Text
-
600514000 9
U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORGMENT REGION IV Report No.
99900330/79-01 Program No. 51400 Company:
Westinghouse Electric Corporation Switchgear Division 700 Braddock Avenue East Pittsburgh, Pennsylvania 15112 Inspection Conducted: November 27-29, 1979 Inspector k.
/ /f
[
)]p J. R. Agee, Contractor Inspector
/ Dat6 ComponentsSection II Vendor Inspection Branch Approved by:
2d
/'2//W77 D. M. Hunnicutt, Chief
/Dats ComponentsSection II 1
Vendor Inspection Branch Summary Inspection on November 27-29, 1979 (99900330/79-01)
Areas Inspected:
Implementation of 10 CFR 50, Appendix B, criteria and applicable codes and standards including:
action on previous inspection findings; QA Program Review; Design Review / Design Tests / Production Tests; Quality Assurance Records; and Control of Measuring and Test Equipment. The inspection involved twenty-four (24) inspector-hours on site by one (1) NRC inspector.
Results:
In the five (5) areas inspected no deviations or unresolved items were identified as in four (4) areas. The deviation is described as follows:
Deviation: Quality Assurance Records-QA Manual procedures do not address requirements for QA records for Class IE, safety-related products (See Notice of Deviation).
F 2
DETAILS SECTION A.
Persons Contacted D. A. Acosta - Quality Control Engineering Manager A. P. Coloiaco - Development Engineering Section Manager L. H. Horvat - Test Foreman Kozlovic - Senior Engineer, Design and Development L. Magarac - Quality Control Supervisor
- H. L. Miller - Assistant Manager of Quality Assurance B. G. Patterson - Quality Control and Test Manager
- D. M. Sauter - Division Manager
- H. I. Stahr - Manager of Quality Assurance J. Subasic - Instrument Laboratory Foreman
- Attended exit interview.
B.
Action on Previous Inspection Findings 1.
(Closed) Deviation (Inspection Report 78-02): QA Manual did not commit to meet applicable requirements to 10 CFR 50, Appendix B.
The inspector verified the QA Manual, Revision 78-01, dated August 1978, was revised to display commitment to 10 CFR 50, Appendix B, and applicable ANSI standards.
2.
(Closed) Deviation (Inspection Report 78-02): QA Manual had not been reviewed or revised since February 20, 1974.
The inspector verified the QA Manual was revised August 1978.
3.
(Closed) Deviation (Inspection Report 78-02):
Certain departments' personnel (example: purchasing and engineering) had not received QA indoctrination and training.
The inspector verified that a QA indoc-trination and training program had been initiated for personnel whose activities affect quality.
Training sessions were conducted September 20, 1978, and September and October 1979, concerning QA program overview including: 10 CFR 50 Appendix B; ANSI N45.2; Part 21; IEEE 323/344; and switchgear program for qualification of Class IE nuclear safety related switchgear. Personnel in attendance were from the following functional groups:
sales; low and medium voltage switchgear engineering; Engine-ering; switchgear assembly; purchasing; customer services; and AST Engineering Services.
4 (Closed) Deviation (Inspection Report 78-02): An audit program had not been implemented nor had audit records been maintained in the files of the Manager of Reliability Control. The inspector verified that an audit prograr had been implemented and audits records are being maintained in the files of the Quality Assurance Manager.
3 5.
(Closed) Deviation (Inspection Report 78-02): Provisions had not been Onplemented for source evaluation and inspections at contractor or subcontractor sources. The inspector verified that a program had been implemented for source inspection and evaluation of selected suppliers or subcontractors at designated intervals dependent upon the importance, complexity, and quantity of the product or services.
6.
(Closed) Deviation (Inspection Report 78-02): Quality assurance requirements were not transmitted to certain suppliers.
The inspector verified that procedures had been implemented requiring compliance to applicable portions of 10 CFR 50 Appendix B and ANSI N45.2 by suppliers of special purchases and critical items for Class IE. equipment.
C.
QA Program Review 1.
Objectives The objectives of this area of the inspection were to:
Discuss with QA and senior management personnel the status of the a.
QA Manual and organizational structure.
b.
Determine that status and location of production of Cla'ss IE products.
Discuss the status of QA procedures and manuals that have been c.
compiled and implemented since the last NRC inspection.
