal protective

agreement provided by the NRC in order to ensure their

confidentiality.

A draft of this agreement was presented

by the attorneys to NRC investgators on December 17, 1979.

This agreement was forwarded to NRC Headquarters for legal

review and subsequently sent to the allegers' attorneys

for implementation.

When no new workers came forth even

with the protective agreement, the NRC investigators

inquired as to the reason.

The attorneys stated that they

(attorneys) had decided not to risk the lives of these

'

additional allegers due to potential threats to their jobs

and/or persons.

)

l

!

!

59

T

.-

.

The NRC could not reconcile this statement insofar as it had

noted in i), 11) and 111) above that no evidence of any threats

whatsoever could be substantiated during this investigation.

c.

NRC Conclusion

The NRC found no evidence and/or information that would sub-

stantiate this allegation.

l

i

l

)

.

60

-_.

- - . _ - - -

.

_ _ _

_

. ..

_

- _ _ _

_ - - - _ _ _ _ _ _

_ . - .

.

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

o

.

IV. EXHIBITS

Exhibit A: Referenced Codes, Specifications and Procedores

ACI 301

Specifications for Structural Concrete for Buildings

ACI 306

Recommended Practice for Cold Weather Concrete

ACI 347

Recommended Practice fo Concrete Formwork

ASTM (Draft 14)

Proposed Manual of Coating Work for Light Water Nuclear

Power Plant Primary Containment Facilities (Subcommittee

D-01.43)

SH1-64

Specifications for Substructure Work

SH1-354

Specification for Concrete Work

,

SH1-228

Protective Coatings Within the Primary Reactor Con-

tainment Structure

SH1-228.700

Procedure for Applying Protective Coatings Within the

Suppression Chamber

W 300-Section A

General Procedure for Cadwelding of Reinforcing Steel

QC-10.3

Field Quality Control Procedure - Concrete Quality

Control

QC-14.2

Field Quality Control Procedure - Cadwelding

QC1-10.3.012

Quality Control Instruction - FQC Preplacement Pour

Card

QCl-10.3.013

Quality Control Instruction - Preplacement Inspection

.

QC1-14.2.001

Cadweld Data Analysis

61

=

(

. - -

._.

. ..

. .

. - - - .

.

- - - -

--

-

--;

<

  1. e,M N

EXHIBIT B

  1. o,

UNITED STATES

8

NUCLEAR REGULATORY COMMISSION

,

o

D

j

REGION I

$

631 PARK AVENUE

4,***** ,@g

KING OF PRUSSIA, PENNSYLVANIA 19408

NOTICE

The U. S. Nuclear Regulatory Commission is conducting an investigation

into alleged improper construction practices which may have been

undertaken at the Shoreham site. Any worker having information

concerning these al*iegations or other concerns is urged to contact

the NRC (collect) at 215-337-5000.

NRC investigators will be on site

from February 11-15,1980*and may be contacted through the NRC Resicent

Inspector (extension 83-221) or at the Holiday Inn at Riverhead, New

York, (516-369-2200).

The NRC wf'll maintain the confidentiality of

the source of any information received during this investigation and

in any resultant reports.

  • new notices were posted prior to each on-site visit and the appropriate

,

dates inserted at this location