Forwards IE Insp Rept 50-483/80-03 on 800114-31 & Notice of Violation
ML19323B083
Person / Time
Site: Callaway 
Issue date: 03/20/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Bryan J
UNION ELECTRIC CO.
Shared Package
ML19323B084 List:
References
NUDOCS 8005090235
Download: ML19323B083 (2)


See also: IR 05000483/1980003

Text

r

8005090g M

TIC

>

UNITED STATES

<

[

NUCLEAR REGULATORY COMMISSION

s, ,

g

t

REGION lli

-

o,

[

799 ROOSEVELT ROAD

i

'

% . . . . . g

GLEN ELL YN. ILLINolS 60137

pg10 W

'

Docket No. 50-483

Union Electric Company

ATTN:

Mr. John K. Bryan

Vice President - Nuclear

Post Office Box 149

St. Louis, MO 63166

Gentlemen:

This refers to the inspection conducted by Mr. W. A. Hansen of this

office during the period of January 14 - January 31, 1980, of activities

at the Callaway, Unit 1, construction site authorized by NRC Construction

Permit No. CPPR-139 and to the discussion of our findings with Mr. Weber

and others of the Callaway staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of

a selettive examination of procedures and representative records, obser-

vations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in non-

compliance with NRC requirements, as described in the enclosed Appendix A.

This notice is sent to you purst. ant to the provisions of Section 2.201 of

the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions. Section 2.201 requires you to submit to this office within thirty

days of your receipt of this notice a written statement or explanation "

reply, including for each item of noncompliance:

(1) corrective action

taken and the results achieved; (2) corrective action to be taken to

avoid further noncompliance; and (3) the date when full compliance will

be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy cf this letter, the

enclosures, and your response to this letter will be placed in the NRC's

Public Document Room, except as follows.

If the enclosures contain

information that you or your contractors believe to be proprietary, you

must apply in writing to this office, within twenty days of your receipt

of this letter, to withhold such information from public disclosure.

.

Union Electric Company

,2 -

MAR 2 0 ME0

The application must include a full statement of the reasons for-which

the information is considered proprietary, and should be prepared so

that proprietary information identified in the application is contained

in an enclosure to the application.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

1

At'$

G. Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-483/80-03

cc w/ enc 1:

Mr. W. H. Weber, Manager

Nuclear Construction

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

,

TIC

Regions 1 & IV

Ms. K. Drey

Mr. Ronald Fluegge, Utility

Division, Missouri Public

Service Commission

!

l

!

i