Forwards IE Insp Rept 50-271/80-02 on 800205-08.No Noncompliance Noted
ML19323B399
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 03/28/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Rich Smith
VERMONT YANKEE NUCLEAR POWER CORP.
Shared Package
ML19323B400 List:
References
NUDOCS 8005120325
Download: ML19323B399 (2)


See also: IR 05000271/1980002

Text

8005120 h

.

.

UNITED STATES

p Kacq,

o

NUCLEAR REGULATORY COMMISSION

j

R EGION I

O

'- -

'..o$

631 PARK AVENUE

5

'M

g

KING OF PRUSSI A, PENNSYt.V ANIA 19406

.....

MAR 2 8 1980

Docket No. 50-271

Vermont Yankee Nuclear Power Corporation

ATTN: Mr. Robert L. Smith

Licensing Engineer

25 Research Drive

Westborough, Massachusetts 01581

Gentlemen:

Subject:

Inspection Report No. 50-271/80-02

This refers to the inspection conducted by Mr. W. Raymond of this offie on

February 5-8, 1980 at Vermont Yankee Nuclear Power Plant, Vernon, Vermoit

of activities authorized by NRC License No. DPR-28 and to the discussic.1s

of our findings held by Mr. Raymond with Mr. W. Murphy and other members of

your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within these areas, the inspection consistu of selective examinations of

procedures and representative records, interviews with perstonel, and

observations by the inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If

this report contains any information that you (or your contractor) believe

to be proprietary, it is necessary that you make a written application

within 20 days to this office to withhold such information from public

disclosure. Any such application must be accompanied by an affidavit

execute d by the owner of the information, which identifies the document or

part sought to be withheld, and which contains a statement of reasons which

addresses with specificity the items which will be considered by the Commission

as listed in subparagraph (b) (4) of Section 2.790.

The information sought

to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document

Room.

.

.

.

MAR 2 8 19B0

Vermont Yankee Nuclear Power Corporation

2

No reply to this letter is required; however, if you should have any

questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

c

-_,_D_

E on J. Brunner, Chief

actor Operations and Nuclear

Support Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-271/80-02

cc w/ encl:

Mr. Warren P. Murphy, Plant Superintendent

Ms. J. Abbey, Technical Secretary

Mr. J. E. Griffin, President

.