Advises That Class III Fee Has Been Waived Re 791222 Application for Tech Spec Change Concerning Fire Protection. Refund Is Being Processed
ML19323C491
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/02/1980
From: Miller W
NRC OFFICE OF ADMINISTRATION (ADM)
To: Crouse R
TOLEDO EDISON CO.
References
NUDOCS 8005160008
Download: ML19323C491 (1)


Text

-

N a na v9'

      • ('

UNITED STATES 80082do00

[

.gj' g NUCLEAR REGULATORY COMMISSION gj;.g j

WASH WGTON,0. C. 20555 T

l

+,, e,e,f

'l MAY 2 1980 DOCKET fi0. 50-346 Toledo Edison ';ompany ATTri: Mr. Richard P. Crouse Vice P"esident - fleclear Edison Plaza 300 Madison Avenue Toledo, Ohio 43652 Gentlemen:

The Commission's Office of the Controller has been authorized to refund the Class III ($4,000) fee for Davis-Besse fluclear Power Station Unit I which was sent with your application dated December 22, 1979.

The Commission has determined that a waiver of the license amendment fee for this technical specification change relating to fire protection is appropriate.

The refund is being processed and will be sent to you as soon as possible.

Sincerely,

  • lAo m'JLO William 0. Miller, Chief License Fee Management Branch Office of Administration Q

.....