,s Georgia Power Company 230 Peachtree S'Jeet Post Offics Box 4545 dp Atlanta, Georgia 30302 8((
Telephons 404 522-6060 90 97" Georgia Power Powev Gewredon Department
_' q.
yp q.
y tre sour?nn mtrc sniern 0032 March 26, 1980 U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement
REFERENCE:
Region II - Suite 3100 RII: JPO 101 Marietta Street, NW
$0-321/50-366 Atlanta, Georgia 30303 I&E Bulletin 79-27 Attention:
Mr. James P. O'Reilly Gentlemen:
In our letter dated February 28, 1980, we provided a response to I&E Bulletin 79-27, " Loss of Non-Class 1E Instrumentation and Control Power System Bus During Operation". Item # two of the bulletin requires the preparation or review of certain emergency procedures.
In our response we stated that our study of procedures would be completed on or about January 31, 1981. Having learned that this schedule is unacceptable to the I&E staff, we are greatly expediting this effort. We are now scheduling the review of emergency procedures to be complete by June 26, 1980.
If you have any further questions in this regard, please contact my office.
Sincerely,
[f @e e, f
[
W. A. Widner Vice President and General Manager Nuclear Generation LTG/mb xc: Director of the Office of Inspection and Enforcement Director of the Division of Operating Reactors, Office of Nuclear Reactor Regulation t
O' MoE CDPy,J.i
~