2.
Method of Accomplishment The preceding objectives were accomplished by:
Discussions with QA management concerning the QA Manual which a.
previously had failed to address such areas as compliance to 10 CFR 50 Appendix B and ANSI N45.2 that had been imposed as QA requirements by customers for Class IE switchgear and ci.cuit breakers.
b.
Review of the QA Manual Section 2.0, Organization, dated August 1973.
Review of the Purchasing Manual dated September 11, 1978, which c.
previously had not been implemented.
3.
Findings a.
Deviation None.
4 b.
Unresolved Items None.
c.
Comments (1) The Switchgear Division manufactures two (2) major types of products: Switchgear assemblies that are designed on a
" Customer Order" basis wherein each assembly is customized to the number and arrangement of standard components to customer order and specifications, and switchgear components that are standard devices, such as, circuit breakers, power fuses, con-trol switches, etc.
Class 1E products are in the first category with the switchgear assemblies and low voltage cir-cuit breakers being built in East Pittsburgh, Pennsylvania, and the medium voltage circuit breakers being built in Puerto Rico.
(2) The document No. NQD-351-00, Westinghouse Switchgear Division Program for the Control of Bought Outside Components used in Class lE Equipment dated November 1979 is being implemented as a supplement to the Purchasing Manual for procurement of products to be used in Class lE equipment.
D.
Design Review / Design Tests / Production Tests 1.
Objectives The objectives of this area of the inspection were to verify that:
Procedures have been established for performing design tests a.
and production tests on Class 1E equipment that are consistent with applicable national codes and standards.
b.
Established test procedures are being implemented for Class IE equipment.
Service conditions identified in procurement documents are satis-c.
fied by equipment qualifications.
d.
Test sequences identified in the qualification test procedures satisfy the test sequence requirements identified in IEEE stand-ard 323-1974.
Sub-components that determine the life of the equipment have been e.
adequately qualification tested or analyzed.
f.
Production test procedures are consistent with applicable national i
standards, test criteria.
l i
5 g.
Design review of Class IE products are subject to design review by another engineer acting independently who signs all job original drawings.
h.
Verify that production orders (manufacturing / shop orders) are completed, fully stamped and signed off by quality control inspectors at completion of final production tests.
2.
Method of Accomplishment The preceding objectives were accomplished by:
Discussions with the engineering manager and development engine-a.
ering personnel regarding progress in the development and quali-fication of Switchgear Devision generic switchgear for Class 1E applications.
b.
Verifying that qualification testing of generic switchgear and its safety related components has been completed and the final qualification reports will be completed and approved by the second quarter of 1980.
Current documentation concerning this qualification iest program includes the following:
(1) Seismic Simulation Test Report No. 43443-J, June 2, 1977 (this is the test facility report).
(2) Westinghouse Document No. NQD-024-00, Switchgear Addamblies for Class IE A.71ications, Projected Qualified Life Rating 1
for Type DS Bast-Breaker, August 29, 1977, which contains the conclusion that states in part,
. The basic breaker will satisfactorily perform its intended a function for at least 40 years with routine inspection and a
ca.ntenance. During the projected 40 year period, the con-metallic materials, which may age, will retain their important character-istic sufficiently to prevent a common mode failure during a design basis earthquake; and, during a seismic event, the unit will prop-i erly perform its function within the limits described in the seismic report.
"Therefore, it may be reasonably concluded that the basic breaker has a projected qualified life of 40 years within the limits of the operational life specifications."
c.
Verifying by reference to customer purchase orders reviewed f.a previous inspections that service conditions, codes and standards referenced in the purchase orders and related specifications had been satisfied by the qualification tests conducted.
1 6
d.
Review of Quality Control Instruction (CQI) No. 106, Air Circuit Breaker type 150 DHP, November 10, 1978.
Verified by inspection of assembly and production line activities that assembly of the low voltage circuit breaker inspected was assembled in compliance with CQI No. 106.
Review of Electrical - Insulation - Test - Specification Switch-e.
gear, Test Specification for Type DHP Air Circuit Breakers, T-Spec. No. 710030, March 20, 1979.
Verified by inspection of production testing of a low voltage circuit breaker that production testing of this circuit breaker was completed in compliance with T-Spac. No. 710030.
f.
Review of CQI No.134, Inspection of DHP Metalclad Switchgear, November 10, 1978. Verified by inspection of production as-mbly that metalclad switchgear is assembled in compliance with t CQI.
g.
Review of Test Specification Switchgear, Commercial Test Specifi-cation for Low Voltage Metal Enclosed Switchgear, T-Spec. 347880-F, July 25 1969. Verified by inspection of the test / checkout of a low voltage switchgear assembly that production line test of low voltage switchgear is completed in compliance with this test specification.
h.
Ver.1fied the above test specifications meet the applicable test criteria of ANSI standards C37.09 and C37.20 for the testing of circuit breakers and switchgear assemblies, respectively.
i.
Verified that approved checklists were punched, stamped or ini-tiated by QC ic.spectors for each major step in the assembly and test of low voltage circuit breakers and switchgear assemblies and that typical manufacturing instructions (MI's) for these pro-ducts were signed off before release of the products for packaging and shipment.
3.
Findings Within this area of the inspection, no deviations or unresolved items were identified.
E.
Quality Assurance Records 1.
Objectives The objectives of this area of the inspection were to verify that:
a.
Sufficient records are saintained to furnish evidence of activities affecting quality.
4
7 b.
Records include evidence of design and qualification of Class IE products, production and inspection records, certificates of con-formance.
c.
Records are consistent with applicable regulatory requirements concerning record retention, duration, location and assigned responsibility.
2.
Method of Accomplishment The preceding objectives were accomplished by:
Review of the QA Manual for evidence of requirements for storage a.
and retention of records concerning Class IE products.
b.
Examination of the three-hour fire-rated storage vault for retention of original documents concerning design and quali-fication testing for Class 1E products.
Examination of the areas for storage o:..iginal tracings c.
(drawings), aperture cards, and manufacturing records.
3.
Findings a.
Deviation See Notice of Deviation b.
Unresolved Items None.
F.
Control of Measuring and Test Equipment 1.
Objectives The objectives of this area of the inspection were to verify that i
s.
A system has been established and is saintained to assure that tools, gages, instruments and other measuring devices used in activities affecting quality are properly controlled, calibrated and adjusted at specified periods to maintain accuracy within specified limits.
b.
Calibration records are kept for each instrument and that these records include the following infor=ation:
(1) Purchase date and calibration history.
(2) Accuracy required and calibration results.
l (3)
Location for use.
8 (4) Present calibration interval and date due.
(5) All maintenance and repair details.
(6) Person or agency performing all calibration.
(7) Serial number or identification of each standard used to perform the calibration.
(8) Number or name of the calibration procedure.
(9) Envir,nmental conditions used during calibration.
(10) Equipmen: recall schedules.
2.
Method of Accomplishment The preceding objectives were accomplished by:
Review of the Quality Assurance Manual, Sub-Section 7.7, Inspection a.
Equipment Control.
b.
Review of QCI-7000, Instrument Calibration Control, and QC1-7002, Automatic Sensor Tester Programming.
Verification of calibration status of randomly selected instru-c.
ments, examples:
0.D. micrometers, voltmeters, AC amplifiers, surface plates, master breaker cells and gages.
d.
Interviews with cognizant technical and management personnel in the calibration laboratory.
Review of the Master List that establishes frequencies of cali-e.
bra tion.
f.
Examination of the separate calibration facilities in the cali-bration laboratory for the calibration of various types of instruments such as mechanical, electrical AC, electrical DC, and temperature sensors.
3.
Findings Within this area of the inspection, no deviations or unresolved items were identified.
i i
v 9
G.
Exit Interview The inspector met with those individuals identified in paragraph A above at the conclusion of the inspection on November 29, 1979, at the East Pittsburgh facility.
In this meeting the inspector summarized the scope and the findings of the inspection including:
1.
Action on previous inspection findings.
2.
QA Program Review.
3.
Design Review / Design Tests / Production Tests.
4.
Quality Assurance Records.
5.
Control of Measuring and Test Equipment.
Subsequent to the exit meeting Mr. D. H. Sauter, Divisica Manager, was apprised by telephone of the scope and findings of the inspection since he wau unable to attend the exit meeting at the East Pittsburgh facility.
Man,agement adknowledged the statements made by the inspector.